January 25, 2016
North Loop
Road: OPEN
Bloomber g
Cent er
South Loop
Road: CLOSED
CAMPUS
CONSTRUCTION
START
FINISH
STATUS
Goldwater Demolition
Jan 2014
Jun 2015
Complete
Dec 2014
Nov 2016
Ongoing
Mar 2015
Aug 2016
Ongoing
Bloomberg Center
Mar 2015
Apr 2017
Ongoing
Co-Location Building
May 2015
May 2017
Ongoing
Residential Building
Jun 2015
Jul 2017
Ongoing
The Bridge
(Co-Location)
Bloomberg
Center