ASOSIASI KONTRAKTOR LISTRIK INDONESIA

ANALISA HARGA SATUAN JASA


PEMASANGAN INSTALASI LISTRIK

NO JENIS PEKERJAAN HARGA BIAYA JUMLAH


SATUAN (Rp.) DIBULATKAN
(Rp.) (Rp.)

1 2 3 4 5

DASAR UPAH
- Pekerja (pembantu tukang) upah minim
- Tukang
- Kepala Tukang
- Mandor
- Teknisi
- Supervisi
- Tenaga Ahli (Expert)

1 PEKERJA
Upah 1 hari 17,250.00 17,250.00
Transfort 1 hari 8,000.00 8,000.00
Uang Makan 1 hari 7,000.00 7,000.00
32,250.00 32,250.00

2 TUKANG
Upah 1 hari 24,500.00 24,500.00
Transfort 1 hari 8,000.00 8,000.00
Uang Makan 1 hari 8,000.00 8,000.00
40,500.00 40,500.00

3 TEKNISI
Upah 1 hari 38,250.00 38,250.00
Transfort 1 hari 8,000.00 8,000.00
Uang Makan 1 hari 10,000.00 10,000.00
56,250.00 56,250.00

4 TENAGA AHLI MUDA


Upah 1 hari 93,500.00 93,500.00
Transfort 1 hari 15,000.00 15,000.00
Uang Makan 1 hari 15,000.00 15,000.00
123,500.00 123,500.00

5 SUPERVISI
Upah 1 hari 139,750.00 139,750.00
Transfort 1 hari 15,000.00 15,000.00
Uang Makan 1 hari 20,000.00 20,000.00
174,750.00 174,750.00