Professional Documents
Culture Documents
TP176 CaseStudiesofPEC
TP176 CaseStudiesofPEC
TP176 CaseStudiesofPEC
Eddy Current to
Measure Wall Loss in
Feedwater Piping and
Heater Shells
TP176
July 2008
By
Marvin J. Cohn and Jordan W. Norton
Aptech Engineering Services, Inc.
INTRODUCTION
The FAC damage mechanism consists of
material dissolution accelerated by fluid flow.
It is primarily a material dissolution process,
where the single or two-phase flow is
responsible for the material transport. This is
a chemical corrosion process causing removal
of the protective oxide film and the metal
surface from the inside of the pipe wall.
ACRONYMS
APTECH Aptech Engineering
Services, Inc.
ARCO Atlantic Richfield Company
AWT Average Wall Thickness
DWT Defect Wall Thickness
TP176
maintenance
personnel,
and
systems
engineers are useful to identify unique unit
specific problems to be considered in the
selection process.
For example, piping
downstream
of
leaking
valves
or
malfunctioning steam traps should be
considered as part of the initial list.
APTECH
TP176
EXAMINATION TECHNIQUES
Electrical power generating plants have
several piping systems and feedwater heaters
susceptible to FAC and erosion-corrosion
damage. These components are insulated to
prevent heat loss. The insulation may be up
to 102 mm (4-inches) thick and is usually
protected by aluminum, galvanized steel, or
stainless steel lagging.
Wall thickness
evaluations have historically been performed
by removing the lagging and insulation and
then performing an UTTH on the heater shell
or piping. Wall thickness measurements are
typically performed off-line using a 5-10 MHz
frequency ultrasonic transducer placed on the
outside surface of the shell. Under ideal
conditions, the UTTH accuracy may possibly
be as good as 0.1 mm (0.004 inch). The
major limitation is the requirement for
insulation removal and disposal, which is very
expensive, especially for asbestos insulation,
APTECH
TP176
productivity.
Cohn and de Raad [10]
compared
UTTH
wall
thickness
measurements to INCOTEST measurements
through insulation for three service-degraded
elbows. de Raad [11] has provided additional
information on the use of PEC as a screening
tool for full-surface coverage detection of
significant wall wastage. Where a thickness
gradient (e.g., grooving) occurs in a footprint
area, INCOTEST equipment may also be
used to estimate the MWT within the
interrogated area.
TP176
Mark II System
APTECH has been using the RTD-INCOTEST
systems since 1997 and discussed some PEC
APTECH
TP176
TP176
APTECH
TP176
CONCLUSIONS
APTECH has been using the RTD-INCOTEST
PEC system since 1997 and has performed
more than 200 power plant projects to
measure wall loss with this equipment. Where
areas of substantial wall loss (at least 15%)
have been revealed by PEC, the locations and
significance of wall loss were accurate. In
areas of grooving (localized steep gradients),
the degree of wall loss was underestimated in
the PEC AWT thickness measurements. The
optimized PEC signals evaluated with the
Defect Algorithm methodology were closer
estimates to the scanning UT maximum wall
loss values.
APTECH
TP176
REFERENCES
[1] Chexal, B., and J. S. Horowitz, 1992,
Chexal-Horowitz Model for FlowAccelerated
Corrosion
in
CHECWORKS, 20th Water Reactor
Safety Meeting, Bethesda, Maryland.
[2] White, G. A., D. J. Gross, and T. M.
Cullen, 1996, Cost-Effective Monitoring
of Flow Assisted Corrosion at Fossil
Power Plants, EPRI Fossil Plant
Maintenance Conference, Baltimore,
Maryland.
[3] Chexal, B., et. al., 1998, FlowAccelerated Corrosion in Power Plants,
EPRI TR 106611 -R1.
[4] EPRI,
1996,
CHECUP,
a
CHECWORKS Application for FAC
Evaluation of Fossil Power Plants User
Guide,TR-107066
[5] EPRI, 1997, CHECWORKS Computer
Program Users Guide, TR-103198-P1.
[6] Bouchacourt, M., et al., 1998, Analysis
of 10 Years Feedback Concerning the
FAC Phenomenon at EdF, and
Maintenance Optimization by Means of
BRT-Cicero Code, French Nuclear
Energy Society International Symposium,
Fontevraud IV, Fontevraud, France.
[7] Garud, Y.S., Cohn, M. J., and de Raad,
J. A., 1999 Recent Developments in
Measurement and Evaluation of FAC
Damage in Power Plants, Corrosion/99,
San Antonio, Texas, Paper 353.
