Bill of Quantities: Kalipayan Drainage System 217.00

You might also like

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 2

Bill of Quantities

PROJECT

Drainage

LOCATION

Kalipayan

TYPES OF STRUCTURE :

Drainage System

FLOOR AREA

217.00

ITEM
NO.
I.

II.

III.

DESCRIPTION

ln m

UNIT

QTY

Unit price

Amount

GENERAL REQUIREMENTS
1

Mobilization / Demobilization

lot

1.00

Temporary Facilities

lot

1.00

Safety Requirements

lot

1.00

Testing and Commissioning

lot

1.00

As-Built Construction Plans

lot

1.00

Hauling and Disposal of Waste Material

lot

1.00

Construction Billboard

lot

1.00

CIVIL AND SITE WORKS


1

Demolition of existing Drainage

Excavation

Gravel Bedding

Clearing and Grabbing

MASONRY WORKS
A.

1.00

lot

lot

1.00

cu.m.

88.00

cum

20.00

lot
###

1.00
sq m

Material Cost
CHB 4"

Pcs

Cement

bags

70.00

Sand ,washed

cu.m

4.00

Gravel 3/4"

cu.m

8.00

3,300.00

Total cost for materials


B.

Labor Cost

Total cost for labor


IV

PLASTERING WORKS
A.

###

sq m

Material Cost
Cement

bags

70.00

Sand ,washed

cu.m

4.00

Total cost for materials


B.

Labor Cost

Total cost for labor


V

CONCRETE WORKS
A.

35.00 cu m

Material Cost
Cement

bags

350.00

Sand ,washed

cu.m

17.00

Gravel 3/4"

cu.m

35.00

Total cost for materials


B.

Labor Cost

LS

1.00

Total cost for labor


C.

Equipment Rental
1-Concrete Mixer

days

15.00

Page No. 1

ITEM
NO.

DESCRIPTION
1-Concrete Vibrator

UNIT
days

QTY

Unit price

Amount

15.00

Total cost for Equipment


D.

Fuel & Oil

LS

1.00

Total costfor Fuel and oil


VI

REINFORCING STEEL
A.

kgs.

3,925.00

Deformed bar

kgs.

3,925.00

Tie Wire

kgs.

40.00

1-Unit Cut-off Machine

days

8.00

1-Concrete Vibrator

days

8.00

Lot

1.00

coco lumber

Lot

300.00

CWN Assorted

kg.

20.00

Material Cost

Total cost for materials


B.

Labor Cost

Total cost for labor


C.

Equipment Rental

Total cost for Equipment


VII

FORMWORKS
A.

Material Cost

Total cost for materials


B.

Labor Cost

Total cost for labor


TOTAL DIRECT COST
TOTAL INDIRECT COST
TOTAT BID AMOUNT
TOTAL BID AMOUNT (in word):
NOTE:
1. Total Cost of Line Item includes cost of contractors profit, Tax and OCM.
2. A detailed estimate should be attached to show derivation of unit cost.

Page No. 2