Time Scehedule NPPTKB Project - Batam
Time Scehedule NPPTKB Project - Batam
No
Description
Qty
Unit
Mobilization of Equipment
1.00
Ls
Preparation On Site
1.00
Ls
51,480.00
51,480.00
Demobilization
Note :
Production 5 pile / day / rig ( We use 8 rig )
2,880.00
1.00
Joint
Ls
I
1
II
3
II
3
IV
1
Remark
No
Equipment
Brand / Type
Capacity
Quantity
Piling Rig
Nissha D408
40 Ton
Service crane
P& H 335 AS
35 Ton
Diesel Hammer
DD 63
6.3 Ton
Hydraulic Hammer
NH 70
7 Ton
Note :
All of equipment will be prepared for 2 weeks before the Mobilization to project site
Remark