Professional Documents
Culture Documents
Construction Methodology PDF
Construction Methodology PDF
Construction Methodology PDF
CISMHE
16
CONSTRUCTION METHODOLOGY
16.1
INTRODUCTION
Hirong Hydro Electric Project is located on river Siyom in West Siang district of
Arunachal Pradesh. The Project envisages construction of a concrete gravity dam 133.5 m high, a
9.2 km long Head Race Tunnel, a 15 m diameter Surge Shaft, two underground pressure shaft
bifurcating into four near an underground Powerhouse to generate 500 MW. Considering the
seasonal variation, the working season of seven months starting from mid October to mid May
every year has been considered while preparing the construction programme especially for the
project works in the open. Underground works have, however, been considered as continuous
even during the monsoon season though with a slow rate of progress on account of practical
problems in movement of heavy machinery and vehicles carrying men and material. Construction
Programme and selection of methodology with the planning for equipment has, as such, been
worked out keeping above site constraints in view. The project has been planned to be
commissioned in a period of six and half years (78 months) including period for completion of
infrastructure development works.
16.2
COMMON EQUIPMENT
For construction of this project, main common equipments are Aggregate Processing
Plant, Batching Plant and Concrete cooling arrangement. These are common for all civil works.
In addition to this, diesel captive power is also amongst common facility. However, this has been
dealt with in Infrastructure chapter because diesel generating capacity is designed not only for
civil works but also for garage and workshops etc.
16-1
CISMHE
As worked out above the APP having capacities of 500 TPH on left bank located at dam
site, 100 TPH APP will be located at Powerhouse site near MAT portal and 60 TPH APP will be
located near Diversion Tunnel portal.
FE Loader 3 cum
5 (2 at Quarry + 3 at APP)
5 (2 at Quarry + 3 at APP)
2 (at Quarry)
2 (at Quarry)
14 (6 at Quarry + 8 at APPs)
Three CBPs (CBP1, CBP2, CBP3) and CBP6 will be required to match with the APP-1
and APP3. For APP-1 works, three CBPs, (CBP-1, 2 and 6), one of 300 cum/hr, second of 30
cum/hr and third 30 cum/hr capacity will be deployed. For APP-3 works one CBP-2 of 30 cum/hr
Hirong H.E. Project, Arunachal Pradesh
16-2
CISMHE
shall be deployed. For APP-2 works two CBPs one 30 cum/hr (CBP-4) and second 60 cum/hr
(CBP-5) capacity CBP will be deployed. The location of the CBPs are given here in below:
16.3
DIVERSION ARRANGEMENT
The Hirong HE Project envisages construction of a Concrete Gravity dam having its
anticipated deepest foundation at 1225m with top of dam at 1358.50m. Thus the height of dam
from the deepest foundation level is 133.50m. Diversion arrangement for construction of
concrete gravity Dam of Hirong HE Project comprises of:
i).
A Diversion Tunnel 10.15m dia Horse-shoe (modified) shaped, concrete lined and 473m
long.
ii).
iii)
An Upstream concrete coffer dam with top at 1251m, 65.6m long at top.
iv)
A Downstream concrete coffer dam with top at 1242m, 50.4m long at top.
In view of the better geology on the right bank of river Siyom, the diversion arrangement
has been planned on the right bank. The left bank is readily accessible and to have access to right
bank, a bridge on river Siyom along with access roads will be needed. However to take up the
construction of adit and DT, the equipment will be taken on the right bank in dismantled
condition by barges and by the time the excavation has been done, the access to this bank would
be established.
ii).
Establishment of junction of Adit and DT such that the invert of adit at the tunnel grade is
at 1239.659 i.e. the benching level of DT.
iii)
Excavation of heading of DT both towards u/s and d/s side and leaving a rock plug at
both the u/s and d/s portal ends.
16-3
iv)
CISMHE
Regarding of adit invert in a length of about 36m to meet the invert of DT at the junction
i.e. 1236.609 m elevation
v)
vi)
The structures at the inlet and outlet of DT to be established along with the activity 1
above during non-monsoon period after making ring bunds
vii)
viii)
Removal of u/s and d/s plugs in DT, which were left earlier.
ix)
x).
