REMEDIAL WORKS OF PHASE 1 FOR BESUT SETIU AGROPOLITAN (BSA) PROJECT, PANC

DEVELOPMENT
CONTRACT
12.0 SITE MEMO LOG
NO.

SITE MEMO REF.

21
54
61
87
105
106
109
134
136
138
144
169
170
171
173
174
178
179
180
181

ECER/BSAP1/020
ECER/BSAP1/053
ECER/BSAP1/060
ECER/BSAP1/086
ECER/BSAP1/104
ECER/BSAP1/105
ECER/BSAP1/108
ECER/BSAP1/138
ECER/BSAP1/140
ECER/BSAP1/142
ECER/BSAP1/148
ECER/BSAP1/173
ECER/BSAP1/174
ECER/BSAP1/175
ECER/BSAP1/177
ECER/BSAP1/178
ECER/BSAP1/182
ECER/BSAP1/183
ECER/BSAP1/184
ECER/BSAP1/186

191

ECER/BSAP1/198

198
199
200
201
124

ECER/BSAP1/205
ECER/BSAP1/206
ECER/BSAP1/207
ECER/BSAP1/208
ECER/BSAP1/125

FOR BESUT SETIU AGROPOLITAN (BSA) PROJECT, PANCHUR BEDERU, SETIU, TERENGGANU DARUL IMAN
DEVELOPMENT COUNCIL (ECERDC)
CONTRACT NO. : 4600000681

DESCRIPTION

MEMO DATE

Proper storage to reusable dismantled material


Delay due to late provision of preliminaries works
Improper stacking of BRC reinforcement
Cover to sand or earth material on lorries during transportation
Sand test report - report no. : SOIL022/15/R1322
Informing cracked portion at existing column of APU A10
Improper stacking of dismantled roof trust members
Wash trough condition and workability to maintain
Removal of demolished boulders from work area (APU's area)
Unavailability of portable salt-free water for site mix concreting works
Removal of demolished reinforcement steel bars from work area.
Remarking of dismantled Structural Elements from APU Type 2
Approval of welders
Inadequate Office and Site Equipment
NCR:ECER/BSAP1/NCR/014 - Damaged of Temporary Hoarding
Water spray to vehicle at wash trough no. 3 (behind site office)
Concrete Cube Test
Slow Progress in Micro Piling Works
Provision of drinkable water from SATU
Clearing of debris before piling work

10/26/2015
11/1/2015
11/5/2015
11/17/2015
11/30/2015
12/1/2015
12/2/2015
12/10/2015
12/13/2015
12/13/2015
12/14/2015
1/7/2016
1/7/2016
1/7/2016
1/13/2016
1/12/2016
1/13/2016
1/13/2016
1/13/2016
1/17/2016

NCR improper cover to dismantle APU's structural members - APU Type 2

1/25/2016

NCR on inoperative Wash Trough No.3


Keeping all excavation free from water
Failure of micropile cement grout strength test
Failure of concrete cube 7 days strength test - APU Type 1 : B36
RFI on pile cap construction at store and work area

2/2/2016
2/3/2016
2/4/2016
2/4/2016
12/6/2015

NGGANU DARUL IMAN FOR THE EAST COAST ECONOMIC REGION

REMARKS
Pending
Pending
Pending
Pending
Pending
Pending
Pending
Pending
Pending
Pending
Pending
Pending
Pending
Pending
Pending
Pending
Pending
Pending
Pending
Pending
Pending
Pending
Pending
Pending
Pending
Pending