Demolition and Rebuild Structure Work Programme
Demolition and Rebuild Structure Work Programme
ID
TaskName
Duration
Start
Finish
Predecessors
21/11/15
25/10
6
ConstructionofCBPWall6
218days
Mon16/11/15Tue2/8/16
CH0150(1000mmDia)
218days
Mon16/11/15Tue2/8/16
Settingoutalignment
2days
Mon16/11/15 Tue17/11/15
Temporarysheetpile
15days
Wed18/11/15 Fri4/12/15
ExcavationandTransportExtraOver 20days
Earth
PreparingPlatform
3days
Boring&Concreting(140nos)
99days
Tue29/12/15 Tue26/4/16
HackingPile
60days
Sat20/2/16
Fri29/4/16
7FF+3days
CappingBeam
60days
Thu3/3/16
Wed11/5/16 8FF+10days
10
CantileverSlabandRetaining
Structure
Backfilling
50days
Thu12/5/16
Fri8/7/16
18days
Wed13/7/16 Tue2/8/16
11
11/4/16
7/2
25
10
13/3
26
13
29
14
21/6/16
17/4
30
16
22/5
1
17
1/
26/6
3
31/7
19
Wed23/12/15 Mon28/12/15 5
2Boringpointsperday
9
10,21FF
Ch150205(600mmDia)
84days
Wed27/4/16 Tue2/8/16
13
Settingoutalignment
2days
Wed27/4/16 Thu28/4/16
14
Temporarysheetpile
10days
Fri29/4/16
Tue10/5/16
13
15
Thu5/5/16
Sat21/5/16
14FS5days
16
ExcavationandTransportExtraOver 15days
Earth
PreparingPlatform
1day
17
Boring&Concreting(64nos)
32days
Wed27/4/16 Thu2/6/16
18
HackingPile
15days
Mon23/5/16 Wed8/6/16
17FS10days
19
CappingBeam
10days
Mon6/6/16
Thu16/6/16
18FS3days
20
CantileverSlabandRetaining
Structure
Backfilling
25days
Fri17/6/16
Fri15/7/16
19
15days
Sat16/7/16
Tue2/8/16
20
11
Mon23/5/16 Mon23/5/16 15
22
Finish
0days
Tue2/8/16
Tue2/8/16
23
DemolitionandReconstructExisting
KPKT'sStructure
Methodstatementapproval
121days
Wed2/3/16
Wed20/7/16
1day
Wed2/3/16
Wed2/3/16
24
24
3/1
9
12
21
22
1/2/16
29/11
8
25
Preparationworks
30days
Thu3/3/16
Wed6/4/16
26
Hackingofstructure
30days
Thu7/4/16
Wed11/5/16 25
27
Rebuildofexistingstructure
60days
Thu12/5/16
Wed20/7/16 26
2/8
24