Professional Documents
Culture Documents
Cop Buildable Design Sep05
Cop Buildable Design Sep05
Cop Buildable Design Sep05
Buildable Design
September 2005
Contents
CODE OF PRACTICE
1
Scope
Definitions
Statutory requirements
ANNEX
A
11
Introduction
The limits on supply of foreign workers and rising demand for better quality make it necessary for
the industry to adopt labour-efficient designs and use of more pre-assembled products. A key
measure to achieve this is the introduction of government regulations under the Building Control Act
to require building designs to have a minimum Buildability Score.
This Code sets out the requirements of minimum buildability and the submission procedures. It also
sets out the method of determining the Buildability Score. Some amendments and revisions may be
expected from time to time.
If you need clarification on any aspect of this Code of Practice, please contact the Building and
Construction Authority, Singapore.
SCOPE
This Code of Practice sets out the minimum Buildability Scores for different categories of building,
the submission procedures and the method for determining the Buildability Score of a building
design.
DEFINITIONS
For the purpose of this Code, the following definitions shall apply:
Buildability
Buildability Score
Minimum Buildability
Score
The gross floor area is calculated using the definition by the Urban
Redevelopment Authority (URA).
Type of Use
Type of Building
Work
STATUTORY REQUIREMENTS
3.1 Act and Regulations
The following Act and Regulations have relevance:
a.
b.
c.
3.2 Responsibility
3.2.1
3.2.2
The owner shall engage the appropriate qualified persons to carry out buildable
design. The QP for building works and the QP for structural works shall be
responsible for ensuring that the buildability requirement is met. The QPs shall
jointly declare the Buildability Score achieved. The QPs shall also jointly declare
the As-built Buildability Score achieved.
The Buildability Score of the building design shall be determined using this Code
of Practice and the BDAS which is given in Annex A of this Code. BDAS may, from
time to time, be amended, modified or replaced with a new edition.
4.1.2
Part 2
Part 3
In addition to the above, bonus points are obtainable in Part 3 if a project uses
single integrated components such as prefabricated bathroom/toilet units and precast
household shelters.
The maximum buildability score achievable for a project is capped at 100 points.
The minimum Buildability Score requirement shall apply to new building works
with Gross Floor Area (GFA) equals to or greater than 2,000 m2.
4.2.2
The minimum Buildability Score requirement shall also apply to building works
consisting of repairs, alterations and/or additions (A&A work) to an existing building
if the building works involve the construction of new floor and/or reconstruction of
existing floor for which their total gross floor area is 2,000 m2 or more.
4.2.3
4.2.4
For building works with GFA equals to or greater than 2,000 m2 but less than
5,000 m2 and for which applications for planning permission were made before 1st
January 2004, the minimum Buildability Score requirement shall not be applicable.
TYPES OF DEVELOPMENT
Residential (landed)
Terrace house
Semi-detached house
Bungalow
Clustered housing
Residential (non-landed)
Condominium
Flat
Service apartment
Apartment
Dormitory
Hostel
Commercial
Bank
Departmental store
Shopping centre
Office building
Supermarket
Restaurant
Hotel
Conventional hall and facilities
Exhibition hall
TYPES OF DEVELOPMENT
Industrial
Factory
Warehouse
Godown
Brewery
Cold storage building
Packaging and processing plant
Printing plant
Sub-station
School
Primary school
Secondary school
Library
Hospital
Home for the aged
Childcare centre/Nursery
Research building
Educational facilities
Terminal building
Campus
Medical centre
Camp
Embassy
Museum
Crematorium and Columbarium
Club house
Cinema/Theatre
Sports/Recreational facilities
Public transport station
The above list shall not be exhaustive. The QP is advised to seek clarification with BCA if his type of
development is not stated in the above list.
4.2.5
For buildings not listed in the First Schedule, the QP may apply for exemption if
the building has a uniqueness arising from special functional requirements. The
exemption will be on a case-by-case basis. The application for exemption is to be
submitted to the Commissioner of Building Control.
For new building work and A&A work outside existing building (considered as new
work), the minimum Buildability Score for each category of development, namely
residential projects, commercial projects, industrial projects, school projects and
institutional and other projects are tabulated in Table B. Different minimum Buildability
Score requirements are given for 2,000 m2 GFA < 5,000 m2, 5,000 m2 GFA < 25,000 m2
and GFA 25,000 m2.
