I.

Scope of Works
1. Mobilization - 10,000
2. Working Permits
3. Welding Works - 40,000
4. Masonry Works - 40,000
5. Electrical/Houskeeping - 30,000
6. Preparation/layout of working areas
7. Layout of Concrete Pillar
8. Fabrication of steel trusses
9. Painting of steel trusses

125,000

10. Layout of concrete flooring

11.
12.
13.
14.
15.

Hauling & Assembly of Steel Trusses


Installation of electrical works
Installation of roof
Commissioning - 5,000
Demobilization - 10,000

II. Materials
114,700
1. Sand - 80bags - 4,000
2. Cement - 40bags - 10,000
3. Gravel - 120bags - 8,000
4. Steel Round Bar - 12mm -45 pcs 10mm - 30pcs - 15,000
5. Angle Bar - 2"x2" - 20pcs - 1 1/2"x1 1/2" - 40 pcs - 35,000
6. Explosion Proof Ligting Fixtures - 2pcs - 20,000
7. Electrical Wires, Conduits & Switches - 2,500
8. Redoxide paint - 3,600
9. Color Roof - 2,500
10. Latex Paint - 3,600
11. Lumber & Plywood - 10,000
III. Miscelleneous
1. Service vehicle - 10,000
2. Consumbales - 10,000
3. Lodgings - 20,000
4. Tools/PPE/Equipment - 15,000
Work duration - 10 days
Manpower - Welder -2
- Mason - 4
- Steelman - 2
- Electrican - 1
- Helper - 2

Total
Vat
Grand Total

55,000

294,700
35,364
330,064

Total Manpower - 11