[8] Lara,
P.
F.,
1989,
Transient
Electromagnetic Method for Detecting
Corrosion of Conductive Containers
APTECH
TP176
Table 1
PEC Results for a Feedwater Heater
Row/
Col
72
66
60
54
48
42
36
30
24
18
12
C/L
12
18
24
30
36
42
48
54
60
66
72
0
1
0.555
0.567
0.560
0.569
0.546
0.532
0.538
0.539
0.535
0.536
0.541
0.548
0.541
0.546
0.556
0.543
0.539
0.545
0.538
0.533
0.541
0.559
0.557
0.581
0.555
0.595
0.592
0.590
0.576
0.566
0.520
0.516
0.503
0.516
0.532
0.530
0.548
0.658
0.661
0.547
0.544
0.532
0.518
0.537
0.544
0.554
0.566
0.584
0.593
0.587
0.595
0.596
0.585
0.569
0.566
0.528
0.523
0.534
0.528
0.555
0.791
0.786
0.776
0.768
0.775
0.551
0.514
0.531
0.523
0.538
0.551
0.558
0.595
0.596
0.570
0.564
0.581
0.577
0.565
0.569
0.536
0.546
0.547
0.559
0.778
0.759
0.526
0.536
0.526
0.543
0.561
0.560
0.592
0.592
0.556
0.523
0.547
0.541
0.532
0.548
0.490
0.527
0.517
0.730
0.796
0.780
0.506
0.513
0.520
0.528
0.544
0.543
0.571
0.546
0.537
0.535
0.552
0.542
0.534
0.513
0.512
0.460
0.510
0.504
0.757
0.785
0.762
0.497
0.506
0.470
0.533
0.514
0.541
0.540
0.555
0.567
0.552
0.562
0.557
0.525
0.497
0.539
0.528
0.728
0.774
0.770
0.514
0.536
0.516
0.527
0.535
0.539
0.554
0.556
0.555
0.581
0.592
0.589
0.561
0.540
0.532
0.565
0.555
0.580
0.756
0.737
0.548
0.564
0.557
0.552
0.588
0.594
0.573
0.583
0.578
0.612
0.590
0.571
0.566
0.549
0.535
0.561
0.570
0.583
0.577
0.587
0.771
0.776
0.787
0.771
0.591
0.575
0.580
0.553
0.563
0.583
0.597
0.594
0.597
0.590
10
0.596
0.588
0.589
0.567
0.550
0.535
0.567
0.556
0.584
0.582
0.579
0.577
0.617
0.689
0.585
0.594
0.586
0.594
0.577
0.579
0.595
0.606
0.600
0.612
0.598
11
0.604RAS3
0.609
0.598
0.581
0.547
0.538
0.569
0.573
0.591
0.611
0.609
0.595
0.592
0.588
0.602
0.597
0.591
0.588
0.581
0.592
0.603
0.609
0.613
0.599
12
0.572
0.593
0.602
0.577
0.633
0.532
0.562
0.555
0.600
0.610
0.612
0.594
0.579
13
0.593
0.594
0.596
0.560
0.610
0.525
0.590
0.552
0.599
0.611
0.610
14
0.594
0.611
0.603
0.573
0.545
0.519
0.555
0.562
0.593
0.618
0.615
37
LT .529
149
GE .529 to LT .5818
78
GE .5818 to LT .6045
27
GE .6045 to LT .665
23
GT .665
PIPING OBSTRUCTION
0.600
0.592
0.569
0.578
0.583
0.579
0.595
0.611
0.607
0.593
0.586
0.587
0.564
0.643
0.607
0.569
0.590
0.613
0.609
0.601
0.600
0.584
0.579
0.576
0.573
0.585
0.590
0.574
0.607
0.594
Average Reading:
0.58
Total Count:
314
inch
Minimum Value:
0.460
Reference Thickness:
0.605
inch
inch
0.529
inch
0.665
inch
APTECH
TP176
10
Table 2
PEC Results for Auxiliary Steam Line
BOILER PIPING, AUXILIARY STEAM: LOCATION 2-AS-6A (90 ELBOW) DEFECT MODE
ROW/COL
1
2
TEE
0.378
0.374
0.386-RUSP
0.378
TEE
0.367
VALVE
0.176
0.256
0.256
0.256
0.272
0.244
0.223
0.248
0.244
0.398
0.398
0.280
0.288
0.280
0.402
0.418
0.410
0.304
0.365
(ASSUMPTIONS)
PIPE
STAND
0.417
0.510
0.409
0.390
0.359
0.390
