Professional Documents
Culture Documents
BP Hazard Identification Task Risk Assessment
BP Hazard Identification Task Risk Assessment
Rev. No.
HAZARD IDENTIFICATION & TASK RISK ASSESSMENT
DOCUMENT CONTROL
Revision Record
Revision
No.
Revision
Date
Section / Page
Dec. 05,
2005
Various
August
18, 2007
Various
Document No.:
PRO/SFTY/018
Issue Date:
Page 1 of 38
TABLE OF CONTENTS
1.0
INTRODUCTION .......................................................................................................... 3
2.0
3.0
4.0
DEFINITIONS ............................................................................................................... 4
5.0
6.0
7.0
8.0
8.1
8.2
8.3
8.4
8.5
8.6
8.7
8.8
8.9
8.10
8.11
8.12
8.13
8.14
8.15
8.16
8.17
8.18
8.19
8.20
8.21
PROCEDURE ............................................................................................................ 10
WORK REQUEST.......................................................................................................... 11
CHECK TASK CATEGORY ............................................................................................. 11
PERFORM LEVEL-1 TRA.............................................................................................. 11
DEFINE TASK PARAMETERS ......................................................................................... 12
PERFORM LEVEL-2 TRA.............................................................................................. 12
FORM TRA TEAM ........................................................................................................ 12
BREAK DOWN OF TASK INTO ACTIVITIES ...................................................................... 14
IDENTIFY HAZARDS ...................................................................................................... 14
IDENTIFY HAZARD EFFECTS (CONSEQUENCES) ............................................................ 14
DEFINE RISK RATING ................................................................................................... 15
IDENTIFY CONTROLS.................................................................................................... 18
CONTROLS ADEQUATE ................................................................................................ 21
RESIDUAL RISK ACCEPTABLE ...................................................................................... 22
AGREEMENT ON RISKS AND CONTROLS ....................................................................... 22
DOCUMENT AND RECORD ............................................................................................ 22
REVIEW OF TRA.......................................................................................................... 23
COMMUNICATION ......................................................................................................... 23
IMPLEMENT CONTROLS ................................................................................................ 22
CARRY OUT THE TASK................................................................................................. 24
MONITOR FOR CONDITION CHANGE .............................................................................. 24
RECORD LESSONS LEARNED ....................................................................................... 24
Document No.:
PRO/SFTY/018
Issue Date:
Page 2 of 38
1.0
INTRODUCTION
Pre-job risk assessment is a key element of the BP Group Standard for the Control of
Work (Element 5 Assess and manage the risks), the BP Golden Rules of Safety
(Getting the Basics Right) as well as the Getting HSE Right Management Framework
(Element 2 Risk Assessment and Management).
The identification and control of risk is an essential pre-requisite to ensure safe
execution of work activity and secure compliance with the requirements of health
and safety legislation. The process comprises the following three basic stages:
risk assessment assessing the risk that may arise from hazards.
3.0
Document No.:
PRO/SFTY/018
Issue Date:
Page 3 of 38
4.0
TERMINOLOGY
Hazard
The potential or condition to cause harm, including ill health and injury,
damage to property, plant, products or the environment, production losses or
increased liabilities.
Hazard Effect
[Consequence]
The harm or consequence which takes place due to the realization of the
hazard.
Probability
Risk
The likelihood that a specified undesired event will occur due to the
realization of a hazard by, or during, work activities or by the products and
services created by work activities. Risk is the combination of the Hazard
Effect (Consequence) and Probability (likelihood of its occurrence).Risk =
Hazard Effect (Consequence) x Probability (Likelihood of Occurrence).
Control
ALARP
Competency
Planning
Measuring
Task Risk
Assessment
Also known as JSA (Job Safety Analysis) or JHA (Job Hazard Analysis). It is an
organized and systematic effort to identify and analyze the significance of
potential hazards of each manageable task associated with the materials,
equipment, instrumentation, utilities, human actions (routine and non-routine),
and external factors that might impact the process. (This is done by breaking
the activity into manageable tasks) and then to identify suitable controls to
ensure risks are reduced to an acceptable level and document risk
assessment results.
Residual Risk
The Risk remaining after applying Control measures, and carrying out a reassessment of HE rating and Probability.
Auditing
Document No.:
PRO/SFTY/018
Issue Date:
Page 4 of 38
5.0
5.1
5.2
Reviewing and auditing the risk assessment process to ensure that the standard
of risk assessments is maintained and areas of improvement are identified and
implemented.
