Professional Documents
Culture Documents
Presentation On Commissioning of CFBC Boiler
Presentation On Commissioning of CFBC Boiler
Hydro Test
Commissioning Checkpoints
Chemical Cleaning
ACTIVITIES OF COMMISSIONING
Steam Blowing
Steam Dumping
Synchronization
ACTIVITIES OF COMMISSIONING
Pressure parts
approximately 7 - 8ksc
The purpose of air leak test of air, gas ducting & ESP
is to ensure leakage proof in ducts, welding joints,
flange joints to ensure efficient operation of fans,
boiler
Hydro Test
subjected
to
high
operating
pressure
during
Commissioning Checkpoints
Checklist have to be prepared for all equipments and
all activities.
shall commence
ID fan
PA fan
SA fan
Feed pumps
Fuel feeders
Chemical Cleaning
scale etc.
Chemical Cleaning
The
The
Check
the
following
equipments
are
having
interlocks
Check
the
following
equipments
interlocks
are
having
Check
the
following
equipments
interlocks
are
having
air flows
Start up sequence
Steam Blowing
Steam Dumping
Steam Dumping
Synchronization
Synchronization
is
nothing
but
matching
the
of the plant is
allowed
plant
and
after
tripping
to
be
For
of the boiler,
For
any
trouble
shooting
of
the
performance deviations
boiler
for