GFA 25,000 m2
Residential (landed)
57
59
62
Residential (non-landed)
63
65
68
Commercial
65
72
75
Industrial
67
74
77
School
64
69
72
60
66
69
4.3.2
For clarity, reference shall be made to the table below for the relevant issue of
Code of Practice on Buildable Design to be used.
Not applicable
4.3.3
For A&A work within existing buildings, the minimum Buildability Scores for
residential, commercial, industrial, school and institutional and other projects are
shown in Table C.
Residential (landed)
57
Residential (non-landed)
60
Commercial
62
Industrial
62
School
60
60
4.3.4
The minimum Buildability Scores will be raised in January 2007 and August 2008
as shown in Table D.
Table D Minimum Buildability Score with effect from 2007 and 2008
MINIMUM BUILDABILITY SCORE
st
CATEGORY OF BUILDING
WORK / DEVELOPMENT
st
1 JANUARY 2007
1 AUGUST 2008
GFA
2,000 m2 5,000 m2
GFA
2,000 m2 5,000 m2
2
GFA < GFA < 25,000 m GFA < GFA < 25,000 m2
5,000 m2 25,000 m2
5,000 m2 25,000 m2
60
62
65
Residential (landed)
60
65
68
72
75
74
77
74
77
69
72
66
69
57
(A&A work within existing building)
66
68
71
Residential (non-landed)
67
60
67
74
77
Commercial
69
62
69
74
77
Industrial
69
62
64
69
72
School
64
60
60
66
69
60
60
The minimum Buildability Scores in Table D shall take effect for projects submitted for planning approval
on or after the respective dates.
4.3.5
% OF BUILDING GFA
Residential (non-landed)
70% of GFA
70% of 65 = 45.50
Commercial
30% of GFA
30% of 72 = 21.60
100% of GFA
67
(rounded to nearest integer)
% OF BUILDING GFA
GFA 25,000 m2
Residential (non-landed)
70% of GFA
70% of 68 = 47.60
Commercial
30% of GFA
30% of 75 = 22.50
100% of GFA
70
(rounded to nearest integer)
4.3.6
% OF GFA
5,000 m2 GFA < 25,000 m2
20% of GFA
20% of 62 = 12.40
80% of GFA
80% of 72 = 57.60
100% of GFA
70
(rounded to nearest integer)
5.1
BP stage
ST (Structural plan) superstructural stage
Temporary Occupation Permit (TOP)/Certificate of Statutory Completion (CSC) stage
Submission at BP Stage
The QPs shall indicate in Form BPD_BP03 (Application for Approval of Building Plans)
whether Buildability Score calculations are applicable to the proposed building works. If
applicable, the Buildability Score is to be submitted together with the BP submission
using Form BPD_BS01. The Buildability Score is to be jointly declared by all QPs and the
detailed computation of the Buildability Score attached. Forms BPD_BP03 and
BPD_BS01 can be downloaded from BCAs website at http://www.bca.gov.sg/.
5.2
5.3
Upon project completion, the QPs shall compute and declare the As-built
Buildability Score and submit one set of the computation to BCA using Form
BPD_BS03. This application is to be made within one month of obtaining TOP or
before CSC, whichever is earlier. Form BPD_BS03 can be downloaded from
BCAs website at http://www.bca.gov.sg/.
5.3.2
First Schedule
BUILDING WORKS WHICH ARE NOT SUBJECTED TO THE MINIMUM
BUILDABILITY REQUIREMENT
The types of development which are not subjected to the minimum buildability requirement are:
(a) any culvert, bridge, underpass, tunnel, earth retaining or stabilising structure, slipway, dock,
wharf or jetty;
(b) any theme park;
(c) any place of worship;
(d) any power station; or
(e) any waste processing or treatment plant.
