UNIVERSITY OF WISCONSIN - University of Wisconsin - La Crosse

CAMPUS PHYSICAL DEVELOPMENT PLAN


PROJECT SEQUENCE CHART: 2011 - 2023

NEAR TERM IMPLEMENTATION MID-TERM IMPLEMENTATION


2011-13 2013-15 2015-17 2017-19 2019-21 2021-23

CAMPUS PHYSICAL DEVELOPMENT PLAN - PLANNED PROJECT SCHEDULE OF EVENTS

$ 144.0 GPR $ 59.0 PR

COWLEY HALL ADDITION & RENOVATION


$80M GPR

Design Construction
$4.0M GPR $76.0M GPR

PARKING RAMP
$11.0M PR

Design & Constrution


$11.0M PR

NEW STUDENT UNION


$40.0M PR

Planning Construction
$3.0M PR $37.0M PR

WITTICH HALL RENOVATION


$22.50M GPR

Design Construction
$1.5M GPR $21.0M GPR

ADDITION TO REC
$8.0M PR

Design & Constrution


$8.0M PR

MITCHELL HALL ADDITION & RENOVATION


$24.0M GPR

Planning Design & Construction


$1.5M GPR $22.5M GPR

CENTER FOR ARTS ADDITION & RENOV


$27.0M GPR

Planning Design & Constrution


$2.0M GPR $25.0M GPR

TOTAL
GPR $ 5.5 $ 97.0 $ 1.5 $ 22.5 $ 2.0 $ 25.0 $ 153.5 M
PR $ 14.0 $ 37.0 $ 8.0 $ - $ - $ - $ 59.0 M
PR $ 14.0 $ 37.0 $ 8.0 $ - $ - $ - $ 59.0 M
GIFT $ - $ - $ - $ - $ - $ - $ - M
GRNT $ - $ - $ - $ - $ - $ - $ - M
$ 212.5 M
KEY

DURATION OF CAMPUS PHYSICAL DEVELOPMENT PLAN


DURATION OF PROJECT
DURATION OF PROJECT CONSTRUCTION
DURATION OF PROJECT PLANNING