COMPLETION REPORT
OPEN HOLE LOGGING
Well Name : BTJ-206
Report By
WELL-TECH
I.
WELL INFORMATION
BTJ-206 is the name of the third well of Pertamina PBMSJ in Betung, Jambi. From
the picture below, we can see the location mark with A. This location is in Sumatra island.
Coordinat Loacation :
South : 870 5 7.176
East : 580 20 37.844
BTJ-206
BETUNG
JAMBI
Vertical Drilling
Development Well
Production Well
L2, L3, L4, L6, L7, and L8. Benakat Water
Formation
535 m
350 HP Land Rig, Mobile Truck Mounted
5 m from ground level
64 m from sea water
WELL-TECH
II.
EQUIPMENT INFORMATION
We use Skid Unit with serial number ESSS 9724 in this location. For downhole tools, we can
see the information below :
No.
Description
Serial Number
Insulation Bar
EIST63
281014
SY XJ,11-0803 SY XJ1108-04
3 EA
Swivel tool
EPLT61XA
281016
73678
2 EA
ERMT61XA
292421
260115
2 EA
Temperature/Tension/Fluid Resistivity
Sub
Remote Transmitting Tool
ERTT71XA
292411
270003
2 EA
EDST61XA
281276
281277
2 EA
ECNT62XA
270058
260215
2 EA
EZDT61EA
281295
260180
2 EA
EZDT61MA
281295
260180
2 EA
EIST61XA
281004
281001
2 EA
EDLT72EA
270082
270086
2 EA
EDLT72MA
270084
2103086
2 EA
EMSF61XA
272407
5302908
2 EA
EDAT61EA
EDAT61MA
270072
270072
292171
292171
2 EA
2 EA
EDAT61FA
270072
292171
2 EA
ASSET NUMBER
Qty.
Isolation Sub
9
Dual Laterolog Tool
10
11
12
13
ESAT61XB
ECCL61XA
280895
270098
260145
270104
2 EA
2 EA
14
Knuckle tool
EKJT61XA
280965
HE070203
2 EA
15
GR/CCL tool(1392XA)
GR/CCL
16
2315XA
17
2312XA
YN-04
2 EA
18
N/A
N/A
CCL05125210
N/A
19
ERSC
20
Sink Bar
N/A
N/A
N/A
1 EA
1 EA
WELL-TECH
For radioactive source we use in this location we can see in table below :
Item
1
2
3
4
5
Isotope name
Ice Block
Neutron Source
Density Source
GR Calibrator
JIG Block
R/A Substance
Am-241Be
Am-241Be
Cs-137
RA-226
Cs-137
Intensity
400mCi
18Ci
2.5Ci
2.5Ci
500/40Ci
Source No
7220NN
83464B
77794B
DA-377
CSII-0275,CS0260
Qty.
1ea
1ea
1ea
1ea
1ea
Description
QTY
Unit
Ea
Power Pack
Ea
Generator
Ea
Blue Box
Ea
Source Container
Ea
Tool Basket
Ea
Material Container
Ea
Compressor
Ea
Ea
10
Cable Drum
Ea
11
VSP Box
Ea
All equipments are still in good condition when arrived in location. We didnt get any
problem when we do check tools.
WELL-TECH
III.
PREPARATION
After arrived at location, we contact the geologist or company man to get job
programmes so we can know and arrange our plan to all crew before job.
We must do Pre Job Safety Meeting with safety officer in wellsite, we also give them JSA.
Before job we must pay attention to all of our tools condition because if some tools error
when we run logging, it will be big problem for us.
Make sure we check the tools condition for main tools and backup tools. We must use the
tools in best condition. After that give some mark on it, so easy for us to pick those tools
when we want to do our job.
Check the cable head condition (continuity and insulation) and pump some grease to
prevent the water enter into it. If neccesary, make another cable head as a backup.
Make sure diesel oil for our generator is enough until our job finish. Fill the tank until
full. If something happend to our tools, find out the cause of the problem and try to fix it.
