Professional Documents
Culture Documents
SAP FI Bank Recon
SAP FI Bank Recon
Activity:
Bank Reconciliation
Step 1:
Step 2:
Step 3:
Step 4:
Step 5:
Step 6:
Page 1 of 27
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
Activity:
Bank Reconciliation
Step 1:
Pre-requisite:
a.
Downloaded copy of HSBC Hexagon Electronic Bank Statement in MT940
format.
b.
At this moment, this electronic bank statement function only applicable for the
following bank account: i)
HSBC Current Account MUR (001497163006)
ii)
HSBC Call Deposit Account MUR (001497163017)
Page 2 of 27
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
2. Remove item
:86:STANDING
INSTRUCTION 021
BAT
TO/FROM 017
DR BALANCE
As this item can cause error
during the import. However,
this line is merely for
information purposes. No
posting is required.
Page 3 of 27
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
Enter Document header data
1. Import Data : CHECK
2. Elect. bank statement
format: S
3. Statement file: Specify the
modified statement file
location and filename.
Posting Parameters
4. Assign value date : CHECK
Output Controls
5. Execute as background job:
CHECK
6. Print Bank Statement:
CHECK
7. Print posting log: CHECK
8. Print Statistics: CHECK
9. Separate list: CHECK
10. Select
Page 4 of 27
to execute.
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
Page 5 of 27
to execute.
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
Output Controller: List of
Spool Requests
16. Select the spool no
(Title = RFEBKA00)
and Select on the print
icon
OR
17. To change printer
settings,
Spool request ->
Print -> Print with
changed parameters.
OR
For displaying the cheque,
Ticked on the particular spool
follow by GOTO > Display
requests > Contents.
Page 6 of 27
to return to previous
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
19. Collect the print out
from the printer.
Page 7 of 27
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
The 1st Spool generated list
22. In this list, you will be able
to identify the line item
produce by the TEXT file.
23. This
list
provides
information such as: Header
a. Bank No.
b. House Bank
c. Account Number
d. Statement Number
e. Statement date
Line Item
a. Item No.
b. Value Date
c. Cheque
No.
/
References
d. Transaction type
NBOA - Bill Of Exchange
NBRF - Brokerage Fee
NCHG - Charges and Other
Expense
NCHK - Cheque
NCLR - Cash Letter / Cheque
Remittance
NCOL - Collections
NCOM - Commision
NDCR - Documentary Credit
NDIV - Dividends - Warrents
NEQA - Equivalent Amount
NECK - EuroCheques
NFEX - Foreign Exchange
NINT - Interest
NLBX - LockBox
NLDP - Loan Deposit
NMSC - Miscellaneous
NRTI - Return Item
NSEC - Securities
NSTO - Standing Order
NTCK - Travellers Cheques
NTRF - Transfer
NVDA - Value Date Adjustment
e. Amount in debit or
credit
Page 8 of 27
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
24. Notice the line item
00001, a message Error:
(F5 263) The difference
is too large for clearing
appear.
For
this
message, it can mean
only that: a. System not able to
find the value to clear
against.
b. System consists of
few same values.
Therefore, require use
to clear manually.
25. If
the
upload
is
successful, a posting
document will appear.
Notice the line item
00002,
a
document
number displaying at the
bottom acknowledging the
transaction made.
Page 9 of 27
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
28. Select
to exit
Page 10 of 27
to execute.
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
34. Notice that document has
been cleared and position
under cleared item.
35. Item left under open item
means cheque or
payment
un-presented.
Hence will be used for
Future
reconciliation
purposes.
Page 11 of 27
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
Step 2:
Page 12 of 27
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
2.
Application: 0001
3.
4.
5.
Page 13 of 27
6.
Select
7.
to execute.
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
Step 3:
5. Select
Page 14 of 27
for overview.
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
6. Double click on the bank to
further
drilldown
to
statement level.
7. The
next
list
display
statement uploaded into the
system with the statement
number attached.
8. Double
click
respective
number.
Page 15 of 27
on
the
statement
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
9. The next list display the
statement
line
item
uploaded.
10. Select
Page 16 of 27
to exit.
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
Step 4:
Pre-requisite:
a. This process applies to both items uploaded but posting failed OR,
b. Manual bank reconciliation
For this training material, the follow process describe the posting transfer fr
Menu path : Accounting Financial Accounting General Ledger Document entry
Enter G/L Account Document
Transaction code : FB50
This process posts the
transfer amount from Call
Deposit to Current Account.
Page 17 of 27
1.
2.
Posting
Date:
Insert
based on the date from
the statement
3.
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
4.
5.
D/C: Debit
6.
Amount: 160,298.50
7.
8.
9.
D/C: Credit
13. Select
document.
Page 18 of 27
to
to post the
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
with
5. Posting Key : 40
6. Account : 102400 (Main
account)
Page 19 of 27
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
7. Amount
:
Insert
the
amount needed to be
transferred.
8. Text : Bank Reconciliation
posting
9. Select on Process Open
Item icon.
Page 20 of 27
Process
Open
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
14.
Page 21 of 27
Select all
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
Page 22 of 27
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
17. Document -> Simulate
18. Select
Page 23 of 27
Save
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
Step 5:
IMPORTANT NOTE : This step is optional. Unless the cheque encashment date is
important to be listed together on the cheque register, otherwise, can be omitted.
Prerequisite:
a. This process is only valid whereby cheque numbers are maintained in the
system.
b. Manual bank reconciliation transfer with clearing. (Non electronic bank
statement)
c. Upload e-statement failed and transfer with clearing posting was made manually.
d. Transfer posting from outgoing account is made to main account.
Menu path : Accounting Financial Accounting Accounts Payable Environment
Check information Change Additional info/cash
Transaction code : FCH6
Page 24 of 27
1.
Paying
MU01
company
code:
2.
3.
4.
5.
Select
to execute.
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
6.
7.
Select
8.
Goto transaction
FCHN
code:
9.
Paying
MU01
code:
to save.
company
Page 25 of 27
to execute.
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
Notice on the last column,
comprise of encashment /
void date.
13. Enca./void:
06.04.2004
14. Select
Page 26 of 27
to exit.
e.g.
Project Islander
SAP 4.7 Training Material
Topic : Bank Reconciliation
Step 6:
to execute.
Page 27 of 27