RetainedLogic/OutofSequenceProgress

OriginalPlan

RetainedScheduleLogic(Acceptable)

ProgressOverRideLogic(Unacceptable)

.
2010M.C.Dean,Inc

ProjectCPMScheduling |1

RetainedLogic/OutofSequenceProgress(continued)

TheCPMnetworkisupdatedasoftheDataDate.IntheexamplebelowtheDataDateisworkday151.

ActivityAhasstarted,butasoftheDataDatetheactivityisestimatedbythesuperintendenttorequirean
additional5workdays(WD)tocomplete.

ActivityBhasstartedoutofsequencerelativetoitsplannedFinishtoStartrelationshipwithActivityA.It
isalsoestimatedbythesuperintendenttorequireanadditional5WDtocompleteafteractivityAhas
finished.

Notethathistoricalinformation(actualdates)arenotincludedintheforwardorbackwardpass
calculations.

RETAINIEDLOGICIGNORESTHEACTUALSTARTDATEANDLOOKSATTHEREMAININGWORKOFTHE
PREDECESSORANDWILLNOTPERMITTHEREMAININGWORKOFITSSUCCESSORTOBEGINUNTIL
THEPREDECESSORHASBEENCOMPLETED.ITRETAINSTHELOGICWHICHINTHISEXAMPLEISAFINISH
TOSTARTRELATIONSHIP

DataDate=151

EF=155

ActivityA
RD=5wd

151+51=155

Dashedlineis

impliednot

graphicallyshown
FSRelationship

EF=160

ActivityB
RD=5wd
156+51=160

FLOATVALUESWILLBEINCORRECTISUSINGPROGRESSOVERRIDEANDWILLSHOWMOREFLOATTHAN
THEREREALLYISNEVERUSEPROGRESSOVERRIDE

.
2010M.C.Dean,Inc

ProjectCPMScheduling |2