0.351
0.212
0.284
0.317
0.349
0.288
0.378
0.410
0.398
0.394
0.410
0.398
0.394
0.402
0.406
INTRADOS
LIMITATIONS
0.414
0.406-R90
0.394
0.394
0.398
0.382
0.394
0.398
0.398
0.382
0.398
0.414
0.402
0.341
0.374
0.390
0.365
0.386
0.406
0.410
0.357
10
0.304
0.374
0.365
0.317
0.386
0.333
11
0.309
0.345
0.329
FLOOR
UPSTREAM PIPE
WELD INFLUENCE
90 ELBOW
0.349
25
Rows
Ref
Min
Avg
16
1 to 4
0.386
0.176
0.321
19
5 to 11
0.406
0.280
0.375
15
>= 110%
76 readings
APTECH
TP176
11
Table 3
PEC Results for Superheater Spray Pipe AWT Mode
Col/Row
0.407
0.398
0.421
0.424
2
3
0.451
0.480R1
0.474
0.464
0.450
0.469
0.476
0.461
0.570
0.534
0.544
5
6
7
T
T
0.465
0.560
0.592
0.458
D
0.509
0.457
0.601
0.509
0.477
Horizontal of 3
inch Tee
0.449
0.480
0.421
0.358
0.358
0.339
Reducer 2x3
inch
10
0.430
0.406
0.397
0.404
11
12
13
0.438
0.455
0.435
0.415
0.426
0.429
0.409R2
0.408
0.411
0.409
0.396
0.393
5
10
11
13
7
Rows
1 to 9
10 to 13
Reducer 2x3
inch
Vertical of 3 inch
Tee
Ref
0.480
0.409
Min
0.338
0.393
Avg
0.469
0.416
46 readings
SPECIFICATIONS: TEE 3.50-INCH OD X 0.437-INCH NWT, MANUF MWT=0.382", 0.268-INCH CODE MIN.
SPECIFICATIONS: (2 EA.) 2" X 3" REDUCERS" 2.375-INCH OD X 0.343-INCH NWT, MANUF MWT=0.300", 0.182" CODE
MIN.
ROW 1 @ 8" U/S THE TEE
COL A ON TOP /NORTH
T = TEE GEOMETRY
D = DRAIN LINE
S = PIPE STAND HANGER
R1 = ROWS 1-9
R2 = ROWS 10-13
APTECH
TP176
12
Table 4
PEC Results for Superheater Spray Pipe DWT Mode
Col/Row
0.312
0.316
0.302
0.324
2
3
0.451
0.480R1
0.474
0.464
0.450
0.469
0.476
0.461
0.570
0.534
0.544
5
6
7
T
T
0.465
0.560
0.592
0.458
D
0.509
0.457
0.601
0.509
0.477
0.449
0.480
0.272
0.256
0.266
0.209
10
0.430
0.406
0.397
0.404
11
12
13
0.438
0.455
0.435
0.415
0.426
0.429
0.409R2
0.408
0.411
0.409
0.396
0.393
8
7
11
13
Rows
1 to 9
10 to
13
Horizontal of 3
inch Tee
Vertical of 3 inch
Tee
Ref
0.480
Min
0.209
Avg
0.440
0.409
0.393
0.416
46 readings
SPECIFICATIONS: TEE 3.50-INCH OD X 0.437-INCH NWT, MANUF MWT=0.382", 0.268-INCH CODE MIN.
SPECIFICATIONS: (2 EA.) 2" X 3" REDUCERS" 2.375-INCH OD X 0.343-INCH NWT, MANUF MWT=0.300", 0.182" CODE MIN.
ROW 1 @ 8" U/S THE TEE
COL A ON TOP /NORTH
T = TEE GEOMETRY
D = DRAIN LINE
S = PIPE STAND HANGER
R1 = ROWS 1-9
R2 = ROWS 10-13
At grid Locations D8 and D9, the measured defect mode values are slightly below the manufacturer's MWT values.
At grid Locations D8 and D9, the measured defect mode values are slightly above the code MWT values.
APTECH
TP176
13
APTECH
TP176
14
TP176
15
Business Units:
Power Generation Services
Nuclear Power Services
Petrochemical Oil & Gas
Forensic Engineering
Industrial Engineering
Offices:
Headquarters:
601 West California Avenue
Sunnyvale, CA 94086-4831
408.745.7000 Fax 408.734.0445
www.aptecheng.com
Mailing: PO Box 3440
Sunnyvale, CA 94088-3440
APTECH