Construction of plug at the junction of DT and adit (before diverting river water into the
DT)
16-4
CISMHE
accordingly the minimum excavated dia as well as excavated vertical dimension will be 10.95m
with 8.0m base width. The excavation and lining of diversion tunnel will require about 12
months as such at least one monsoon season resulting in high water levels / flows in the river
Siyom has to be faced by the under construction diversion arrangement. The drilling of holes will
be done by Two Boom Hydraulic Jumbos. Haulage of excavated material shall be done by a
combination of 2.5 cum side dump loader and 20 ton capacity rear dumpers.
16.3.5 Ventilation
At the time of excavation of tunnels, adequate provision for proper ventilation is
absolutely essential, therefore an effective ventilation arrangement has been planned during
execution of Adit and DT. It is proposed to provide two fans ZVN-1-14-110/4 in series with a
circular ventilation duct of 1.4 dia. As soon as the tunnel is through, ventilation will not be
required. Following criterion have been adopted for provision of ventilation arrangement.
While the overt lining for the downstream reach is in progress, simultaneously the invert
laying in the upstream reach would be carried out. After the completion of overt lining on the
downstream side the shutter would be moved from downstream side to the upstream side, where
the invert would have been laid by then for the length of the reach such that it can accommodate
the shutter easily. At the time of execution of Diversion Arrangement, it is planned to set up a
Concrete Batching Plant of 30 m3/hr capacity and to cater for the requirement of Aggregate, an
Aggregate Processing Plant of 60 TPH (APP-3) shall be provided nearby CBP (CBP-2). At the
time of construction of Diversion Arrangement, an weighted average lead of about 1.2 km has
been considered from CBP-2 to the Portal of Adit to Diversion tunnel.
16-5
CISMHE
supported with the help of rock bolts / ribs as the case may be. Then the invert for this reach
would be laid. While the shutter for the lining in the reach occupied by the downstream rock
plug is being erected, the upstream rock plug would be removed by excavation in heading and
benching.
Removal of overburden material and excavation for Portals at the Inlet and Outlet ends of
DT
ii).
iii).
Raising of 4m high earthen ring dyke for the inlet structure and 3.5m high for the outlet
structure.
iv).
Reinforcement and Concreting for the walls of the Box RCC structure duly fixing the first
stage embedment of gates
v).
vi).
vii)
viii)
ix).
x).
xi)
xii)
Erection of the first stage embedment (anchor bolts) in the blockout left in the RCC walls.
ii).
Each set of guides, and seal seat arrangements shall be assembled in the respective
blockouts, secured in place by anchorages.
iii).
iv).
16-6
v).
vi).
Suitable Hoisting arrangement shall be installed at 1262 m. for Inlet and 1253m for
CISMHE
Outlet.
16.3.10 Plugging of Adit
The Diversion Tunnel has to be ready for diverting the river water along with plugging of
Adit before the Earthen dykes for concreting of closure of coffer dams is taken up. At the same
time the last few activities in the diversion tunnel which are removal of rock plugs, concrete
lining of the respective reaches upstream and downstream along with contact / consolidation
grouting have to be completed prior to commencement of work on the construction of earthen
dykes. These earthen dykes would be constructed for closure of coffer dam only after the
diversion tunnel is fully ready for passing of the diverted water of the river i.e. the Diversion
Tunnel is complete in all respects and the Adit has been plugged.
For the closure of the coffer dams, earthen dykes would need to be constructed. From the
water availability series evolved for the Hirong HE Project it is seen that maximum 10-daily
inflows during the Jan, Feb and March months are 94.60, 125.42 and 102.34 cumecs. As such the
closure of the coffer dams has to be planned during the months from January to March.
16.4
up to sound rock profile (b) Treatment of shear zones, if any (c) Laying of concrete in lifts of 2.0
m thickness (d) Consolidation grouting (e) Curtain grouting (f) Drainage holes (g) Laying of
spillway bridge (h) Erection of hydro mechanical equipments.
16-7
CISMHE
1,19,733 m3
2.
Rock excavation
1,74,003 m3
1,02,114 m3
2.
Rock excavation
1,06,652 m3
Left Bank excavation between dam blocks and trajectory impact pit
1.
2.
Rock excavation
88,985 m3
1,04,461 m3
Excavation for Road between dam blocks and trajectory pit on left and right bank
1.