10
Annex A
BUILDABLE DESIGN APPRAISAL SYSTEM
11
Contents
1.0
INTRODUCTION
13
1.1 Objective
1.2 Principles of Buildable Design
1.3 Scope
1.4 Buildability Score and Contractors Productivity
1.5 Rationale on Allocation of Points
1.6 Rationale on Derivation of Labour Saving Indices
1.7 Development of Buildable Design Appraisal System, BDAS
2.0
15
12
24
1.0 INTRODUCTION
The Buildable Design Appraisal System or BDAS was developed by the Building and
Construction Authority as a means to measure the potential impact of a building design on the
usage of site labour. The appraisal system results in a Buildability Score of the design. A
design with a higher buildability score will result in more efficient labour usage in construction
and therefore higher site labour productivity.
1.1
Objective
The objective of BDAS is to result in the wider use of buildable design. It is not the
intention to adopt buildability at the expense of good architectural design. The need
for more varieties and architectural features to satisfy clients needs is recognised.
There are, in fact, many examples of attractive designs that have high buildability
scores.
Neither is the BDAS intended to solely promote prefabrication. Although, in
general, prefabrication should give higher buildability scores, designs using
simple cast-in-place construction can also yield reasonably high buildability scores.
Most importantly, buildable designs will lead to improvements in quality. This is
due to the relative ease of construction and the need for fewer skilled tradesmen.
1.2
13
1.3
Scope
BDAS therefore looks at the design and computes the extent to which the
principles of standardisation, simplicity and single integrated elements are found.
It covers the structural system and the major architectural components such as
external and internal walls, doors and windows.
Points are awarded based on the types of structural and architectural system used.
More points are awarded to the more buildable systems. The points are totalled
to give the Buildability Score of the design.
1.4
1.5
1.6
1.7
Development of BDAS
The Buildable Design Appraisal System was developed with the assistance of a committee
comprising leading local and foreign contractors who provided productivity data inputs
from their projects. Inputs from various government agencies, consultants and product
manufacturers were also incorporated. The concern for buildability, or the need to integrate
design with construction, has also been taken up in developed countries. In Japan, this
integration is maximised as most projects proceed on a design-and-build basis. Major
Japanese contractors such as Takenaka Corporation, Taisei Corporation and Kajima
Corporation have developed their own in-house buildability appraisal systems. BCAs
Buildable Design Appraisal System is modelled after Takenakas system.
14
(b)
(c)
15
Buildability
Score of
Building
BS
where As
Asa / Ast
Lw
Lwa / Lwt
As
Ast
Total floor area which includes roof (projected area) and basement area
Asa
Lw
Percentage of total external & internal wall length using a particular wall
system
Lwt
Total wall length, excluding the length of external basement wall for
earth retaining purpose
Lwa
Ss
Sw
Labour saving index for external & internal wall system (Table 2)
Bonus points =
The Buildability Score of a project which consists of more than one building should be computed
by multiplying the respective Buildability Score of the individual building with its percentage of
the total floor area of that building in the project. That is,
BS project = Sum of [BS building x (Ast) building / (Ast) project]
16
Ss :
A labour saving index for the particular structural system. The labour saving indices for
the various structural systems are given in Table 1.
All structural systems used must be accounted for. If a combination of systems is used, then
the contribution of each system is computed and summed up to arrive at the score. The
maximum Buildability Score for the structural system is 50 points.
The total floor area is the total floor area constructed in the project, and includes roof (projected
area) and basement area.
(b)
The extent to which a particular external or internal wall system is used. This is expressed
as a percentage of the total wall length of the building.
Sw :
A labour saving index for the particular external or internal wall system. The labour
saving indices for the various wall systems are given in Table 2.
All wall systems must be accounted for. If a combination of systems is used, then the contribution
of each system is computed and summed up to arrive at the score. The maximum Buildability
Score for the wall system is 40 points.
The total wall length includes all external and internal walls but exclude external basement
wall for earth retaining purpose.
(c)
(d)
17
STRUCTURAL SYSTEM
LABOUR
SAVING INDEX
Ss
DESCRIPTION
Full precast
1.00
0.95
0.90
0.85
0.80
0.75
0.75
0.75
Roof System
0.95
0.85
Flat plate(1)
0.90
Flat slab(1)
0.85
0.75
0.65
0.50
0.90
0.85
0.75
0.60
0.55
NOTE:
(1)
(2)
*
*
For cast in-situ floor with cast in-situ transfer beam, an index of -0.10 shall be applied to the entire cast in-situ floor
area. This requirement does not apply to cast in-situ floor with transfer beam designed for ramp access.
