Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

John Cross, P.E.

fter decades of minimal activity, steel-framed parking


structures are gaining popularity with designers and developers, according to Dale
Denda, an industry analyst with the Parking
Market Research Company. Exposed steelframe construction is back as a recognized
option for multi-story parking structures, he
insists.
Steel has long been recognized for its obvious advantages: lower construction costs (in
addition to reduced structure weight which
reduces foundation costs), rapid construction
time, and longer clear-spans. Some designers
have also touted steels security benefits
fewer and smaller columns mean fewer places
for predators to hide.
In the past however, some designers have
shied away from steel because of structural
fire protection requirements and perceived
failings of standard coatings. Fortunately, the
steel industry has addressed both of these
concerns.
In 1972, the steel industry sponsored the
full-scale Scranton Fire Test, the results of
which put the fire safety issue to rest. The test
showed that a car fire in an open parking
garage does not spread to fully involve adjacent vehicles, and temperatures of unprotected steel during this exposure are well
below those at which the strength of structural steel begins to diminish. Today, under
the International Building Code, open, detached parking garages up to 75-high can be
framed with unprotected steel in most jurisdictions. In fact, a study of more than 400

AT&T-Lucent, Warren, NJ

STRUCTURE July/August 2001

37

parking garage fires during the past decade by


the Parking Market Research Corporation
reveals less than a total of $50,000 in structural damage.
The coatings industry has also played
their part in increasing the viability of steel
for parking structures. Today, coating technology exists that can effectively protect steel
framing systems with limited touch up for
significant periods. Hot dip galvanizing,
which utilizes the cathodic process of introducing zinc to the corrosion circuit as the
sacrificial anode, has a projected protection

Steel has made the fastest inroads into the


airport, health-care and university markets.
These three markets share the need for fast
erection on tight sites, and also often are involved with the expansion of existing structures.

Portland International Airport,


Portland, OR
A notable recent project is the expansion
of a parking garage at Portland International
Airport. The project involved adding 3,300
spaces to an existing three story, pre-cast con-

Portland International Airport, Portland, OR

The expansion of the garage required


7,500 tons of structural steel. Typical interior
floor framing for the expansion consisted of
3 composite G90 galvanized metal decking
with a 3-1/2 concrete topping. Reinforcing
steel was added to the low flutes of the deck
as a backup system in event of deck corrosion.
W16x26 floor beams span 30 to W30x116
girders with columns in a 30 x 60 bay system. Two levels of the expansion were supported directly on top of existing pre-cast
concrete columns. New pin piles were installed inside the garage and supported approximately half the weight of the existing
structure and the upper two levels of the expansion.
The west expansion of the garage was column free to allow buses and commercial vehicles unimpeded access. To create this
column free space, W33x118 beams at 10 on
center span 95 between column lines. To accomplish this span large cambers were required that varied from beam to beam to
provide slope for storm water runoff.
Structural engineer for this award-winning project was KPFF Consulting Engineers. Project architect was Zimmer Gunsul
Frasca. Baugh Construction served as general
contractor with Fought & Company and
Canron Steel as steel fabricators.

Jefferson at Lenox Park,


Atlanta, GA

Jefferson at Lenox Park, Atlanta, GA


life (less than 5% surface corrosion) in excess
of 40 years.
Likewise, new high-performance paint
systems are now available at an economic
price. Todays high performance paint systems, which utilize zinc rich primers and one
or two topcoats of epoxy, have an expected
life-span (with minimal touch-up) that exceeds 25 years.

38

crete framed parking structure. Steel was chosen as the framing material for the garage
expansion to minimize structure weight and
allow the existing garage to remain open during the construction process. The design of
the expanded structure called for a four-story
addition to the top of the existing garage and
a 95 widening of the existing structure with
a seven-story steel framed addition.