30,402 m3
2.
Rock excavation
36,074 m3
3,41,235 m3
2.
Rock excavation
4,21,191 m3
2.
Rock excavation
3,762 m3
11,964 m3
11,16,093 m3
1,300 m3
11,17,393 m3
20,277 m3
The civil works for Main Dam and Intake are planned to be executed in five working seasons.
i)
ii)
iv)
iv)
v)
16-8
CISMHE
i).
2 Nos.
ii)
20 t capacity dumpers
9 Nos.
iii)
4 Nos.
iv)
4 Nos.
v)
2 Nos.
vi)
2 Nos.
vii)
2 Nos.
viii)
2 Nos.
ix)
4 Nos.
16-9
CISMHE
x)
Silo Buses
10 Nos.
xi)
2 Nos.
xii)
3 Nos.
xiii)
6 Nos.
xiv)
2 Nos.
xv)
2 Nos.
xvi)
2 Nos.
xvii)
2 Nos.
2 Nos.
2 Nos.
xx)
2 Nos.
xxi).
16.5
2 Nos.
The total length of the 7.5 m dia (finished) circular shape Head Race Tunnel, aligned on
right bank of river Siyom is 9202 m. Tunnel with a circular shape will be concrete lined having a
finished diameter of 7.5 m. The alignment of tunnel has been fixed in such a way that adequate
lateral and vertical rock cover is available at any particular location.
16.5.1 Infrastructure
In order to access the work sites on right bank from the BRO road on the left the
following basic infrastructure is required to be in place before taking up the tunnel excavation.
Two no. bridges of approximately 60 m and 80 m span shall be needed to access the Adit
locations. One steel girder bridge of 80 m span is proposed to be erected on river Siyom near
Powerhouse location at an Elevation of 1040 m. A suitable diversion road from existing BRO
road will be provided to connect the bridge location which will provide access to Adit near Surge
Shaft and Intermediate Adit no.-2. Second bridge of 60 m span across Siyom river is proposed to
be erected upstream of junction of Sitten Nallah with Siyom river. The bridge will provide access
to Inlet adit and Intermediate Adit no.-1.
16-10
CISMHE
Intermediate Adit-1 and 2 and Adit to HRT near Surge Shaft. The above Adits meet the HRT at
chainage 596.12 m, 3029.228 m, 5876.828 m and 9097.974 m respectively. Thus eight faces are
available for excavation of HRT.
16.5.2.1 Excavation
After jungle clearance and construction of roads and bridges, the excavation of Adit
portals will be taken up. The overburden will be removed with the help of Excavator and Dozer
whereas open excavation at portal face will be carried out by conventional Drill Blast Method
with the help of Jack hammers and portable compressor. The mucking will be done by Excavator
and Dumpers. The rock above the portal face will be excavated in a stabilized slope.
Four no. Adits (7.0 m D-shaped) will be provided for excavating HRT having total length
of 9202 m. The location of Adits has been fixed keeping in view the geological and
topographical conditions as well as construction convenience. The size of Adits has been kept as
7.0 m D-shaped keeping in view the easy movement of mucking equipment. The slope of various
adits has also been kept mild in order not to stress the loaded equipment unnecessarily. A
positive slope to all the adits has been provided in order to make them self draining. The
excavation of Adits has been planned to be carried out full face by normal Drill and Blast
Method as soon as the portals are established. The drilling operation for excavation of Adits is
proposed to be carried out by deploying two-boom drilling jumbos and mucking will be done
with the help of side tilting loader (2.5 cum) and 20 T capacity dumpers.
ii).
Drilling operation Drilling will be done by using two boom hydraulic drilling Jumbos,
which can theoretically drill up to 2 m per minute say 100 m per hour of 50 minutes
working)
iii).
Charging and Blasting (The holes drilled will be loaded by Powergel or equivalent. Nonelectric detonators with millisecond delay are proposed to be used.
iv).
Defuming (At the time of excavation of tunnels, adequate provision for proper ventilation
is absolutely essential; therefore an effective ventilation arrangement has been planned
during excavation of tunnels).
16-11
v).
CISMHE
Scaling (The scaling is proposed to be carried out manually with help of scissors
platform.
vi).
