Index: Methods To Complete The New Building................. 4
Index: Methods To Complete The New Building................. 4
Summary:..............................................2
Reasons for the work:............................2
Effective Argument/ Persuasion..............2
Estimate time and cost...........................3
Request For Qualifications Response......4
MethodstoCompletetheNewBuilding.................4
Attachment............................................4
ProposalforSingerSalvageYard20152016BuildingProject
Summary:
EveryoneneedsaplacetogetridofcertainthingsandtheSingerSalvageYardisthe
placetotakeallunwanteditems.Wecanhelppeoplegetridofnotonlysalvage,but
ofitemsthatareofasupernaturalnatureaswellashumanbodies.TheSinger
Salvageyardhasbeengrowingexponentiallyforthelast5consecutiveyears,and
withthingscontinuingtogrow,theSingerSalvageyardmustgrowaswell.
Thisproposalisarequestforfundingforanewfacilityweareplanningonbuilding
inthenextfewmonthstocome.TheSingerSalvageYardhasseenaverylargegrowthin
requestsforbodydisposal.Weneedthisfacilitytohelpundertakethelargenumberof
ordersthatwehavebeenfacedwith.Wehypothesizethatthisbuildingwillallowusto
morethandoublethecurrentamountoforderswearehandling,anditwillensurethe
growthoftheSingerSalvageYard
Thespecificaimsofthenewfacilityareasfollows:
1)Tohavemorespacetoprocessmorehumanbodyorders
2)Aseparatebuildingwhichwillprovideanewmeansofsortingwhatmaterialsweare
workingon(salvage,bodies,itemsofsupernaturalnature)
3)EnsuremajorgrowthcapabilitiesoftheSingerSalvageYard
analysisshowsthatholdingbackonthisnewfacilitywouldcompromiseandaffect
currentbusinessgreatly.Furthermore,currentcontractswillexpiresoon.Withnew
competitionarising,ifwedonotoffermoreforthemoneytoourclientswewillbe
loosingtherenewalofthecurrentcontracts.Thesecontractscurrentlybringin
$1,500,000.Withoutthenewfacilitieswewouldalsobeeloosingonthepotential
contractsofpartnerswhohaveexpressedtheirinterestforwhenthenewfacilitiesthat
allowustostoreandreceivelargeramountsofmaterialsarerunning.Itisestimatedthat
futurecontactscouldamount$2,5000,000ofadditionalrevenue.Withoutthenew
buildingswearealsogoingtohavetostartaprocessofcleanupatourcurrentfacilities.
Thecurrentfacilitiesdonothavemorespacetokeepgrowingandcannotkeepupwith
demand.Wedonothaveenoughpersonnelortimeinordertoprocessalloftheproducts
currentlyinthewarehouseandwewouldneedtobasicallythrowawaymoneyinorderto
openupspaceinthewarehouseandbeabletosatisfythecurrentcontracts.Currentlywe
have20investorsthatamountto$3milliondollarsinassets.Theyhaveallagreedthat
thenewbuildingisrequiredforbusinesstocontinuetogrowandexpand.Refusingornot
continuingwiththisprojectwouldpotentiallycreateconflictwithinvestorfundingand
wewouldbeloosingaverylargeportionofourassetsshouldtheydecidetoinvest
somewhereelse.
requireavisibilityshieldthatprotectstheareasthatshouldremainvisiblefrom
everythingelse.Thetotalcostofthevisibilityshieldis$500,000.Shouldno
complicationsarisethebuildingshouldbeelevatedhiddenandfullyfunctionalby
December2018
MethodstoCompletetheNewBuilding
TocreatealargerfacilitytoexpandtheSignerSalvageYard,wearegoingto
needalotoftimeandmoney.Onemethodtobuildournewfacilitycouldbeworking
withourpartnersfromtheNimbusRacingBroomCompanytoassistusinthebuilding
process.Thespeedybroomsandspellscouldmakethebuildingprocessalotquickerand
moreproductive.IftheNimbusRacingBroomCompanyagreestohelpuswecouldusea
spelltoquicklyhaveanewbuilding.WecouldalsousetheRacingBroomstotransport
material.Theracingbroomsarespeedyandcontainamplestorespaceintheirmagic
storagecontainers.
Anothermethodtobuildanewfacilityquicklywouldbehavingourfriendsfrom
DharmaandDanFairwayhelpususecreateatimebarrier.CreatingaTimebarrieror
travelingthroughtimewouldallowustobuildafacilitywithouttakingalongtime
withinthenormaltimebarrier.Wecouldtravelthroughtimetoafterthebuildinghas
alreadybeenbuiltthiswouldbeasimplewaytospeedupthebuildingprocesstomake
thenewfacilityrightforusequickly.
Attachment
ItemName
Material
Labor
Equipment
Total
Excavation
19,083.00
5,580.00
24,663.00
Foundation,Piers,Flatwork
45,826.00
64,663.00
11,350.00
121,839.00
RoughHardware
2,744.00
3,878.00
685.00
7,307.00
MasonryFrame
93,717.00
115,826.00
7,329.00
216,872.00
Insulation
17,018.00
10,437.00
27,455.00
ExteriorFinish
48,382.00
25,920.00
3,599.00
77,901.00
ExteriorTrim
3,277.00
4,628.00
815.00
8,720.00
Doors
8,306.00
6,252.00
14,558.00
Windows
14,305.00
8,724.00
23,029.00
FinishHardware
1,384.00
1,043.00
2,427.00
GarageDoor
3,921.00
1,434.00
5,355.00
Roofing,Flashing,Fascia
37,999.00
28,593.00
66,592.00
FinishCarpentry
5,043.00
22,789.00
27,832.00
InteriorWallFinish
24,208.00
33,538.00
57,746.00
Painting
14,463.00
30,296.00
44,759.00
Wiring
14,686.00
24,873.00
39,559.00
LightingFixtures
11,010.00
3,107.00
14,117.00
Flooring
17,638.00
22,452.00
40,090.00
Carpeting
35,094.00
11,231.00
46,325.00
BathAccessories
5,332.00
2,945.00
8,277.00
Shower&TubEnclosure
3,403.00
2,561.00
5,964.00
Countertops
10,294.00
7,740.00
18,034.00
Cabinets
33,845.00
9,548.00
43,393.00
BuiltInAppliances
16,468.00
2,062.00
18,530.00
PlumbingRoughinandConnection
25,197.00
54,898.00
3,674.00
83,769.00
PlumbingFixtures
51,187.00
14,548.00
65,735.00
HeatingandCoolingSystems
12,206.00
18,309.00
30,515.00
UnitHeatingandCooling
FireplaceandChimney
SubtotalDirectJobCosts
$556,953.00
$551,378.00
$33,032.00
$1,141,363.00
FinalCleanup
5,274.00
5,274.00
Insurance
36,917.00
36,917.00
Permits&Utilities
22,414.00
22,414.00
Plans&Specs
5,274.00
5,274.00
SubtotalIndirectJobCosts
$64,605.00
$5,274.00
$69,879.00
ContractorMarkup
164,807.00
164,807.00
TotalCost
$786,365.00
$556,652.00
$33,032.00
$1,376,049.00