TUGAS

PROJECT MANAGEMENT

Nama : Kadek Tio Adi Saputra


Nim : 130010267

LATIHAN SLIDE : Halaman-33


1. Path dan leght of Path
Path 1 = A, B, C, G = 5 + 6 + 4 + 4 = 19
Path 2 = D, E, F, G = 5 + 5 + 6 + 4 = 20
Path 3 = D, H, I = 5 + 7 + 4 = 16
2. Critical path dan duration of CP
Path 1 = A, B, C, G = 5 + 6 + 4 + 4 = 19
Path 2 = D, E, F, G = 5 + 5 + 6 + 4 = 20 (Critical path)
Path 3 = D, H, I = 5 + 7 + 4 = 16
3. Float / Slack
Path 1 = 20 19 = 1 hari
Path 3 = 20 16 = 4 hari
4. Dimensi waktu ESD & EFD, LSD & LFD
a. Path 1

b. Path 2

c. Path 3

LATIHAN SLIDE : Halaman-34


1. Path dan leght of Path
Path 1 = A, B, C = 3 + 1 + 7 = 11
Path 2 = D, E = 4 + 3 = 7
Path 3 = D, F, G = 4 + 2 + 2 = 8
2. Critical path dan duration of CP
Path 1 = A, B, C = 3 + 1 + 7 = 11 (Critical path)
Path 2 = D, E = 4 + 3 = 7
Path 3 = D, F, G = 4 + 2 + 2 = 8
3. Float / Slack
Path 2 = 11 7 = 4 hari
Path 3 = 11 8 = 3 hari
4. Dimensi waktu ESD & EFD, LSD & LFD
a. Path 1

b. Path 2

c. Path 3

LATIHAN SLIDE : Halaman-35


1. Path dan leght of Path
Path 1 = 1, 2, 3, 5 = 2 + 6 + 3 + 7 = 18
Path 2 = 1, 4, 5 = 2 + 6 + 7 = 15
Path 3 = 6, 4, 5 = 4 + 6 + 7 = 17
Path 4 = 6, 7 = 4 + 8 = 12
2. Critical path dan duration of CP
Path 1 = 1, 2, 3, 5 = 2 + 6 + 3 + 7 = 18 (Critical path)
Path 2 = 1, 4, 5 = 2 + 6 + 7 = 15
Path 3 = 6, 4, 5 = 4 + 6 + 7 = 17
Path 4 = 6, 7 = 4 + 8 = 12
3. Float / Slack
Path 2 = 18 15 = 3 hari
Path 3 = 18 17 = 1 hari
Path 4 = 18 12 = 6 hari
4. Dimensi waktu ESD & EFD, LSD & LFD
a. Path 1

b. Path 2

c. Path 3

d. Path 4