Mucking
vii)
Rock Support Measures (Shotcreting shall be carried out up to excavated face after each
blast whereas rock bolting shall be provided about 2 pulls behind the excavated face).
16.6
i).
ii).
iii).
41 mm
iv).
102 mm
v).
vi).
Drilling Equipment
vii).
3m
Two boom hydraulic drilling Jumbos
2 m / minute
or 100 m / hour
viii).
80 m / hour
ix).
Swell Factor
x).
xi).
xii).
3.5 m
xiii).
385 m
16.7
1.5
235.98 m3
110
The concrete lining in HRT is proposed to be carried out after completion of benching.
The lining is proposed to be carried out by using three set of shutters (each set containing two
shutters and one traveler). The sequence of concrete lining operations in overt will be as follows:
16-12
i).
CISMHE
One set of shutter will be installed at chainage 0.0 m. This shutter will move towards Inlet
Adit (Ch. 596.12). After completion of this reach the above set of shutter will be
dismantled and installed at chainage 3029.228 m. This shutter will move towards the Inlet
Adit. For supply of concrete 30 cum/hr capacity CBP installed at Inlet Adit will be used.
ii).
Second set of shutter will be installed at chainage 5876.828 m and lining will proceed
towards Intermediate Adit-1. The 30 cum/hr capacity CBP installed at the portal of
Intermediate Adit-1 will be used for concrete placement.
iii).
Third set of shutter will be installed at upstream end of Surge Shaft at chainage 9202 m
and lining will proceed towards Adit to Surge Shaft i.e. 9097.974 m. The concrete during
this reach will be supplied from CBP of 30 cum/hr capacity installed at portal of Adit to
Surge Shaft. After completion of lining from chainage 9202 m to Ch. 9097.974 m the
above set of shutter will be installed at chainage 9097.974 m and the lining between the
two chainages i.e. 5876.828 m and 9097.974 m will be completed and concrete will be
supplied from 30 cum/hr capacity CBP installed at portal of Intermediate Adit-2.
16.7.1 Grouting
16.7.1.1 Contact Grouting
Contact grouting in the tunnel is proposed to be carried out after 30 days of placement of
concrete in tunnel invert. After this the contact grouting will progress simultaneously with lining
activity of tunnel. Contact grouting is provided to fill any gap, especially at crown level, which
has been left during concreting activity between rock and concrete lining. For this purpose grout
holes of 38 mm diameter will be drilled 300 mm inside the rock and grouting will be done at a
low pressure of about 1 to 1.5 kg/cm2. The water cement ratio in the beginning will be kept
leaner and the same will be thickened as grouting progresses.
16-13
CISMHE
concrete plug the consolidation grouting will be carried out after plugging operations have been
completed. Two no. adits i.e. Adit near Surge Shaft and Inlet Adit are proposed to be provided
with a vehicular access each.
Construction Equipment
Quantity
Drilling and Blasting Equipment
Portable Compressors 1000 cfm
6
Two boom drilling Jumbos
6
Crawler drill IRCM 341 along with 450 cfm compressors
4
Jack Hammer with Pusher legs
12
Mucking Equipment
Wheel mounted Dozer (180 HP)
3
3
Loader 2.5 m bucket capacity side Dump Loader
6
Dumper (20 T)
30
Concrete Production and Placement
Aggregate Processing Plant 500 t/hr Capacity
1
Aggregate Processing Plant 100 t/hr Capacity
1
Aggregate Processing Plant 60 t/hr Capacity
1
Concrete Batching Plant - 30 cum/hr Capacity
4
Tunnel Shutters with Vibrators Complete (each of 12 m length)6 (with 3 travelers)
Needle Vibrator - 65mm diameter with flexible shaft.
10
Transit Mixers - 6 cum Capacity
9
Concrete Pump (38 cum/hr.)
