Department of Civil Engineering

NSHM Knowledge Campus, Durgapur


5th Semester (Group-A), Session 2014-15
Quantity Surveying, Specifications and Valuation Practical (CE 593)

Sheet No-3. Estimate of Road

Prepare an estimate of the following items:


1.Earthwork in Cutting & Banking
2. Turfing Area
3. W.B.M.
4. Tack coat
5. Bituminous Concrete
6. Surface Coat
Following data are given.
Chaina 20
21
22
23
24
25
26
27
28
29
30
ge
R.L. of
74.2 73.2 71.5 68.3 69.6 71.3 74.0 75.1 72.3 70.5 70.1
Ground 0
0
0
0
0
0
0
0
0
0
5
Formation Level= 70.00 + 0.2 X (last two digits of your roll no.)
Formation Width (B) = 9 m
Side Slope (S) = 2:1 for banking
=1.5:1 for cutting
Length of the Chain = 30 m

Upward Gradient for Ch:20 to Ch: 24 = 1/200 (For roll no. 01-19)

= 1/150 (for roll no. 19-remaining students)


Downward Gradient for Ch:24 to Ch: 30 = 1/150(For roll no. 01-19)
= 1/200 (for roll no. 18- remaining students)

Type of Material
1st layer
W.B.M.
2nd layer
3rd layer
Tack Coat
Bituminous Concrete
Wearing Coarse

Thickness (mm)
100
75
75
-50
20

Width (m)
9
9
9
9
7.5
7.5