Make sure all the auxiliary tools is good condition and ready to use. Put the auxiliary
tools in proper place so we can easy to use when we do our job.
Make sure the radioactive source and calibrator in good condition and place it on the
safe area from people.
As an engineer, we have to make sure our unit inside the cabin in good condition,
check the LSP make sure the insulation and continuity test produce good result. Beside that,
we also make sure for another panel must be in good condition.
Make sure our computer also in good condition, and screen can be used for our job.
After all the stuffs above is done, then we are ready to do our job.
Before job, we must contact the geologist to confirm the sequence and the tools they
need to logging. After confirm we just wait the information from company man to start the
logging job. After we get information from company man, we go straight to location and
prepare the tools and rig up.
We set the skid unit straight to well. Remember the position must be straight, so our
cable can easy to move.
We ask for crane operator to move our tools in basket next to catwalk and pick our
tools from basket one by one and lay those down on catwalk. While doing that another
WELL-TECH
operators can pull the wireline cable from cable drum and form it become 8 on the ground
as much as neccesary.
Move all the rig up equipments to drilling floor, set the upper and lower sheave wheel
and thighten the lower sheave wheel with proper chain on BOP. Make sure the tension cable
on tension device can bring tension information to our computer. Also make sure the speaker
is work. Prepare the clamp, make up table, spaner, and grease and put in proper place on the
drilling floor.
After finish now we can connect our tools to start our job.
Here are JSA when we want to do our Job.
WELL-TECH
V.
OPERATION PROCEDURES
Interval (m)
0 - 50
50 400
Bit (inch)
12
Casing
(inch)
9-5/8
Mud Properties
Logging Job
Type
SG
Visc
Pre-Hydrated
Gel
8.4 - 8.5
35-40
Not Required
45-50
DLL-MSFL-GR-SP
Sonic, Densitiy,
Neutron, Caliper,
KCL PHPA
Polymer
8.4 - 8.6
PV/YP
15-20/18-25
CBL-VDL-GR-CCL
Picture beside show the interval we must do the logging job. There only 1 interval as seen in
the picture.
46.8 m 545 m1
Section 1
WELL-TECH
SECTION 1
: 8 inch
Job
Time Of Job
Section 1 is 8 in Open Hole. TD is set at 535 m and the previous casing shoe at 46
m. Logging sequence was based on client request start from Resistivity log, Radiocative and
Sonic log, and the last was CBL-VDL.
CBL job was held in defferent time after they set 7 casing along this interval.
(1).
Resistivity Log
Here are the list of tools we use when we do resistivity log
Tools
Serial Number
Asset Number
SP
EIST63
SY XJ,11-08-03 / SY XJ11-08-04
ESWT
ESWT61XA
3944XB 73678
ERMT
ERMT61XA
292421
ERTT
ERTT61XA
292411
EDST
EDST61XA
281276
EIST(28)
EIST61XA
281004
EDLT
EDLT71XA
270082
EMSFL
EMSFL61XA
272407
WELL-TECH
While the operator connect the resistivity tools, we load the calibration and
verification data for our tools in ELIS computer. Also we put some data about
Wellsite information and fill some information in Proccessing Parameters. These are
important engineering things we should never forget. Another thing we must ask
report about mud properties from Mud Engineer at wellsite, we also request for
sample of Rm, Rmf and Rmc and after that we must measure those values.
Those data are :
Rm@78F = 0.48, Rmf@78F = 0.1 and Rmc@78F = 0.85.
After operator complete the tool string connection, then we can power on our tool
string, make zero point and after that we can start our job.
Logging Job :
WELL-TECH
Casing logger @ 46 m
From that result we can see that Rmsfl is separated with Rd and Rs. But Rd and Rs
itself have small separation. We can assume the permeability of this formation is not
so good
WELL-TECH
(2).
