Ref No.

: 8521/CSPD/ACC

Date: 28/12/2015

NATIONAL GRID, SA
CENTRAL OPERATING AREA
P.O. BOX. 57, RIYADH
Kind Attn.

Engr. Ahmed Al Jaffin


Division Manager-Substation projectsCentral Region,
National Grid, SA

Project

: Construction of 132/13.8kV Substation # 8521 in Shaqra University

Subject

: Modification at 132KV GIS Scheme VT Segregation for Core 1 & Core 2


supervision Snag A

Dear Sir,
With reference to the above-mentioned which is evaluated as snag of A category,
we need to highlight the following:
1) This is not mentioned in either PTS or Protection requirements.
2) ACC got approved PLD, Base Design & Detailed Design for the existing scheme.
3) The existing VT status (Core 1 & Core 2 supervision is common) is not affecting
the energizing.
4) This is a complex modification will affect the approved scheme which has a time
impact will lead consequently to major time delay affecting the energizing date.
ACC is looking for NG support as ACC will never successfully complete its job without
NG support.
As per the above highlighted points, please support us to close such snag.
P.S
Attached Snag description as per PL#15

With Best Regards,


Engr. Abdul Majid Atiyah
Power Chief Manager