is-S09C Seabed Survey

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

CONTRACT

GC13105700

IS-S09 / 02 / 15

REPORT NO:

ONLINE W.O. NO

>>> Refer to QP Intranet


Online W.O. for Details

31112003

MRV SHADDAD
LOCATION

IS-S09C Platform

TASK

Pre Rig Move Seabed Survey for Rig Al Wajba

STARTED

07-06-2015

COMPLETED

08-06-2015

SUBMITTED

08-06-2015

FROM

TO

MODE

ACTION

MRO/21

MRO/2

Email

REGISTER & FOR DISTRIBUTION

MRO/2

MRL

RETAIN ORIGINAL, DEPARTMENTAL


REVIEW COLLATE & FORWARD
RECOMMENDATION TO
ASSET HOLDER .
COPY RECOMMENDATION TO MRO/2

MRO/2

OXY

TO ACTION IF REQUIRED
MRL RECOMMENDATIONS

MRO/2

PLAN / ACTION ASSET HOLDERS


REQUESTS

ELECTRONIC REPORT TRANSFER (E-REPORT)

Location: IS-S09C Platform

07.06.15 08.06.15

WO# 31112003
Pre Rig Move Seabed Survey for Rig Al Wajba
INSPECTION CO-ORD: D. DYSON

VESSEL: MRV SHADDAD

TABLE OF CONTENTS
INTRODUCTION................................................................................................................................... 3
WORKSCOPE....................................................................................................................................... 3
SUMMARY REPORT............................................................................................................................ 3
ATTACHMENTS.................................................................................................................................... 4
SELECTED PHOTOS........................................................................................................................... 4

Location/Description: IS-S09C Platform Pre Rig Move Seabed Survey for Rig Al Wajba
Report Ref: IS-S09 / 02 / 15

Compiled by: HOSC Halul Subsea Section


Page 2 of 4

Location: IS-S09C Platform

07.06.15 08.06.15

WO# 31112003
Pre Rig Move Seabed Survey for Rig Al Wajba
INSPECTION CO-ORD: D. DYSON

VESSEL: MRV SHADDAD

INTRODUCTION
Halul Offshore Services Company (HOSC) ROV and dive teams on board the MRV
Shaddad were instructed to carry out pre rig move seabed survey, debris recovery and install
pipeline marker-buoys, at the IS-S09C Platform in the IS-Field, prior to the Rig Al Wajba
arriving on location.
The operations were carried out between 7th & 8th June 2015.

WORKSCOPE
As per Work Order: 31112003
1. Start at the reference point on the IS-S09C platform and proceed 200m on a bearing of
357 from the point of origin along the grid centre-line, extending the survey to 75m either
side of the grid centre-line.
2. Locate obstructions/debris considered hazardous to the rig spud cans and recover to
surface.
3. Record seabed type and depth.
4. Install two pipeline-marker-buoys on the 8 IS117 pipeline, as per the chart provided.
5. Install two marker-buoys on the 2 3/8 CT, as per the chart provided.
6. Produce a field report for evaluation by the on-board MRO representative.

WO 31112003

IS-S09C chartlet

SUMMARY REPORT
The datum for this survey was taken as the centre of the North Face of the platform which
was recorded at the following coordinates:
639892.57 E, 2817349.99 N
LAT 2528.23186' LONG 05223.55340'
The ROV tracked over the designated seabed survey grid. The visibility was 1.5m at the time
of survey and the ROV sonar was set to a range of 20.0m.
The seabed consisted of fine sand and silt with an average depth of 35.1m.
Depth readings were recorded between 00:56 hrs and 04:09 hrs on 8th June 2015.
The depth readings have not been reduced to the Admiralty Chart Datum.
Seabed features were identified as follows:
No debris items were located or identified within the seabed survey grid area.
A total of six seabed depressions were located within the seabed survey area.
One area of cap rock with a maximum height of 0.15m was located within the seabed
survey area.
One coiled tubing (23/8 CT IS066) passes across the grid area from east to west on the
northern end at the 150m survey line from IS-S09C.
2 x pipelines (8 IS117 & 12 IS113) intersect the seabed survey grid area at the southeastern corner.
Rig Move to take note of their positions.
The above items are depicted on the attached seabed survey datasheet

Location/Description: IS-S09C Platform Pre Rig Move Seabed Survey for Rig Al Wajba
Report Ref: IS-S09 / 02 / 15

Compiled by: HOSC Halul Subsea Section


Page 3 of 4

Location: IS-S09C Platform

07.06.15 08.06.15

WO# 31112003
Pre Rig Move Seabed Survey for Rig Al Wajba
INSPECTION CO-ORD: D. DYSON

VESSEL: MRV SHADDAD

Pipeline Marker Buoys Installation


A total of two A1 & two A4 sized Norwegian marker buoys were attached to the 8 IS117
pipeline as per the chartlet provided. Each pair of buoys was tied to the pipeline via a 40m
long section of 18mm diameter polypropylene rope.
A total of two A1 & two A4 sized Norwegian marker buoys were placed adjacent to the 2-3/8
CT IS066 attached to drop-weights as per the chartlet provided. Each pair of buoys was tied
to the pipeline via a 40m long section of 18mm diameter polypropylene rope.

ATTACHMENTS

IS S09C Seabed Fix


Data

IS-S09C datasheet

SELECTED PHOTOS

An Area of Cap Rock Reported at Fix #4

Location/Description: IS-S09C Platform Pre Rig Move Seabed Survey for Rig Al Wajba
Report Ref: IS-S09 / 02 / 15

Compiled by: HOSC Halul Subsea Section


Page 4 of 4

You might also like