3
Surge Hopper
3
Shotcrete, Drilling and Grouting
Wet Shotcrete Machine with Telescopic Arm
4
Grouting Pump (Surfex / Mai)
4
Support Equipment for Underground Works
Ventilation Fans 1400mm dia Impeller
13
Ducting 1400mm dia
10718
Scissors Platform
4
Rib Erector
4
Rib Bending Machine with Jack etc. Complete
1
Alignment Lazer
6
Profiler
6
16-14
16.8
CISMHE
SURGE SHAFT
The Head Race Tunnel terminating in a 15.0m finished dia and 140.25 m high Surge
Shaft at RD 9217.53 m. The excavated dia of surge shaft is 17.20m (including 1000 mm thk
lining and 100 mm thk shotcrete) from 1277.75 m to 1388.00 m and 18.10 m (including 1450
mm thk lining and 100 mm thk shotcrete) from. 1388.00 m to 1418.00 m. The location of Surge
Shaft has been so planned that sufficient cover is available on all side of Surge Shaft. Sufficient
space has also been ensured for working of a gantry crane at top to facilitate widening of pilot
shaft and supply of concrete for concreting operations.
The excavation of pilot for Surge Shaft is proposed to be carried out from Adit to HRT near
the Surge Shaft bottom. For this purpose an Alimak raise climber will be installed at the bottom and a
pilot of 2.6 m diameter will be excavated with the help of raise climber. If needed the temporary rock
support by way of spot rock bolts of 2 to 2.5 m length shall be provided in the pilot shaft.
A temporary winch of 10 T capacity will be installed for carrying out the sinking
operations. A Tripod will be erected over top of pilot shaft from where the sinking operations
will be carried out. Mucking in this case will have to be carried out manually. In case rock is very
much shattered in top reaches the shaft will be supported by providing temporary steel supports.
A 30 T capacity gantry crane will be installed at top of surge shaft for lowering and lifting
excavation equipments, men and material as the excavation for widening proceeds. Widening
operations shall be taken up proceeding from top to bottom by drill and blast method for 1.0 m
depth at a time. The muck generated after blast will be dozed of by a small dozer upto pilot shaft
and will be collected at bottom of surge shaft from where it will be hauled to nearest dumping
site. The above sequence shall be repeated until the entire depth of the Surge Shaft is excavated.
Total depth of Surge Shaft to be excavated in this manner is around 140.25 m. Normal benching
operation shall be followed while widening of surge shaft.
Hirong H.E. Project, Arunachal Pradesh
16-15
CISMHE
In the initial reach of about 30 m from the top the widened Surge Shaft is proposed to be
supported by composite steel section of ISMB 300 x 140.25 with plates of 16 mm welded on
both flanges and concrete. The ISMB will be completely embedded in concrete with a cover of
150 mm on its front face.
16.8.3 Concreting
The concreting of Surge Shaft is proposed to be carried out by deploying a slip form
shutter. The installation time for slip form shutter will be about two months. Concrete mix shall
be transported from batching and mixing plant installed at adit to HRT near Surge Shaft through
transit mixers feeding 40 cum concrete pumps for concrete lining up to 30 m height from bottom
Hirong H.E. Project, Arunachal Pradesh
16-16
CISMHE
of Surge shaft. Concrete lining in rest of the Surge Shaft shall be done from top of Surge Shaft.
Shutter vibrators and needle vibrators shall be used for vibration of concrete. The progress with
slip form shutter will be of the order of 15 m / month and it will take about 9 months to complete
the operation of concrete lining of 138 m deep Surge Shaft. For providing reinforcement a
separate platform will be erected which will move ahead of concrete lining.
16.8.4 Grouting
16.8.4.1 Contact Grouting
The contact grouting is to ensure proper contact of concrete with rock and consequent
load transfer. For this purpose periphery holes will be drilled 300 mm deep into rock and
grouting carried out at low pressure of 1 to 1.5 kg/cm2. The water cement ratio of the grout mix
will be kept leaner in the beginning and thickened consequently. The contact grouting is to be
carried out till refusal of the grout intake.
(Nos. 3), Concrete Pump (1), Needle vibrator (4), Batching and mixing plant 30 m3 cap
(1), Grout pump (1) and Slip form shutter 1.1 height (1).
16.9
16-17
CISMHE
Shafts. For approaching vertical portion of Pressure Shafts all the two approaches will be
utilized.
For widening of Pressure Shaft an 15 tonne winch shall be provided in Top Adit to
Penstock. Platform will be lowered in the vertical reach of Pressure Shaft from where men and
material will be taken inside the widened portion of Shaft. A progress of 1 m will be achieved for
widening the Pressure Shaft to its full dimensions.