Serial Number
Asset Number
ESWT
ESWT61XA
3944XB 73678
ERMT
ERMT61XA
292421
ERTT
ERTT61XA
292411
EDST
EDST61XA
281276
ECNT
ECNT73XA
270058
EZDT
EZDT71XA
260780
EDAT
EDAT61XA
270072
Before we do this job, radioactive source must be placed at the proper spot on the drill
floor so is makes easy for operator to install or uninstall the source. Dont forget to
prepare the cover to prevent something down fall into the hole.
Before install the source, make sure the source chamber of CNT and ZDT in clean
condition. If not, then we must clean it first. The direction of CNTs decentralizer and
ZDTs caliper also must be same.
We also put the rubber stand off at EDAT upper and bottom body.
After that, install the source from CNT to ZDT. If uninstall from ZDT to CNT.
Make sure we already set the police line arround the well so nobody can come closer
to the well. Also for operator who install or uninstall the source, he must wearing the
protector to cover his body.
After Install, now we can Power On the tool string, make zero point at ERMT and
after that RIH the tools.
Logging Job
While RIH, we must catch first arrival wave along the cased hole (DT24 arround
57s/ft) by set the gain and other parameters like search window and threshold to
certain value. After pass cased hole, we also keep to catch first this arrival wave. After
reach TD we open the EZDT caliper and start to record up untill passing casing shoe,
and after reach the cased hole we stop pull out the tools and make verification for
EZDT caliper.
WELL-TECH
Logging Result
From the logging job we get result like some pictures below
From both pictures above we can see there is no crosplot between density-neutron log
along this interval.
Along the collapse hole interval we can see that density is acting like have small
density, but in the smooth hole the value of density become normal again.
Sonic log is stable along this interval because we catch good arrival wave.
WELL-TECH
(3).
Serial Number
Asset Number
ESWT
ESWT61XA
8302307
ERMT
ERMT61XA
292366
ERTT
ERTT61XA
270245
EDST
EDST61XA
270040
EDAT
EDAT61XA
292179
After set casing 7 we run CBL and VDL job. We use rubber stand off on EDAT so
the movement of the tools become smooth while rocord up and we can get better data.
After operators connect the tools, we can power on, set zero point and RIH.
Set the Search window at the first wave and observe the AMP3 data along the casing
hole interval.
Before record up fill the data we get in Max Observed Amp and then fill 100 in
Target Amplitude. After that we can start to record up until surface.
Logging Result
Here are some pictures about CBL and VDL
is
already
WELL-TECH
WELL-TECH
V.
TROUBLE ISSUE
Before do the job, we check our downhole tools condition and we found that there is
no problem with our tools. All the tools was in good condition.
The only one problem was bad reading of our cable head, and after checked it comes from
torpedo, one cable already broken, so we make a new torpedo. After that the reading is good
again.
WELL-TECH
VI.
CREW EVALUATION
Hendrik Sahertian
Operator
This time after we arrived in Jambi, we strightly go to location because our job will be
start after several hours. All operator actually ready with this condition and even we are tired,
we can do our job correctly.
Before we do our job, we checked our tools condition and found that torpedo is not good,
because bad reading continuity.
I wish Mr Qian can respons quickly to solved this problem because our job will start in a few
moment, but he didnt. Maybe next time, he can do better.
Bagus have good attention to this job, he dirrectly take responsibility to make new torpedo
and helped by Antoni and Dika.
Kesyanto still new and must learn about the whole operation in location. He still looks
confuse about how to do, but i think he learn about this. Me and others already try to explain
how to do our job effectively.
WELL-TECH
VII.
1. Both open hole and cased hole job is done without any problem. We have good
communication with client and they satisfy with our service.
2. Both Main and Backup computer in Skid Unit ESSS9724 salready in English for
ELIS Software, i wish all of our unit will be like this.
3. From the begining until job finish, there are no injuries among our crew. We have
to pay attention to this and try to do something with safety first so the risk of
injuries is small every time we do our job.