Rate Analysis for turfing of buffalo grass


RA 05

Remarks

Rate Analysis was prepared according to the previous records.


This rate is used for future payments.
Initially the existing ground was prepared by removing unnecessary wastes such
as stones roots and ect. Then the top soil (carbonic soil) was spread over the
prepared ground and thickness was maintained as 50mm. After that the plates of
buffalo grass (300mm*300mm) were placed together on the top soil layer and
completed it to get level surface.
(Since the Turfing area was in steep the work was little difficult than in plane
surface)
By considering 30m2 area,
Preparing existing ground

= Unskilled 2

Spreading top soil

= Unskilled 1

Placed & compacting turf

= Unskilled 2
Unskilled 5

For 30m2

(Rs) = 5*540

For 01m2

(Rs) = 5*540/30

The rate for 01m2

Prepared by
Checked by .
Certify by
Recommended
Approved by ..

(Rs)

= 90.00