Slab/beam refers to the value of slab area over number of beams.
An index of 0.03 each would be given if prefabricated reinforcement/cage is used in cast in-situ slab, beam and
column.
Indices for other systems not shown in this table shall be determined by BCA on a case-by-case basis. For such
cases, the QPs are advised to seek BCAs comments before proceeding with the designs.
18
STRUCTURAL SYSTEM
LABOUR
SAVING INDEX
Ss
1.00
DESCRIPTION
Full precast
Precast beam and precast slab
Precast beam and precast column/wall
0.90
(3)
(3)
0.80
0.75
0.75
Roof System
(1)
0.85
(1)(3)
0.75
0.95
0.85
0.90(4)
0.80(4)
0.85(4)
0.75(4)
0.75
0.65
0.50
0.90
0.85
0.75
0.60
0.55
NOTE:
(1)
(2)
(3)
(4)
*
*
For cast in-situ floor with cast in-situ transfer beam, an index of -0.10 shall be applied to the entire cast in-situ floor
area. This requirement does not apply to cast in-situ floor with transfer beam designed for ramp access.
Slab/beam refers to the value of slab area over number of beams. In flat plate or flat slab cases, this refers to the
value of the flat plate area (or flat slab area) over the number of perimeter beams bounding the flat plate (or flat
slab).
Precast wall refers to load-bearing walls only.
An additional index of 0.05 would be given if flat plate/flat slab is used with precast columns (or precast load bearing
walls). For example, the index for flat plate with no or minimal perimeter beams (slab/beam > 15) with precast
columns would be 0.95 (0.90 + 0.05).
An index of 0.03 each would be given if prefabricated reinforcement/cage is used in cast in-situ slab, beam and
column.
Indices for other systems not shown in this table shall be determined by BCA on a case-by-case basis. For such
cases, the QPs are advised to seek BCAs comments before proceeding with the designs.
18a
Table 1 has been arranged into 4 main systems of precast concrete system, structural steel
system, cast in-situ system and roof system with their respective labour saving indices. In the
event when a structural system used for a project is not stated in Table 1, the labour saving
index shall be decided by BCA.
(b)
For precast concrete system, the labour saving indices are given according to the
combinations of precast components (slab, column/wall and beam) used.
(c)
For cast in-situ beam and slab construction, the slab/beam value is calculated by dividing the
floor slab area over the number of beams supporting that floor area. *In the case of a flat plate
or flat slab, this value is calculated by dividing the flat plate or flat slab area over the number
of perimeter beams bounding the flat plate or flat slab. A continuous beam across three
columns is considered as two beams for the purpose of determining the value of slab area
over number of beams. Similarly, a continuous beam across four columns is considered as
three beams.
st
* applies only to projects with planning applications made on or after 1 January 2007
(d)
Flat plate refers to a slab design which does not have column heads or drop panels. Under
BDAS, a flat plate system could be viewed as a floor with flat soffit (with the exception of
perimeter beams). From the buildability point of view, such floor with flat soffit would ease
formwork construction and reinforcement work at site considerably and helps to improve site
productivity.
(e)
The index for concrete roof depends on the type of structural system used and follows the
respective index given under cast In-situ system or precast concrete system.
(f)
The integrated metal roof refers to prefabricated roofing system complete with insulation and
can be installed as an entire roof section.
(g)
A transfer beam refers to a beam that interrupts the paths of load bearing elements from
above and distributes the loads sideways to the ends of the beam.
(h)
Additional points in the form of labour saving index of 0.03 each would be awarded for the use
of prefabricated reinforcement/cages in cast in-situ floor, beam and column.
The use of prefabricated reinforcement/cages must be indicated on plans.
The percentage of coverage for the use of prefabricated reinforcement/cages is to be based
on the total floor area or on the total number of columns or total number of beams.