STRUCTURE July/August 2001

A different approach to steelframed,


conventionally reinforced cast-in-place deck
system was utilized for an apartment complex
parking deck at Jefferson at Lenox Park in
Atlanta, GA. A clear span, 62 parking bay
was constructed using a castellated steel beam
in a composite system with the slab and the
deck. The system included the use of a 30
castellated beam fabricated from W21x44
and W21x50 wide flange beams. The typical
beam weighed only 47 lbs. per lineal foot, reducing the overall weight of the parking
structure. The smaller top cord section had
welded stud shear connectors applied in the
field and is composite with the corrugated
metal deck and concrete. The deck consists of
a 3 deep, 20-gage composite galvanized deck
with 3 of normal weight, reinforced concrete
over the high corrugation.
Principal exterior girders are regular
W24x62 wide flange beams on 30 spans. The
largest column section is a W8x67. The low

weight of the steel in the structure allowed


significant savings in the foundation costs for
the project resulting in a total per space cost
of $4,500 and a differential cost savings of
$600,000 compared to a concrete alternative.
A vibration study of the finished project was
conducted by Dr. Thomas M. Murray, P.E.,
who concluded that the performance of the
beam-deck system was excellent with barely
perceivable vibrations.
The project was developed by JPI, Inc.
with JPI Construction serving as the general
contractor. Structural design was completed
by Alliance Structural Engineers. SMI Steel
Products supplied the castellated beams.

Winthrop University Hospital,


Mineola, NY
The parking requirements of the
Winthrop University Hospital were addressed through the recent construction of a
630 space, three-story steel framed parking
structure with a 6 nominal composite, post
tensioned deck. Ten feet floor-to-floor height
is typical with a minimum clearance of 72.
Architectural pre-cast panels are used as a
faade treatment for the structure. The posttensioned deck was chosen based on the hospitals desire to avoid joints and maintain a
large expanse of crack free space typical with
this style deck. This minimizes the probability of leakage and/or chloride contamination
of the slab, which in turn reduces maintenance and future repair expense. Also, by utilizing post-tensioning, the amount of steel
required to reinforce the slab was reduced. A
40% solids penetrating silane sealer was applied to the deck surface to act as additional
protection against moisture and chloride absorption.
The structure utilized 750 tons of steel.
Typical members were 30 deep spanning 60
across drive lanes and parking bays. By utilizing the composite action of the steel frame
running in a single plane across the drive
aisles and parking bays and the concrete deck,
the weight of the steel frame was reduced to
about 9 lbs. per square foot. The concrete
faade panels were erected at the same time as
the structural components to add stability to
the structure during erection.
The steel was protected by shop blasting
to bare metal (SSPC-SP6) and shop applying
3 mils of an epoxy/zinc based primer. A 4 to

Winthrop University Hospital, Mineola, NY


6 mil epoxy topcoat applied in the field completed the protective coating system.
The project was constructed as a design/build project by Carl Walker Construction and Carl Walker, Inc. Sydney Brown and
Son served as the architect and Axis Construction was the construction manager. The
design/build contracting approach was chosen in order to facilitate faster project delivery and resulted in significant time savings
through the simultaneous structural design,
foundation work, steel fabrication and mill
orders.

AT&T-Lucent, Warren, NJ
The benefits of combining a steel-framing
system and pre-cast double tee decks are very
apparent in four parking structures constructed at AT&Ts office complex in Warren, NJ. The four garages contain a total of
3,600 spaces on three levels.
The garages were designed by Zaldastani
Associates and fabricated by Interstate Steel
utilizing the Hybrid System approach. The
Hybrid System consists of paired steel
columns and girders designed to support the
pre-cast floor deck and provide lateral stability during and after construction. Paired
plates at 5 -on-center interconnect the paired
columns vertically. The columns were erected
to full height, interconnected at each floor
with steel girders at each of the two column
lines. This arrangement provides vertical stability in the transverse direction by the ladder

STRUCTURE July/August 2001

frame cantilevering from the ground and in


the longitudinal direction by conventional
frame action.
Special attention was given to connection
details in order to create a moment resisting
frame that enabled the steel supported structure to readily resist lateral forces without the
introduction of unsightly shear walls or bracing.
The floor consists of pre-cast double tees
that were attached to the top flange of the
frames steel girders. The flanges of the double tees were welded together in the manner
normally provided for pre-topped tees and a
connection was made between the tees in a
shaped cast-in-place infill that incorporates
floor and roof drains into the deck system.
The Hybrid System has been optimized
to reduce the number of pieces in construction and to simplify erection. The advantage
of the approach was evident in the design and
construction of the project in a ten-month
period, matching the demand for parking
spaces from the adjacent office buildings. The
total cost savings of the Hybrid System over
the concrete alternative exceeded one million
dollars.
John Cross, P.E., is National Project Director
with AISC Marketing, LLC in Chicago.

39

You might also like