CONTOH Perhitungan Alignment Vertikal
CONTOH Perhitungan Alignment Vertikal
Keluwesan bentuk :
Lv = 0,6 . V = 0,6 . 80 = 48 m
Drainase :
Lv = 40. A = 40 . 0,193 = 7,72 m
Jadi, Lv1 = 48 m (diambil yang terbesar)
Elevasi dan stationing :
Elev.PLV1 = Elev PPV1 + (g1. Lv1)
= 15,63 + (0,193% . 48 )
= 15,68 m
STA PLV1 = STA PPV1 - Lv1
= 1500 - 48 = 1476 = 1+ 476
Ev1 =
A Lv 0,193.48
0,012m
800
800
Keluwesan bentuk :
Lv = 0,6 . V = 0,6 . 80 = 48 m
Drainase :
Lv = 40. A = 40 . 0,125 = 5 m
Jadi, Lv2 = 50 m (diambil yang terbesar)
A Lv 0,125.50
0,008m
800
800
Keluwesan bentuk :
Lv = 0,6 . V = 0,6 . 80 = 48 m
Drainase :
Lv = 40. A = 40 . 0,339 = 13,56 m
Jadi, Lv3 = 48 m (diambil yang terbesar)
Elevasi dan stationing :
Elev.PLV3 = Elev PPV3 + (g1. Lv3)
= 13,00 + (0,125% . 48 )
= 13,03 m
STA PLV3 = STA PPV3 - Lv3
= 4600 - 48 = 4576 = 4+ 576
Elev.PTV3 = Elev PPV3 + (g2. Lv3)
=13,00+ ( 0,214 % . 48 )
= 13,05 m
STA PTV3 = STA PPV3 +- Lv3
A Lv 0,339.48
0,020m
800
800
5.
Keluwesan bentuk :
Lv = 0,6 . V = 0,6 . 80 = 48 m
Drainase :
Lv = 40. A = 40 . 0,214 = 8,56 m
Jadi, Lv4 = 50 m (diambil yang terbesar)
A Lv 0,214.50
0,013m
800
800
Keluwesan bentuk :
Lv = 0,6 . V = 0,6 . 80 = 48 m
Drainase :
Lv = 40. A = 40 . 0,182 = 7,28 m
Jadi, Lv5 = 50 m (diambil yang terbesar)
A Lv 0,182.50
0,011m
800
800
0,182%
PPV6
STA 8 + 500
+ 14,00 m
Keluwesan bentuk :
Lv = 0,6 . V = 0,6 . 80 = 48 m
Drainase :
Lv = 40. A = 40 . 0,182 = 7,28 m
Jadi, Lv3 = 48 m (diambil yang terbesar)
Elevasi dan stationing :
Elev.PLV6 = Elev PPV6 + (g1. Lv6)
= 14,00 + (0,125% . 48 )
= 14,03 m
0%
F
STA 10 + 380,402
+ 14,00 m
A Lv 0,182.48
0,011m
800
800