GENERAL LIGHTING LOAD

CKT #

DESCRIPTION

VA

220

5.45

1200

220

5.45

1200

3 POWER LAYOUT

220

5.45

1200

220

1750

5 A.C.U (0.75HP)
6
A.C.U (2HP)
7 REFRIGERATOR

1
1
1

220
220
220

6.9
12
12

1518
2540
3000

8
9

220

13.83

2520

LIGHTING
LAYOUT
2 POWER LAYOUT

SMALL APPLIANCE LOAD


3 cxts x 1.5kw = 4,500w

LAUNDRY AND REFRIGERATOR


1 cxt x 2.0kw = 2,000w
TOTAL = 9,523w

OTHER LOADS
1HP A.C.U. @100% DF
8 X 240 X 100% = 1,920w
2HP A.C.U. @100% DF
12 X 240 X 100% = 2,880w

L.O.

C.O.

14

A.C.U (1 HP)

WATER PUMP
SPARE

APPLICATION DEMAND FACTOR


0.75HP A.C.U. @100% DF
6.9 X 240 X 100% = 1,656.W

FIRST 3KW @100% DF = 3,000w


REMAINING (6523w)@35% = 2,283w
i = 11,402.2 / 240 = 47.58A
TOTAL MAXIMUM DEMAND FACTOR = 11,420.2w

SCHEDULE OF LOADS, LOAD COMPUTATION

DRAWN BY:

DRAWING TITLE

CHECKED BY:

GASPAR, MIGUEL
SIR JOJO GALAPON

YR. SEC

G9-4

DWG. NO.

Q4-P1

DATE

MAR 17, 2016


MAR 17, 2016

SCALE

1 : 1 mm

RATING