1. Introduction
It is proposed to connect two 0.9MW wind turbines at the far end of the Castle
33/11kV radial network section at Myreshill No.2 secondary sub-station (see Fig 1.). The
network impedance and loading data are provided in the EXCEL file which can be found in
the module Blackboard site.
2. Tasks
(a) Analyse the voltage profile of the network for the following scenarios:
i
No generation from wind and Maximum system demand,
ii
Maximum generation and maximum system demand, and
iii
Maximum generation and minimum system demand.
(b) Critically analyse TWO of the impacts the proposed wind generators will have on the
operation of the original system, excluding the voltage profile.
(c) Propose and contrast three possible solutions to the network to make sure that the
statutory voltage limits are not breached with and without embedded generation.
Allocation of marks:- a-40%, b-30%, c-30%
Myreshill No.2
(Generator)
Myreshill No.1
Floors Road
Gilmour
(Linn Products)
Eaglesham
251 Sw/Stn
33/11kV
OLTC
System data can be obtained from the EXCEL file which will be made available in GCU
Learn site.
Castle Primary Substation