Approve any reviews / updates / revisions in the HITRA procedure in the light of
experience gained and lessons learned.
Assisting and advising all users of the HITRA procedure in its correct
interpretation and implementation and maintenance of the HITRA system.
Ensure that adequate consultation has taken place (typically with the Area
Authority and/or Permit Issuer).
Document No.:
PRO/SFTY/018
Issue Date:
Page 5 of 38
5.3
5.4
Ensure the team understands the assessment process and what it is trying to
achieve.
Take responsibility for maintaining the quality of the Risk Assessment and ensure
that the assessment team includes personnel with all the necessary knowledge
and competence for the task involved.
Ensure that all members of the Risk Assessment team have a full opportunity to
contribute and that the details of the assessment are agreed by all team
members.
5.5
Help identify hazards and control measures to remove or reduce the likelihood of
an incident/accident happening.
Ensure they agree with the overall Risk Assessment before approval and that
risks have been reduced as low as reasonably practicable.
Understand the hazards and control measures associated with the task.
Stop the job at any time they are concerned about safety.
Document No.:
PRO/SFTY/018
Issue Date:
Page 6 of 38
5.5
Stop the job if they identify a hazard not recorded on the Risk Assessment and
Permit to Work or Procedure.
Carry out work as defined in the Risk Assessment and Permit to Work or
Procedure.
Decide whether the risks can be controlled adequately by the proposed means,
taking into account the controls required by any relevant local procedure and the
competence of the person in charge.
Initiate the need to complete a Level 2 Risk Assessment if they are not
completely assured that the risks will be adequately controlled and believes a
more rigorous risk assessment is required.
Confirm that the risk assessment was carried out by a team with the appropriate
level of expertise.
Confirm that the risk assessment team has taken appropriate guidance on health,
safety and environmental legislation and consequent limits on operation (e.g.,
environmental consents).
6.0
6.1
Training
HITRA methodologies are not complex, but they do rely on wide work-related
underpinning knowledge and experience. This includes experience of:
relevant hazards
realistic consequences
All personnel involved in the HITRA process should undertake the following basic
training:
Document No.:
PRO/SFTY/018
Issue Date:
Page 7 of 38
Before selection for training, Level 2 HITRA Team Leaders should be able to
demonstrate wide knowledge of the work environment and relevant tasks. Although
checklists and other generic tools are available, the Team Leader has to use these
with informed judgement.
6.2
Level 1 HITRA
Completer
Yes
No
No
Yes
Yes
No
HITRA Authorizing
Signatories
No
Yes
The required competency of all relevant personnel should be confirmed during the
planning process for a particular task. The SPA Person (or delegated nominee) should
ensure that new personnel have the required competencies properly certified from
acceptable source or third parties.
Having undergone the appropriate training and having been assessed competent to
carry out the relevant duties, Authorised Signatories and Level 2 Risk Assessment
Team Leaders can only take on these roles when they have been duly certified and
authorised.
6.3
Records
Records of attendance
reference/verification.
Document No.:
PRO/SFTY/018
and
competency
Issue Date:
should
be
filed
for
future
Page 8 of 38
6.4
7.0
7.1
Level-1
Level 1 is a broad overview of the task by a competent person(s) typically the
Performing Authority to identify all significant hazards involved and appropriate
controls which are required to let the job to proceed.
A Level-1 Task Risk Assessment involves a review of the task by the performing
person in consultation with his Team Leader, Superintendent or Supervisor or Area
Authority to identify the hazards associated with the task and appropriate control
measures required for managing these hazards. The Team Leader, Superintendent or
Supervisor must decide whether the risks can be controlled adequately by the
proposed means, taking into account the controls required by any relevant procedure
and the competence of the person-in-charge. Once the task is identified as low risk,
it shall be forwarded for approval to proceed. If the Team Leader, Superintendent or
Supervisor is not completely assured that the risks will be adequately controlled by
proposed means and are medium or high risks, he shall ask for level-2 task risk
assessment.
Level 1 TRA must be carried out for the following:
(a)
Document No.:
PRO/SFTY/018
Issue Date:
Page 9 of 38
(b)
(c)
(d)
A new risk assessment will not be required for every task. Where a task has
previously been assessed and/or is covered by a procedure, it may not need a new
risk assessment. Where this is the case, the previous assessment or procedure
should be reviewed to ensure that the hazards and controls are still relevant and that
any site or job specific controls are identified. If condition is changed or an incident
occurs while the procedure or previously assessed TRA is in use, the whole
procedure, including the risk assessment, must be reviewed before it is re-issued.
For low risk tasks performed by competent people, no formal recorded risk
assessment is required as it is covered by the individuals competency and skill.
7.2
Level- 2
Level 2 is a more structured semi-quantitative assessment which is required when
competent person judges that there are greater hazards or complexities associated
with the task which require more rigorous assessment. A Level 2 TRA is carried out
by a team.
The following are considered high-risk activities that require level 2 TRA, written
procedures, and Permit to Work (PTW) as well:
a)
b)
Trench Excavation or pit more than 4 feet deep or other ground penetration
such as piling.
c)
d)
e)
f)
g)
h)
i)
j)
k)
Mud plugging and hot tapping for tanks or main oil & gas lines.
l)
Document No.:
PRO/SFTY/018
Issue Date:
Page 10 of 38
8.0
m)
n)
o)
HITRA PROCEDURE
The first part of the procedure is to establish what it will involve, once the task is
identified. The initial appraisal should identify the need of special safety assessment
and identify at the outset, if it is obvious that the task cannot be carried out safely. If
the hazards are not reconciled at this stage, the task should be rejected or redefined.
The Task Risk Assessment procedure is shown in the flow chart (Appendix-1) and
following sections give guideline to each stage of the process.
8.1
Work Request
Work request can be in the form of written or verbal request to carry out any work.
The originator of the work request can be from any department of Pakistan PU.
8.2
8.3
Document No.:
PRO/SFTY/018
Issue Date:
Page 11 of 38
8.5
The need for any special safety studies or assessments (e.g. manual handling).
If the hazards cannot be reconciled and it is obvious that carrying out of task is
unsafe, it should be immediately discarded or redefined.
What personal competency requirements are needed of those who will assess
the risks and perform the task
assemble a team of persons with intimate knowledge and expertise of the task
(including knowledge of the task location)
examine all the hazards associated with the task in a structured way
devise a set of controls which will ensure an acceptable level of risk is achieved
PRO/SFTY/018
Issue Date:
Page 12 of 38
and the application of additional controls. Level-2 TRA is mandatory for activities
defined in section 7.2
8.6
Technician(s)
HSE representative
Other members of the workforce or persons external to the site who may have
specialist knowledge or experience which could help with the Assessment.
This requires knowledge and experience of the area, plant, equipment or system to
be worked on and awareness of the hazards involved and the potential
consequences, and knowledge of companys HSE procedures. The team shall have
personnel who:
Are competent to conduct TRAs and have the ability to facilitate the process.
The team shall discuss and carry out preparatory work, job plan review to ensure that
the team members have sufficient background information on which to base their
judgment. The team member shall visit the work site to see the physical layout of the
area and current site conditions. Particular attention shall be given to other plants or
equipment in the area. It shall also be noticed that other adjacent activities are not
planned to take place at the same time as the task to be performed as they could
impact the TRA.
The team leader shall make arrangements for the team to work as a group and shall
ensure that there is adequate space for examination of drawings and that sufficient
time is allocated to reach a rational decision.
Note the Control of Work Group Standard states that:
Document No.:
PRO/SFTY/018
Issue Date:
Page 13 of 38
All Risk Assessment teams must include at least one representative from the
workforce assigned to carry out the task being assessed. Where more than one team
is assigned to carry out the work, a representative from each should be included.
8.7
8.8
Identify Hazards
The team shall list down all significant hazards in a particular activity and then review
them to determine what foreseeable effects they could cause if not eliminated or
controlled. This should be done by way of full group discussion under the direction
of the TRA team leader to ensure that all members are given adequate opportunity to
express their views. To identify the hazard, following aspects of the task should be
considered as minimum:
Characteristics of the plant and systems directly involved, e.g. pressure, noise,
temperature, voltage, H2S, toxic chemicals, foam, sand, wax, sludge, scale, etc.
Consider the hazard effects of, and actions to be taken in the event of an
emergency. Refer to the BP Group Standard for the Control of Work (Element 5).
The team shall note down all the hazards identified for each activity so the
consequences can be identified.
A generic hazards checklist is provided as a guide in Appendix 3.
8.9
Document No.:
PRO/SFTY/018
Issue Date:
Page 14 of 38
be more than one, shall be identified and recorded in TRA form (See Appendix 5).
While writing Hazard Effects, care should be taken to be as specific as possible, i.e.
one should avoid expressions such as personal injury in the Hazard Effects column.
8.10
The worst, reasonably credible severity of the hazard effects, should anything go
wrong, based on (What if? Then), i.e., how severe the consequences could be,
realistically. (Almost all hazards could result in death but most realistic outcome
should be considered. For example, it is remotely possible that someone falling
off a chair in an office may be killed, but the most probable result is bruising or a
fractured bone). See Table 8.10.1.
The probability of the hazard being realized and resulting in the specified hazard
effect. See Table 8.10.2.
It is important to consider property damage and environmental impact and not just
personal injury. The matrix method of making these evaluations helps to focus
attention on the most serious risks. For the purposes of consistency this matrix
should be used when assessing risk.
RISK (R) = Hazard Effect (HE) x Probability (P)
Document No.:
PRO/SFTY/018
Issue Date:
Page 15 of 38
HAZARD EFFECT
HAZARD
EFFECT
RATING
VERY
HIGH
PEOPLE
MULTIPLE
FATALITIES
FATAL INJURY
HIGH
MEDIUM
LOW
VERY
LOW
Document No.:
PERMANENT
DISABILITY
LOST TIME
HOSPITALIZATION
TEMPORARY
DISABILITY
NO LOST TIME NO
HOSPITALIZATION
FIRST AID
FACILITIES
LOST
PRODUCTION
ENVIRONMENT
MAJOR
DAMAGE
MAJOR
DAMAGE
TOTAL LOSS OF
PRIMARY
CONTAINMENT.
LOSS > $ 10
MILLION
LOSS > $ 10
MILLION
SIGNIFICANT
DAMAGE
SIGNIFICANT
DAMAGE
LOSS $ 01
MILLION TO
$10 MILLION
LOSS $ 01
MILLION TO
$10 MILLION
MODERATE
DAMAGE
MODERATE
DAMAGE
LOSS $100K
TO $ 01
MILLION
LOSS $100K
TO $ 01
MILLION
MINOR
DAMAGE
MINOR
DAMAGE
LOSS $10K
TO $ 100K
LOSS $10K TO
$ 100K
LOSS <$10K
LOSS <$10K
SPILL OF MORE
THAN 100 BBLS.
SIGNIFICANT
LOSS OF
PRIMARY
CONTAINMENT.
SPILL UP TO 100
BBLS.
SIGNIFICANT
LOSS OF
PRIMARY
CONTAINMENT.
SPILL > 10
BBLS.
MINOR LOSS OF
PRIMARY
CONTAINMENT.
SPILL < 10
BBLS.
SLIGHT LOSS
OF PRIMARY
CONTAINMENT.
SPILL < 1 BBL.
PRO/SFTY/018
Issue Date:
Page 16 of 38
8.10.2 Probability
Likelihood of event occurring and resulting in the specified Hazard Effect
Probability of occurrence more than once per month
P Rating
Every Time
Very High
(VH)
High
(H)
Often
Medium
(M)
Sometimes
Low
(L)
Hardly Ever
Very Low
(VL)
Risk (R) is derived from matrices showing Hazard Effect (HE) and Probability (P).
These matrix values are presented to allow a semi-quantitative derivation of Risk to
provide consistent application of policies regarding the acceptability of risks Refer
to Table 8.10.3.
8.10.3 Risk Matrix
PROBABILITY
Document No.:
VL
VH
VH
11
20
21
22
25
12
18
19
24
13
17
23
14
16
VL
10
15
PRO/SFTY/018
Issue Date:
Page 17 of 38
21 - 25
CONTROL ACTIONS
Immediate Action. Task must not proceed due to serious loss potential.
Task should be re-defined or, further control measures put in place to
reduce risk, these controls again must be subject to a full assessment and
accepted before the task may commence.
Task may only proceed following direct authorisation from OM / area
authority following consultation with any specialist personnel and full
assessment team.
16 - 20
Wherever possible the task should be re-defined to take account of the
hazards involved or, the risk should be reduced further prior to the task
commencing.
11 - 15
The task may proceed, however only under strict supervision and
monitoring. The team must revisit all areas of the assessment to see if risks
may be reduced further before the task is allowed to proceed.
6 - 10
3-5
12
Once the risk rating has been determined, the next stage is to identify the controls
that are required to reduce /control the risk.
8.11
Identify Controls
The task.
The team must work systematically through the list of hazards to specify all the
methods needed to control each of their associated risks. Existing controls must be
recorded, as well as any additional ones that the team considers necessary to
achieve an acceptable level of overall control. The risk rating scale should be used as
a guide for this purpose. A Hierarchy of Control (Table 8.11.2) may be used together
with the Typical Control Examples as a guide in order that a full range of controls is
considered and that emphasis is placed upon controls at source. Wherever possible,
measures higher in the hierarchy should be used, providing that they are reasonably
Document No.:
PRO/SFTY/018
Issue Date:
Page 18 of 38
practicable. When the control actions have been identified the Evaluation and
Prioritization Matrix (Table 8.10.4) should again be used to establish the level of
residual risk once these controls are in place.
A combination of measures will usually be necessary in order to reduce the level of
risk to that which is considered as low as reasonably practical.
8.11.2 Hierarchy of Control
BASIS OF CONTROL
Prohibit
Substitute
Segregate
Change Process
Enclosure
Reduced Exposure Times
Dilution
Extraction
Knowledge
Personal Protective Equipment
EXAMPLES
No smoking
No stacking over specified height
No unauthorized personnel
Solvent based paint with water based paint
Electric hand tools with pneumatic tools
Barrier
Guard
Separate storage areas
Physical isolations (Spade, Lock-off)
Automated
Semi-automatic
Top of containers
Noise enclosures of turbines/pumps
Job rotation
Breaks
Dispense dilute chemical
Increase airflow / ventilation through work area
Welding
Grinding
Training
Competency
Gloves
Goggles
Boots
Respirators
Note: It is important not to write any of the basis of control (e.g. Prohibit) under
Control in the TRA form. Full details should be inscribed, e.g. No unauthorized
personnel.
An illustrative graphic reproduced from the UK Offshore Industry Step Change in
Safety guidance for Task Risk Assessment is shown below. It must be emphasized
that when identifying control measures, one must always start from the first or
lowest step.
Document No.:
PRO/SFTY/018
Issue Date:
Page 19 of 38
Document No.:
PRO/SFTY/018
Issue Date:
Page 20 of 38
Physical
Procedural
Time
(no change in
consequence, risk reduced
by limiting exposure)
Contingency / Control /
Mitigation:
(no change in likelihood,
but consequences are
reduced when the hazard is
realized)
Typical Examples
Ensure competency of personnel
Use of independent specialist personnel
Regular or constant monitoring of the task
Clear instructions and warnings to workforce
Clear definition of roles and responsibilities during the task
Adequate supervision
Conduct Tool Box Talk (TBT)
Removal of pipe work
Insert spade or blank flange
Lock off valve
Place mechanical barrier
Use locked enclosure
Keep people at a distance (warning tape)
Eliminate or substitute toxic substances
Substitute noisy machinery
Use mechanical handling equipment, etc.
Test for pressure build-up or leaks
Test for flammable gas
Procedure for control of simultaneous or adjacent work
Prohibition of hot work
Equipment locked-out/tagged-out.
Scafftag procedure.
Limit duration of the task
Use time-saving measures such as hot bolting, good work-site
preparation and planning for movement of materials, tools, etc.
Rotational work and applying interim break time.
Emergency shutdown, deluge and blow down systems,
reduction of inventory, etc.
Temporary refuge, emergency response system, water curtain,
provision of PPE, rescue equipment, etc.
The team should specify controls in all these categories, to the extent that they are
appropriate. Particular emphasis, though, must be placed on physical or procedural
controls that prevent or reduce risk by reducing the probability of occurrence or the
severity of consequences as well as on task-specific contingency/emergency
arrangements to control or mitigate the consequences if anything does go wrong.
8.12
Controls Adequate
Once all the controls are identified to reduce the risk, the following questions should
be asked:
Have all the necessary controls measures been fully / effectively identified?
Document No.:
PRO/SFTY/018
Issue Date:
Page 21 of 38
When all the controls of task are identified, the risk evaluation matrix should be
revisited to establish the level of residual risk once these controls are in place.
8.13
8.14
Does a plan exist to implement any outstanding Control Measures before the
Task is begun?
8.15
Date of TRA
Task Title
Location
Document No.:
PRO/SFTY/018
Issue Date:
Page 22 of 38
Distinct activities
Hazard identified
ALARP (Y/N)
Hazard Effects
8.16
Review of TRA
A Review of TRA should be done:
a)
b)
c)
Communication
The success of TRA will depend on how effectively it has been communicated. The
value of the risk assessment will be wasted if the people executing the job are not
fully aware of, or do not thoroughly understand, the hazards and the precautions put
in place. The TRA team shall distribute the copies to all concerned to give
understanding of:
An opportunity shall be provided to all involved in the task to identify further hazards
and control measures, which might have been overlooked in the initial assessment. If
such improvements are identified, this should be fed back to the TRA Team Leader.
8.18
Implement Controls
There are two types of control measures that will be identified from either Level 1 or
Level 2 TRA process:
Prerequisite controls: Controls that must be in place prior to the job execution.
These may, or may not, include a Permit to Work and associated documentation
Document No.:
PRO/SFTY/018
Issue Date:
Page 23 of 38
Before the task is authorised to start the person controlling the work activity must
satisfy himself that:
8.19
the persons allocated to perform the task, are competent to initiate and manage
the required supplementary controls
the output from the risk assessment has beencommunicated in writing and
signed off by all involved in the task. (this is a requirement of the Control of
Work Group Standard)
8.20
8.21
TRA records
In the event of an accident, incident, or near miss taking place, it is critical that the
TRA is reviewed. Three types of error may have contributed to the accident, each of
which requires different remedial actions:
hazard and controls identified, but controls not implemented as defined in TRA
Lessons learned are communicated to all concerned through existing methods such
as meetings, circulars, training, toolbox talks, etc.
Document No.:
PRO/SFTY/018
Issue Date:
Page 24 of 38
WORK REQUEST
8.1
LEVEL-2 (MANDATORY)
CHECK TASK
CATEGORY
8.2
MANDATORY?
NO
YES
PERFORM LEVEL-1
LEVEL-2 TRA
TRA
HIGH OR
MEDIUM RISK
8.3
8.5
FORM TRA TEAM
8.6
DEFINE TASK
PARAMETER
8.4
ACTIVITIES
BREAK DOWN
8.7
LOW RISK
IDENTIFY HAZARDS
for each activity
8.8
FIND ASSOCIATED
HAZARDS for each
activity
LEVEL-1
8.8
IDENTIFY
CONSEQUENCES
for each activity
8.9
DEFINE RISK RATINGS
8.10
IDENTIFY CONTROLS
8.11
NO
CONTROLS
ADEQUATE?
8.12
YES
RESIDUAL RISK
ACCEPTABLE?
YES
APPROVAL TO PROCEED
NO
8.13
8.16
*
8.17
8.14
DOCUMENT & RECORD
8.15
IMPLEMENT
CONTROLS
8.18
STOP
8.19
MONITOR FOR
CONDITION CHANGE
CARRY
OUT TASK
RE-ASSESS IF
REQUIRED
8.20
RECORD LESSONS
LEARNED
IF CONDITIONS
CHANGE
8.21
Document No.:
PRO/SFTY/018
Issue Date:
Page 25 of 38
Using high potential sources of ignition inside tank bund wall area,
for gas blowout / flare lines, or for oil & gas well casing repair.
Mud plugging and hot tapping for tanks or main oil & gas lines.
including
vessel/tanks,
cleaning,
Document No.:
PRO/SFTY/018
Issue Date:
Page 26 of 38
Electrical
Pressure
Document No.:
Examples of Hazards
Two moving parts, one moving part and a
fixed surface
Conveyor belt and drive
V belt and pulley
Power press
"In running nips"
Mangle
Guillotine Scissors
Stapler
Using hammer
Something that may strike or stab someone
or can be struck against
Moving vehicle
Drill
Sewing machine
Hypodermic needle
Pendulum
Crane hook
Something sharp or with a rough surface
Knife, chisel, saw, etc.
