RELIABILITY SECTION
STATIONARY EQUIPMENT INSPECTION REPORT
Date of Inspection:
12/6/2011
Plant: PDH
Equipment No.: C 1302 Regen cooler blower
Description: 24 Discharge Nozzle(N2)
Reason for Inspection:
Operation notified about the presence of crack on Blowers discharge
nozzle on 9.6.11.
Inspection Summary:
The subject blowers nozzle was visually inspected and
observed about 125 mm transverse crack at pipe connection as can be seen
in the below attached photographs.
Page 1 of 3
Sahara
Petrochemicals
Company
Its Affiliates &
RELIABILITY SECTION
STATIONARY EQUIPMENT INSPECTION REPORT
Location
of crack
Transvers
e
Crack
Page 2 of 3
Sahara
Petrochemicals
Company
Its Affiliates &
RELIABILITY SECTION
STATIONARY EQUIPMENT INSPECTION REPORT
Recommendations:
Since the required material is not available, we will go for temporary repair as
mentioned below.
1.
2.
3.
4.
5.
6.
7.
8.
Reported by:
14/06/ 2011
Deva
Date: