MONTHLY REPORT

of
Port Authority Implemented Projects
% Completion
Proj. #

Project Name

Location

Category

prev

Curr

% Expenditure
prev

Curr

Month Ending February 2007

Variation to date
Expenditure to
date

Contract Sum

prev

Projected
Completion Sum

Curr

Scheduled
(Contract)
Completion
Date

Projected
Completion
date
Comments
Following the completion of the designs
the scope of work origainlly included in the
contract has been reduced to that of
project engineer.The PAJ Engineering
department will be resposible for the
monitoring and supervision of the project.
Contract to be awarded as soon as PAJ
received Cabinet Approval.

283

MBFZ Infrastructure Design

Port Authority of Jamaica Projects

Bogue estate, Montego Bay

Civil Works

65%

69% $

5,855,160.63

8,500,000.00

### $

8,500,000.00

30.05.09

Prepared by..Development Engineering Unit.