CONFIRMATION OF SITE INSTRUCTION

Site Instruction Ref.No.

SI - 015

Date

Project Title

Palm mall Muscat

Client

TAMANI GLOBAL DEVELOPMENT & INVESTMENT LLC

Consultant

Engineering Innovation Design & Consulting LLC

Contractor

SMC INFRA LLC

31/10/2015

To
Mohammad Fayazuddin
Resident manager
EIDC
WE CONFIRM THE FOLLOWING INSTRUCTION:S.No.

Description

Corrective action

rectified using to approved


material BASF 907 ( Material
Data sheet & photo copy
attached here) And instructed to
The cracks found over the first
site engineer to do ensure the
floor sunken slab between Part-04/
Curing immediately after the
Grid A-B/34-38.
pouring, Avoiding slurry
accumulation on top layer and
ensure cover blocks as per
approved drawing

For SMC

(Name)

Status

Done

(Signature)

SMC INFRA LLC, P.O.BOX : 1126, P.C : 130, AZAIBA, SULTNATE OF OMAN, TEL : +0968 24492105, FAX : +968 24492115, E-MAIL :
smc@smcinfraoman.com

SMC/IMS/PRJ/021 REV 00

Page 1 of 1

ISSUED DATE : 01/09/2014