Fan blade
Circular saw blade
Sanding belt
Abrasive wheel
Hover mower blade
Drill chuck and bit
Power take off shaft
Pipe threading machine
Abrasive wheel
Cartridge tool
Using hammer and chisel
Abrasive wheel
Electricity above 240v
Electricity 240v
Electricity 110v
Extra low volt electricity
Static
Batteries
Compressed air
Compressed gas
Steam
Vacuum
Hydraulic system
PRO/SFTY/018
Issue Date:
Hazard Effects
Trapping (crushing,
pressing, drawing in
and shearing injuries)
Impact (includes
puncture)
Contact (Cutting,
friction or abrasion)
Entanglement
(rotating parts)
Ignition sources
Release of energy
(Explosion/injection/
implosion)
Page 27 of 38
Category
Stored energy
Thermal
Radiation
Ionizing
radiation
Non ionizing
radiation
Noise
Vibration
Stability
Overload/
Defective due to
mechanical
failure
Document No.:
Examples of Hazards
Springs under tension
Springs under compression
Hoist platform cage
Conveyor tension weight
Raised tipper lorry body
Counterweight
Load carried by crane
Hot surface
Using blow lamp
Welding flame/arc
Refrigerant
Steam
X Rays
or radiation
Neutrons
Micro wave
Radio frequency
Laser
Ultra violet
Infra red
Noise > 85 dB(A)
Pneumatic drill
Operation of plant
Using Jackhammer
Inadequate crane base
Fork lift truck on slope
Machine not bolted down
Mobile scaffold too high
Scaffold not tied
Crane overload
Chain sling
Eye bolt overload
Scaffold overload
Hopper overload
PRO/SFTY/018
Issue Date:
Hazard Effects
Flying/Falling
materials
Burns/fires/scalds/
frostbite
Burns, cancer
Burns
Crushing
Page 28 of 38
Increased Combustion
Flammable
substances (inc.
Highly and Extremely
Flammable)
See also explosive
below
Oxidizing substance
Dust explosions
HEALTH HAZARDS
Corrosive/Irritating
materials
Particles
Vapors
Fumes
Gases
Document No.:
Examples of Hazards
Timber stack
Paper sore
Grease
Plastic foam
Oxygen enrichment
Petrol
Propane gas
Crude oil
Methane
LPG
LNG
Hydrogen
Carbon Monoxide
Organic peroxide
Potassium permanganate
Nitric acid
Explosive material
Detonators
Some oxidizing agents
Highly flammable gas in confined
space
Wood dust
Sulfur dust
Coal dust
Flour
Aluminum powder
Sulfuric acid
Caustic soda
Ammonia
Asbestos fibers
Silica dust
Wood dust
Iron dust
Benzene
Toluene
Acetone
Some solvents
Lead fume
Rubber fume
Asphalt fume
Carbon Monoxide
Hydrogen Sulfide
Sulfur dioxide
PRO/SFTY/018
Issue Date:
Hazard Effects
Burns
Burns
Burns
Burns
Burns
Skin effects
Lung effects
Page 29 of 38
Mists
Category
Asphyxiants
Health hazard by
ingestion
Hazards by contact
ENVIRONMENTAL
HAZARDS
Hazardous waste
storage and disposal
Oil mist
Printing ink mist
Detergents
Aerosols
Examples of Hazards
Nitrogen
Carbon dioxide
Argon
Toxic, harmful, corrosive and irritant
liquids
All harmful aerosols
Polluted water
Contaminated food and drink
Sward
Rough timber
Concrete blocks
Molten metal
Frozen food
Crude/Condensate transportation
Storage of hazardous
sludge/material in pits
NORM waste (scales, sludge)
Hazard Effects
Acute and chronic
effects on health
Burns to upper
alimentary tract
Poisoning
Cuts, abrasions
Burns, Frostbite
Groundwater / Soil
pollution
Work at heights
Obstructions
Stacking/Storing
Document No.:
Examples of Hazards
Damaged floors
Trailing cables
Oil spills
Water on floors
Debris
Wet grass
Sloping surface
Uneven steps
Changes in floor levels
Fragile roof
Edge of roof
Work on ladder
Erecting scaffold
Hole in floor
Low headroom
Sharp projections
High stacks
Insecure stacks
Inadequate racking
Stacking at heights
PRO/SFTY/018
Issue Date:
Hazard Effects
Tripping, slipping
Falls
Striking against
Falling materials
Page 30 of 38
Work over/near
liquids, dusts, etc.
Emergencies
Tank
Reservoir
Sump
Sewer
Work over water
Locked exits
Obstructed egress
Long exit route
Trapping in fire
Repetitive
movements
Posture
Hazard Effects
Back injury, hernia,
etc.
Example of Hazard
Lifting
Lowering
Carrying
Pushing
Pulling
Hot / Cold loads
Rough loads
Live loads persons
Keyboard work
Using screwdriver
Using hammer and chisel
Bricklaying
Seated work
Work above head height
Work at floor level
Confined spaces
Document No.:
Example of Hazard
Glare
Poor lighting
Stroboscopic effect
Arc welding
Molten metal
Work in furnace
Cold room
Outdoor work
Hot weather
Cold weather
Wind chill factor
Work in rain, snow, etc.
