Bill of Quantities/Materials: Quantity Total Amount Total Unit Cost Item Unit Cost
Bill of Quantities/Materials: Quantity Total Amount Total Unit Cost Item Unit Cost
Item
Quantity
A. PRE CONSTRUCTION
1.) Mobilization / Demobilization
2.) Clearing and Grabbing
4.) Temfacil
Unit Cost
Labor
1 lot
1 lot
1 lot
Materials
Total
Unit Cost
Total Amount
PhP 50,000.00
PhP 50,000.00
PhP 50,000.00
PhP 50,000.00
PhP 50,000.00
PhP 50,000.00
PhP 50,000.00
PhP 50,000.00
PhP 50,000.00
B. CONSTRUCTION
1.) Civil Works / RC
a. Concrete
b. Gravel Bedding
112.44 cu.m.
9.60 cu.m.
250.00 /cu.m.
120.00 /cu.m.
4500.00 /cu.m.
1100.00 /cu.m.
PhP 4,750.00
PhP 1,220.00
PhP 534,068.63
PhP 11,715.05
5060.32 kg
2294.48 kg
13163.65 kg
5.00 /kg
5.00 /kg
5.00 /kg
35.00 /kg
35.00 /kg
35.00 /kg
PhP 40.00
PhP 40.00
PhP 40.00
PhP 202,412.88
PhP 91,779.20
PhP 526,545.90
962.83 sq.m.
155.00 /sq.m.
990.00 /sq.m.
PhP 1,145.00
PhP 1,102,435.77
710.59 sq.m.
433.55 l.m.
417.99 l.m.
1421.17 sq.m.
100.00 /sq.m.
120.00 /l.m.
120.00 /l.m.
85.00 /sq.m.
250.00 /sq.m.
450.00 /l.m.
450.00 /l.m.
250.00 /sq.m.
PhP 350.00
PhP 570.00
PhP 570.00
PhP 335.00
PhP 248,704.75
PhP 247,123.50
PhP 238,254.59
PhP 476,091.95
1411.37 l.m.
2179.76 l.m.
300.00 /l.m.
300.00 /l.m.
450.00 /l.m.
450.00 /l.m.
PhP 750.00
PhP 750.00
PhP 1,058,529.00
PhP 1,634,817.00
(Grade 40)
(Grade 40)
(Grade 40)
PhP 6,522,478.21
Sub-Total (A)
1 lot
PhP 100,000.00
PhP 100,000.00
PhP 100,000.00
PhP 100,000.00
Sub-Total (B)
Indirect cost
PhP 652,247.82
Profit (10% of A)
PhP 652,247.82
Sub-Total (C)
PhP 7,274,726.03