The four branch penstocks from bottom adit towards Powerhouse end shall be excavated
10 m short of upstream Powerhouse wall. The 10 m reach of branch Penstocks shall be excavated
after Powerhouse excavation reaches that level. The excavation in penstock branches (i.e.
bifurcation) will be taken up one after the other. The drilling will be done by 2-boom Hydraulic
Jumbo and haulage of excavated muck will be done by loader, dumper combination. The
excavation shall be done full face with conventional drilling/blasting method.
The excavation of Top horizontal reach both upstream and downstream of Valve House
Chamber shall be carried out after completion of excavation of Valve House. For excavation of
Valve House Chamber, adit to top of Penstock will be further extended to reach top of Valve
House Chamber. The overt of this adit shall match with overt of Valve House Chamber. A
central gullet 6.5 m wide and 6.5 m deep shall be excavated (Activity-I). The central Gullet so
excavated shall be widened to its full width before carrying out the benching down operations
Hirong H.E. Project, Arunachal Pradesh
16-18
CISMHE
(Activity-II). The benching down shall be carried out by providing a ramp in a slope of 1:12 to
meet with top of adit to bottom of valve chamber at 1277.00 m (Activity-III). The haulage of
excavated muck shall be carried out from Adit to top of valve chamber. After the completion of
Activity-III the Valve Chamber will be excavated up to 1282.00 m on one side and 1277 on other
side. The ramp removal shall be done from Adit to bottom of valve chamber. The excavation of
rest portion of Valve Chamber will be done by making ramp in a upward slope of 1:12 and the
haulage of excavated muck will be carried out via Adit to bottom of Penstocks. Thus after
completion of this activity i.e. Activity-IV, further benching down up to invert level of Valve
Chamber will be carried out (Activity-V).
The penstock work involves fabrication of steel liners of 4.25.0m and 3.0 m dia, thus
before the fabrication work, exact number and size of each ferrule shall be planned talking into
account the vertical and horizontal bend reaches. For this purpose, a well equipped Ferrule
Fabrication Workshop will be established at site, with the state-of-the-art plant and equipment.
The erection of ferrules shall be started from Adit to bottom of penstock. The erection of bottom
vertical bend shall be carried out first of all. The stepped concrete pedestals (stairs) shall be
provided to facilitate alignment of various pieces of vertical bend. The vertical bend will be
erected in 18 pieces.
After erection of the bottom vertical bend the 5 m vertical pieces of ferrules will be
lowered in the Pressure Shaft with help of 15 tonne winch provided in Adit to top of Penstock.
Backing strip will be welded with upper face of ferrule. The strip will help in proper alignment of
next ferrule. A clear gap of 3 mm will be provided between bevelled edges of two ferrules. The
circumferential welding will then be carried out. The welding flux will be contained with help of
backing strip.
16-19
CISMHE
Pilot Shafts
Side Slashing
Optimum
requirement
1*
3. Dumper 20 T capacity
1*
7. Winch 15 T capacity
16.9.3 Concreting
The backfill concrete behind Steel Liner (ferrules) will be carried out once a ferrule of 5
m length is erected at site. The backfill concrete in vertical reach of Pressure Shaft will be carried
out from top with help of a concrete pump. Similarly in horizontal reaches also the backfill
concreting will be carried out after erection of each ferrule is over.
45.71 cum
Working hours
8 hr
45.71 / 8
5.71 cum
5.71 x 1.05
5.99
6.0 cum
Handling losses (5 %)
16-20
CISMHE
1.2 KM
2 x 1.2 x 60 /12.5
12 min
7.6 min
6.6 min
4.95 min
31.15 min
50/31.15 =
1.61 x 6 x 0.66
6.38 cum
6/6.38
1 No.
Hauling time
(12.5 km/hr (average), transit mixer speed)
Total
1.61
Hence, only 1 No. pump 38 cum/hr is sufficient for placing the backfill concrete in
penstocks.
16.9.4 Grouting
Contact grouting shall be carried out once the backfill concreting operations are over.
This will be carried out from holes left in steel Penstocks for this purpose. Drilling will be carried
out from these holes up to 300 mm inside the rock and contact grouting at a pressure of 1 to 1.5
kg/cm2 shall be carried out. Total requirement of equipment for backfill concrete in penstock are
as under:
S. No.
Equipments Description
No.
