Ifixit Progress Report

Date:
To:
From:

Subject:

October 19, 2015


Ifixit team
Man Truong, California State University, Fullerton student
Eduardo Barrios, California State University, Fullerton student
Helen Huynh, California State University, Fullerton student
Otherwise known as the Fix the Beat team
Progress Report for TDK Life on Record Trek 360

Purpose:
Our teams goal is to provide replacement guides for the TDK Life on Record
Trek 360 wireless speaker in order to help others repair their device.

Summary of Progress

Our team has identified several common user-experienced problems:


No power
No Sound
Distorted sound
Sound only from one speaker
Poor bluetooth signal
Our team has finished the troubleshooting page for our device. Our team will
begin taking photos for all of our guides on Saturday, October 24, 2015. We will
have at least one completed guide by October 29, 2015.

Problems encountered:
When conducting our research into the TDK Life on Record Trek 360, it was
discovered that information was sparse for our device. For example, there was no
information on how to replace the battery or motherboard for our device. If the
device proves to become too difficult to work with then we will contact the
manufacturer in order to gain possible information on the device that can aid us in
furthering our project.

Completed tasks:
The following is a list of completed tasks for our project:
Finished Ifixit group charter
Completed Ifixit project proposal

Constructed Troubleshooting page


Completed Device Page

Current work:
Our current work involves, but is not limited to:
Taking pictures of our device
Finishing the ifixit progress report
Creating the device replacement guides

Remaining work:
This is our remaining work from now, to the completion of our project
Begin replacement guides for our device
Completing the replacement guides for our device
The following is an updated schedule of completed, and uncompleted tasks.
Green is completed tasks and light green is for uncompleted tasks
.
Tasks

Sept 21

Sep 23

Team Charter
Ifixit Proposal
Troubleshootin
g page
Device page
One completed
replacement
guide
Ifixit progress
report
Ifixit Final
project folder
Figure 1. Schedule of completed tasks

Oct 12

Oct 14

Oct 19

Oct 29

Nov 11

Conclusion
We have successfully completed the ifixit proposal charter for the group, project
proposal, troubleshooting page, and device page for our device. We are on
schedule to begin creating replacement guides for our device, and completing the
project on time. We are currently preparing to begin a teardown of the device in
order to locate the components that we shall write repair guides for.
Please contact team Fix the Beat (see above for contact information) if you have
any questions or comments about our work or if you would like to discuss this
project further.