Example of prefabricated reinforcement:
Area of precast floor = 3000 m2
Area of cast in-situ floor using prefabricated reinforcement (mesh) = 7000 m2
Total floor area including roof area = 10, 000 m2
Percentage of coverage
= area of cast in-situ floor using mesh/total floor area
= 7000/10000
= 70%
Therefore, points awarded = 0.03 x 0.70 x 50
= 1.05
19
TABLE 2
WALL SYSTEM
0.70
1.00(1)
0.80
0.90(1)
PC formwork(4)
0.50
0.75(1)
0.50
0.70(1)
0.54
0.74(1)
0.40
0.45(1)
0.30
Brickwall
0.30
NOTE:
(1)
The higher indices apply to no finishes, finishes done off-site or where skim coat and/or paint is applied on site.
(2)
Dry partition walls include sandwich panel wall systems, stud and sheet partition wall systems, demountable wall
systems.
Precast concrete panels/walls include normal weight concrete panels, lightweight concrete panels, autoclaved
aerated concrete panels.
PC formwork refers to precast formwork panel with concrete infill.
(3)
(4)
Indices for other systems not shown in this table shall be determined by BCA on a case-by-case basis.
20
Table 2 has been arranged into the various wall systems with their respective labour saving
indices. Where a wall system has 2 labour saving indices, the lower index is applicable when
the finishes involve plastering, tiling or stone works on site. Conversely, the higher index
applies when there are no finishes, the finishes are done off-site or the finishes only involve
application of skim coat and/or paint on site. In the event when a wall system used for a
project is not stated in Table 2, the labour saving index shall be decided by BCA.
(b)
Dry partitions refer to panels that do not require the use of water for erection. Examples are
solid composite gypsum boards, cementitious panels or glass panels etc. Precision blocks
refer to lightweight concrete blocks that have precised dimensions ( 1mm dimensional
tolerance) and can be laid on thin bed adhesive mortar.
(c)
The use of prefabricated reinforcement in cast in-situ walls must be indicated on plans.
21
BUILDABLE FEATURES
MODULE
UNIT OF
COVERAGE
N VALUE
PERCENTAGE OF
COVERAGE(4)
65% TO
80%
< 80%
1.
Standardisation
1.1
0.5M(2)
no.
2.00
1.2
1.3
0.5M(2)
no.
2.00
0.5M
no.
1.00
1.4
1M/1M
no.
1.00
2.
Grids
0.5M
no.
1.50
2.00
0.5M
no.
0.75
1.00
area
1.50
2.00
area
0.75
1.00
2.1(a)
(3)
2.1(b)
2.2(a)
2.2(b)
3.
3.1
Others
Multi-tier precast columns
no.
2.00
3.2
no.
2.00
3.3
no.
1.50
3.4
no.
1.50
3.5
no.
1.00
3.6
Non-screed floor
area
1.00
3.7
3.8
no.
1.00
no.
1.00
A.
A.1
A.2
no.
2.00
3.00
no.
2.00
3.00
NOTE:
(1)
(2)
(3)
(4)
22
BUILDABLE FEATURES
MODULE
UNIT OF
COVERAGE
N VALUE
PERCENTAGE OF
COVERAGE(4)
65% TO
80%
< 80%
1.
Standardisation
1.1
0.5M(2)
no.
2.00
1.2
1.3
0.5M(2)
no.
2.00
0.5M
no.
1.00
1.4
1M/1M
no.
1.00
2.
Grids
0.5M
no.
1.50
2.00
0.5M
no.
0.75
1.00
area
1.50
2.00
area
0.75
1.00
2.1(a)
2.1(b)
2.2(a)
(3)
2.2(b)
3.
3.1
Others
Multi-tier precast columns
no.
2.00
3.2
no.
2.00
3.3
no.
1.50
3.4
no.
1.50
3.5
no.
1.00
3.6
Non-screed floor
area
1.00
3.7
No column stumps
no.
1.00
3.8
no.
1.00
3.9
no.
1.00
A.
A.1
A.2
no.
2.00
3.00
no.
2.00
3.00
NOTE:
(1)
(2)
(3)
(4)
22(a)
Table 3 shows the point given to each buildable design feature that contributes to labour
saving on site. Points are summed up to form the Buildability Score for this section. The
maximum score for this section is 10 points.