Needle vibrator
2
3
Grout pump
16-21
CISMHE
and houses the Erection bay, Machine Hall and Control Block. The Transformer Hall Cavern is
on the downstream side of the Power House Cavern and is 118m (L) x 15m (W) x 26m (H) and
houses the Generator Transformers and GIS. The 76m (L) x 7m (W) x 10m (H) D.T. Gate
Operating Gallery is located on the downstream side of the Transformer Hall Cavern with a clear
intervening rock cover of 21.50m. The Power House (PH) and the Transformer Hall (TH)
caverns are connected by four nos. Bus Duct Galleries spaced 17m apart from each other. Four
no. Draft Tube tunnels off-take from the bottom of the P.H. Cavern and go up to the bottom of
D.T. gate shaft and further merges into a Collection Gallery forming the TRT for discharging
water into the river. The excavation of the two major caverns i.e. Power House and Transformer
Hall could be done only after establishing of the Approach Adits, viz. 7.5m D-shaped Main
Access Tunnel, a branch Adit (6.5m D-shaped and 158.65m long) off-takes from MAT at RD
255m and meets the bottom of Transformer Hall at 1020m, Another branch Adit (7.5 D-shaped
and 147.25m long), 6.5m D-shaped Adit to top of T.H. Cavern cum Ventilation Tunnel, a branch
Adit (6.5m D-shaped and 95.62m long), 7.5m Dia. Construction Adit cum Surge Gallery, 390m
long with Portal at 1040m
ii).
iii).
16-22
iv).
v).
vi).
vii).
CISMHE
After completion of excavation for central gullet, 10m wide nitches along the profile of
Powerhouse crown will be provided on both sides of central gullet. These nitches will be
staggered by atleast 25 m along the length on both sides of gullet. This will ensure that full width
of Powerhouse is not excavated in one go and part excavation and supporting is completed in
2/3rd portion along the crown before taking up remaining 1/3rd portion. This will ensure proper
supporting of crown with least initial deformations. The widening of the central gullet to full
Hirong H.E. Project, Arunachal Pradesh
16-23
CISMHE
width of the powerhouse roof vault in 22.20m width will be undertaken from the Erection bay
end and proceed towards the Control block end.
After having excavated and supported the roof vault of the powerhouse cavity up to the
1035m, benching down operations up to the Erection bay level at 1019.7m will be taken up.
Initially, the mucking during the benching down of the powerhouse cavern will necessarily
have to be done through the 6.5m D-shaped Adit to top of P.House, as this will be the only
access available. Benching down will be done in stages by making ramps and removing the
same progressively.
In the next phase, i.e. under Stage-V the entire area of the powerhouse will be benched
down to a elevation of .1019.70m which is same as required for the erection bay floor. In
Stage-VII 7.5m wide ramp shall be excavated along upstream wall of the cavity with its
elevation near the control block end being 1012m and that near the Unit Before the end of
Stage-VII, the lower horizontal portions of the Unit Pressure Shafts would have been excavated
up to the U/S wall of the powerhouse cavity. Stage-VIII will thus consist of removal of ramp
and benching down of entire Power House Cavern beyond Erection bay to 1003.20m, which is
the general excavated floor level in powerhouse cavity. Mucking of this portion shall be done
through the lower horizontal portion of Unit pressure shaft-4. Before the end of Stage-VIII, the
Draft tube tunnels will also get excavated through the collection gallery.
First of all, the roof of the Transformer Hall cavity will be excavated. This will be done
through 6.5m D-shaped Ventilation Tunnel meeting the T.Hall cavity gable end at its roof level.
The excavated crown level of the T.Hall cavity is at 1046m which is same for 6.5m D-shaped
Adit to top of T. Hall where it meets the Transformer Hall cavity. After completion of excavation
for central gullet, 10m wide nitches along the profile of T. Hall crown will be provided on both
sides of central gullet. These nitches will be staggered by atleast 25 m along the length on both
Hirong H.E. Project, Arunachal Pradesh
16-24
CISMHE
sides of gullet. This will ensure that full width of T. Hall is not excavated in one go and part
excavation and supporting is completed in 2/3rd portion along the crown before taking up
remaining 1/3rd portion. This will ensure proper supporting of crown with least initial
deformations. The widening of the central gullet to full width of the T. Hall roof vault in 15.20m
width will be then taken up and the supporting of the roof of the widened portion will also be
done concurrently.
