PLACE VISITED

START DATE

START TIME

END DATE

Sattenapally
Sattenapally
TummalaCheruvu- Sattenapally
Sattenapally
Gurajala
Macherla
TummalaCheruvu
Sattenapally
Macherla
***No WorK***
***No WorK***
Sattenapally PE
***No WorK***
Macherla-Peddavura
***No WorK***
Piduguralla
Piduguralla
Pidugurallla
***No WorK***
Macherla-Jahnpahad
Jahnpahad
Rajupalem
Vishnupuram(RTA Check Post)
Vishnupuram(RTA Check Post)
Sattenapally & Vishnupuram
***No WorK***
Gurajala-Jahnpahad
Piduguralla & Rentachintala
Chowtapapayapalem
Sattenapally

1/11/2015
2/11/2015
3/11/2015
4/11/2015
5/11/2015
6/11/2015
7/11/2015
8/11/2015
9/11/2015
10/11/2015
11/11/2015
12/11/2015
13/11/2015
14/11/2015
15/11/2015
16/11/2015
17/11/2015
18/15/2015
19/11/2015
20/11/2015
21/11/2015
22/11/2015
23/11/2015
24/11/2015
25/11/2015
26/11/2015
27/11/2015
28/11/2015
29/11/2015
30/11/2015

9:00AM
9:00AM
9:00AM
9:00AM
9:30AM
8:30AM
10:30AM
9:00AM
9:00AM

1/11/2015
2/11/2015
3/11/2015
4/11/2015
5/11/2015
6/11/2015
8/11/2015
8/11/2015
9/11/2015
10/11/2015
11/11/2015
13/11/2015
13/11/2015
14/11/2015
15/11/2015
16/11/2015
17/11/2015
19/15/2015
19/11/2015
20/11/2015
21/11/2015
22/11/2015
23/11/2015
24/11/2015
26/11/2015
26/11/2015
27/11/2015
28/11/2015
29/11/2015
30/11/2015

9:00AM
8:30AM
8:30AM
9:00AM
10:00PM
8:30AM
9:00AM
9:00AM
9:00AM
9:00AM
9:00AM
9:00AM
9:00AM
9:30AM
8:30AM

END TIME TOTAL HR

BUS/TRAIN

7:00PM
6:00PM
10:00PM
6:30PM
6:00PM
5:00PM
7:30AM
6:30PM
5:00PM

75
75
150
75
75
75
150
75
75

Locator at Sattenapally for reliance work


Sattenapally & Tummala Cheruvu Work
Tummalacheruvu work & Sattenapally Cut(vennadevi)
Locator at Sattenapally for reliance work
Gurajala water pipeline work
Locator at macherla defence work
PE at tummala cheruvu
Sattenapally Work
Locator at mahcerla

7:00AM

150

Anupalem JCB work & Sattenapally PE

5:30PM

75

Locator at Peddavura & Macherla

5:00PM
5:30PM
7:00AM

75
75
75

Cable Cut at Piduguralla


Cable Pulling at piduguralla
PE at Piduguralla

7:00PM
5:00PM
5:00PM
6:00PM
6:00PM
5:00AM

75
Macherla Locator, cable cut at vishnupuram n jahnpahad
75
Jahnpahad 48 Splicing & Chamber work
75
Chambers Work at Piduguralla & Rajupalem
75
Cable Pulling Work at RTA Check Post
75
Cable Pulling Work at RTA Check Post
150
48 Splicing at Vennadevi & OTDR reports at Sattenapally ,PE at Vishnupuram

6:00PM
6:00PM
5:30PM
6:30PM

75
75
75
75

TOTAL HR(DA)
Bus bill total
Auto BILL
Phone Bill
TOTAL
PREPARED BY
P.HEMANTHKUMAR

PURPOSE

OTDR reports at Srinagar Jahnpahad Gurajala


Piduguralla OTDR &rentachintala Chambers
Cable cut b/w Piduguralla - Sattenapally
Locator at Sattenapally for reliance trench work

2100
0
200
250

2550