(b)
For item 1 Standardisation, the criteria of minimum module must be met before points are
given. M denotes 100mm. 0.5M implies that sizes must be in multiples of 50mm. 1M implies
that sizes must be in multiples of 100mm.
(c)
For item 2 Grids, the criteria of minimum module (where applicable) must be met before
points are given. M denotes 100mm. For repetition of floor-to-floor height, 0.5M implies that
the floor-to-floor height must be in multiples of 50mm.
(d)
The unit of measurement for each type of design feature is in number or area. This is specified
in the column entitled Unit of Coverage.
(e)
The percentage of coverage for each type of design feature is classified into 2 categories:
(i) 65% to < 80%
(ii) 80%
(f)
BCA shall determine the points to be awarded or not to be awarded for other buildable design
features that are not stated in Table 3. For such cases, the QPs are advised to seek BCAs
comments before proceeding with the designs.
23
B.
Project Information
No basement
= 18 x 645.90 m2 =
11,626.20 m2
= 18 x 102.40 m2 =
1,843.20 m2
748.30 m2
14,217.70 m2
=
=
129.18 x 5
645.90 m2
102.40 m2
=
=
645.90 + 102.40
748.30 m2
24
Design based on flat plate system with cast in-situ columns with wall combination of precast
walls and precision blocks.
(illustration is based on Table 1 for projects with planning applications made from 1st September 2005 to
31st December 2006)
DESCRIPTION
Structural System
(1) Flat plate for apartment area +
Roof
Asa = 19 x 645.90 = 12,272.10 m2
Ast = 14,217.70 m2
(2) RC beam/slab for lift lobby area +
Roof
Asa = 19 x 102.40 = 1,945.60 m2
Ast = 14,217.70 m2
Value of slab area over number of
beams less than 10
Note : - Roof design as in (1) and (2)
LABOUR
SAVING
INDEX
AREA(m2)
or
LENGTH(m)
COVERAGE
(%)
BUILDABILITY
SCORE
SS = 0.90
12,272.10 m2
86.32%
38.84
SS = 0.50
1,945.60 m2
13.68%
3.42
14,217.70 m2
100.00%
42.26
86.00%
1.29
Total
Use of prefabricated reinforcement
Welded mesh for cast in-situ floor slab
86% of total floor area
0.03
43.55
Total (a)
Wall System
(1) Full height glass and railing
(2) Curtain wall
(3) Precast concrete wall
- skim coat and paint finish
(4) Cast in-situ RC wall
(staircase and lift shaft)
- plaster & paint finish
(5) Precision blocks (internal wall)
- skim coat and paint finish
(6) Precision blocks (internal wall)
- tiled finish
(7) Precision blocks (external walls)
- skim coat and paint finish
Sw = 1.00
Sw = 1.00
Sw = 0.90
408.60 m
717.30 m
5,204.20 m
3.86%
6.78%
49.22%
1.55
2.71
17.72
Sw = 0.50
885.00 m
8.37%
1.67
Sw = 0.45
1,963.90 m
18.58%
3.34
Sw = 0.40
313.60 m
2.97%
0.47
Sw = 0.30
1,080.20 m
10.22%
1.23
10,572.80 m
100.00%
28.69
Total (b)
25
LABOUR
SAVING
INDEX
AREA (m2)
or
LENGTH (m)
COVERAGE
(%)
BUILDABILITY
SCORE
86%
N = 2.00
85%
N = 1.00
85%
N = 1.00
100%
N = 2.00
100%
N = 1.50
85%
N = 1.00
DESCRIPTION
100%
(6) Ground beams on top of pilecaps
85%
Total (c)
8.50
81
26
3.2
B. Buildability Score
The Buildability Score (BS)
Block A
:
Block B
:
Block C
:
Block D
:
Block E
:
Block F
:
Block G
:
Block H
:
blocks is as follows:
(Ast)bldg / (Ast)proj = 0.13
(Ast)bldg / (Ast)proj = 0.13
(Ast)bldg / (Ast)proj = 0.13
(Ast)bldg / (Ast)proj = 0.14
(Ast)bldg / (Ast)proj = 0.12
(Ast)bldg / (Ast)proj = 0.13
(Ast)bldg / (Ast)proj = 0.05
(Ast)bldg / (Ast)proj = 0.17
27
Notes