ATTENTION: ALL TECHNICAL OFFICERS

BRIEF HANDING OVER NOTE


Please take note of the following projects and continue with them. Kindly
liaise with Leonard Koblavie for more clarification.

PROJECTS UNDERWAY
1. LABORATORY WORKS FOR IDL KNUST (moistures and grading samples are in
the oven to be worked on; other tests have not yet been started; see test
schedule for details)
2. LABORATORY WORKS FOR IDL TAKORADI (moistures and grading samples are
in the oven to be worked on; other tests have not yet been started; see test
schedule for details)
3. LABORATORY WORKS ON FILL MATERIAL FOR KAASE WOODEN BRIDGE REPAIR
WORKS (compaction test completed on raw sample. Index property tests yet
to be carried out)
4. LABORATORY WORKS ON CLAY MATERIALS FROM MATERIALS DIVISION
(contact Leonard for details)

EXPECTED PROJECT
1. STABILIZATION OF ROAD MATTERIAL FOR NMSi DODOWA

Thank you.