Once the crown of the THC has been excavated, a 6.5m wide ramp with a slope of 1(V)
in 10(H), which is considered suitable for haulage equipment will be excavated first up to
1029.75m in a length of 87.5m. Further, the benching down of the remaining portion of T. Hall
cavern on both sides of the ramp will be done up to 1029.75m leaving the 6.5m wide ramp for
mucking through VT under Stage-III The rock bolting and shotcreting of the final exposed rock
faces of the cavity walls will be done simultaneously. Under Stage-IV a 4.35m wide ramp shall
be excavated from 1029.75m up to invert level of Connecting Gallery to P.House and 6.5m DShaped Adit to bottom of T. hall i.e. 1020 m along the D/S wall of T. Hall cavern. By the time
this activity is over, the excavation of Connecting Gallery to P.House and 6.5m D-Shaped Adit to
T.Hall bottom off-taking from MAT would have been completed and thus the same will be
available for taking up further excavation and mucking operation. In the next phase, i.e. under
Stage-V, the entire area of the T. Hall will be benched down to a horizontal elevation
of1019.50m which is same as required for the Transformer Hall floor. The benching down
operations for each stage shall be similar as adopted for Power House cavern. The mucking under
this activity shall be done through Adit to bottom of T. Hall.
The excavation and support of niche for Oil separator sump along with balance portion of
Drainage and Dewatering Tunnel between PHC and TH and TH and DT Gate Operating Gallery
will be taken up next. The mucking under these activities shall also be done through Adit to
bottom of T. Hall. The drilling for underground excavation shall be done by Two-Boom
Hydraulic Jumbo adopting conventional drill/blast method for the excavation. Removal of
excavated material shall be done by a combination of Excavator/Side Dump Loaders with
Dumpers. As the excavation proceeds, rock supports system by way of rock bolts, shotcrete, steel
ribs and back fill concrete shall be provided, as required. Drilling for rock bolts shall also be
carried out with Two-Boom Drill Jumbos.
16-25
CISMHE
16-26
CISMHE
8.25 m in normal reaches and 8.50 m in ribbed reaches. Keeping in view the limited reach of
drilling Jumbo, It is proposed to carry out the excavation in 2 stages- heading and Benching.
16.10.1.9 Tail Race Tunnel, Collection Gallery, Draft Tube Tunnels and Outfall Structure.
The length of Tail Race Tunnel is 210m long and has a circular section with finished
diameter of 7.5m. The TRT is proposed to be excavated from Construction Adit cum
Downstream Surge Gallery which is also of similar sectional profile. The Construction Adit
meets the TRT at 10m D/S of junction of TRT with Collection Gallery.
One no. 12m long Gantry shutter will be erected at d/s end of TRT near rock ledge. The
lining operations in this case will be carried out in upstream direction towards junction with
surge gallery. The concrete will be fed from 60 cum/hr capacity CBP-5 installed near MAT
portal. The concrete behind the Shutter shall be placed by Concrete Pumps (38cum/hr capacity).
A Surge Hopper shall be kept near the concrete pump to ensure uninterrupted supply of concrete
to the Pump. Vibration of concrete shall be accomplished by surface vibrators mounted on the
Shutter itself and needle vibrators inserted through inspection window in shutters. While the
lining in this reach is in progress the kerb along with rail fixing will be extended in upstream
reach and the shutter will be moved on rails. The overt concrete lining from up to junction with
collection gallery is completed thus with a progress of 96m/month. The invert lining in TRT will
be done after the overt lining in Surge Gallery is completed. The surface profile of the invert will
be finished to shape by screeding with the help of a tailor made template.
16-27
CISMHE
Completion Date
15.01.2014
15.12.2017
iii).
Intake Structure
15.05.2017
iv).
15.12.2017
v).
HRT
15.07.2017
vi).
30.06.2017
vii)
15.03.2017
15.09.2016
ix).
Transformer Hall
31.05.2017
x).
Surge Gallery
31.12.2016
xi).
30.04.2017
15.05.2017
Water Availability
31.12.2017
b)
28.02.2018
c)
30.04.2018
d)
31.05.2018
e)
30.06.2018
16-28