Work in tank
Chimney, stack
Pit
Basement
Unventilated room
Vessel
Excavation
PRO/SFTY/018
Issue Date:
Hazard Effects
Eye strain, arc eye
and cataracts
Heat stress,
hypothermia
Heat stress, sunburn,
melanoma,
hypothermia, etc.
Asphyxiation,
explosion, poisoning,
claustrophobia, etc.
Page 31 of 38
Ventilation
Sick Building
Syndrome, nausea,
tiredness, etc.
Fumes
Odors
Tobacco smoke
Organization of work
Document No.:
Example of Hazard
Work above employees
Use of harmful substances
Contractors welding
Process fumes
Services (e.g. underground electricity
cables)
Stored hazardous materials
Monotonous work
Stress
Too much work
Lack of control of job
Work too demanding
Trailing cables
Traffic/ Plant / Rig movement
Work above public
Drilling near dwelling area
PRO/SFTY/018
Issue Date:
Hazard Effects
Injuries and ill health
to employees by
contractors work
Injuries and ill health
to contractors
employees by work in
premises
Injuries to employees
Page 32 of 38
Hazards associated with conditions which exist in the confined space before work take
place, for example lack of oxygen, presence of pyrophoric iron sulfide scales on the
inside shell, presence of sludge, and hydrogen sulfide gas.
2.
Hazards which can be introduced into the confined space by the work to be carried
out, and by the equipment/tools and materials to be used, for example using sparking
tools, electrical or pneumatic tools, artificial lighting, using cleaning detergents, etc.
Atmospheric hazards
Oxygen depletion
Flammable liquids/sludge/vapors/mists/gases
Electrical equipment
Hand tools
Detergents
Document No.:
PRO/SFTY/018
Issue Date:
Page 33 of 38
Obstructions/barriers
Limited access/egress
Connected pipe-works/valves/pumps/stirrers/heaters
Heat
Scaffold/ladder/staging
Noise/humidity
Environment pollution
Poor lighting
Biological hazards
Panic/claustrophobia/stress
Entry into confined space is a high-risk activity. A specified task risk assessment, job plan
and written procedures will be required. PTWS and relevant Certificates (e.g. Isolation and
Entry Certificates) is mandatory requirement in each work.
The following arrangements are an indication of the measures to be considered to eliminate
or reduce the risk of the hazards to an acceptable level and ALARP. The Team Leader must
ensure that the equipment, facilities, and working practices are maintained to these
standards by arranging inspections either personally or by a competent Superintendent or
Supervisor.
Arrangements
Planning and Organization
Before any operation commences, the Team Leader must establish if work in confined space
is to be carried out and if so, must arrange for information from operation manuals, P&IDs,
site visit, risk assessments, sampling, equipment, working procedures, training, etc. to be
provided, taking into account the hazards likely to be encountered.
Training and Instruction
Training will be provided through HSE department for all personnel required to carry out
testing and monitoring of atmospheres and for operatives required to use breathing
apparatus, rescue and permit procedures and any other equipment or procedures necessary.
Toolbox Talk (TBT) will be given to personnel before commencing the work.
Management Control
Competent Persons
Document No.:
PRO/SFTY/018
Issue Date:
Page 34 of 38
The planned procedures, including any permit to work systems, are carried out as
planned and that only authorized persons are permitted to enter the confined space
A person is stationed outside the confined space at all times that work is taking place
inside.
All equipment used for confined space work will be inspected by the user on each
occasion, a thorough examination must be carried out every month by the supervisor
and a record made of the examination. A more frequent examination may be required
depending on the circumstances of the specific method statement.
All safety equipment must be regularly maintained and record in accordance with
defined procedures. Any defects in equipment must be attended to immediately.
Document No.:
PRO/SFTY/018
Issue Date:
Page 35 of 38
APPENDIX 5
DATE:
TASK TITLE:
ACTIVITY:
LOCATION:
DESCRIPTION
S/No:
HAZARD
HAZARD EFFECT
RISK EVALUATION
(Refer to Evaluation Form)
HE
CONTROLS
ACTIONS TO BE TAKEN
DESCRIBE
ACTION
MANPOWER
RESIDUAL RISK
HE
ALARP
Y/N
SIGNATURE
Document No.:
P= Probability
PRO/SFTY/018
R= Risk Rating
Issue Date:
Authorizing
SignatoryDateTime..
SHEET
OF
Page 36 of 37
Document No.:
PRO/SFTY/018
Issue Date:
Page 37 of 37