Project Charter:
Custom House
Eric Hunt, Elise Hodges, Peter Hsiao, Vicky Hsu, Mia Quinn

Table of Contents
Introduction....................................................................................................................................2
High Level Project Purpose/Justification..............................................................................................................2
Project Scope.........................................................................................................................................................2
Key Stakeholders...................................................................................................................................................2
Project Budget/Cost...............................................................................................................................................3
Project Timeline....................................................................................................................................................3
Milestones & Delieverables..................................................................................................................................3
Approvals..............................................................................................................................................................3

Scope Statement.............................................................................................................................4
Scope of this Project..............................................................................................................................................4
Solution Overview.................................................................................................................................................4
Project Deliverables Overview & High Level Milestone Plan............................Error! Bookmark not defined.
Assumptions..........................................................................................................................................................5

3
Project Name: Custom House
Project Sponsor: Shawn Alborz.
Project Manager: Eric Hunt. Peter Hsiao. Vicky Hsu. Mia Quinn. Elise Hodges.

Introduction
High Level Project Purpose/Justification
Our purpose as the developer is to create a model home that provides spacious home designs
with high quality workmanship, energy saving construction and state-of-the-art architectural
designs for comfortable family living.

Project Scope
The scope of this project is a two story home with a wooden foundation (upper, cement as a
base) and stone walls. The timeline for it is 3 months and the projected Contractor cost is 1520%of the total Production Cost. Upon completion, the new property will include the following
as described in the listed specifications.
Lot size 1 acre
Energy efficient lighting
4800 sq/ft
Walk in closets
Two Story
State-of-the-art appliances
4 Bed
Granite Kitchen Counter Tops
3 Bath
Marble Bathroom Counter Tops
Fully Landscaped
Intercom system
Pool
Cable/Internet Ready
Hardwood Floors

Project Requirements
The house must be within 4800 square feet. The master bedroom will be 16x16 square ft, and the
other two will be 10x10 square ft. Kitchen, laundry room, and bathrooms will be fully appliance
with state-of-the-art equipment. Backyard will have an in-ground swimming pool along with a
patio. Front and backyard will be fully landscaped. There will be tile and wood floors throughout
the home, marble countertops in the bathroom and granite in the kitchen. This project has an
Expenditure of 300,000 dollars and must be built within 3 months of the start of project.

Key Stakeholders
The Key Stakeholders are listed below.
Construction
Architect
Shawn (sponsor)
Vendors
Suppliers
Government (monitoring water and drainage provision)
Homeowners association

Project Budget/Cost
The budget is $300,000.

Project Timeline
The project must be completed within three months of the initial start date. The following
includes a more detailed breakdown.
Week 1
Site
Preparation

Week 2-5
Footing
Foundation
and Framing

Week 6-8
The Guts:
Heating and
Cooling
Systems,
Insulation,
and Electrical

Week 9-11
Flooring and
Paint

Week 12
Fixture and
Appliances/final
Touches

Milestones and Deliverables

As described above there is a three month time limit and the milestones and deliverables are as
follows in the table below.
Milestones
Blueprint
Foundation

Construction

Completion
Acceptance Review

Approvals
Project Sponsor Name and Signature:
Project Manager Name and Signature:

Deliverables
Completed and Approved
Footings Poured and Set
Foundation poured, block construction
complete, foundation set
Home and Garage exterior closed to
weather
Driveway and Landscape complete
Interior and exterior wiring complete
Drywall and Insulation added
Flooring installed
Interior and exterior plumbing complete
Interior and exterior painting and finish
complete
Walk through complete
Pass regulatory inspections
Approval signatures obtained

Scope Statement
Scope of this Project
The scope of this project is a two story home with a wooden foundation (upper, cement as a
base) and stone walls. The timeline for it is 3 months and the projected Contractor cost is 1520%of the total Production Cost. Upon completion, the new property will include the following
as described in the listed specifications.

Lot size 1 acre


4800 sq/ft
Two Story
4 Bed
3 Bath
Fully Landscaped
Pool
Hardwood Floor

Energy efficient lighting


Walk in closets
State-of-the-art appliances
Granite Kitchen Counter Tops
Marble Bathroom Counter Tops
Intercom system
Cable/Internet Ready

Solution Overview

We are building the model home for the developer with the above specifications.

Project Deliverables Overview

The chart below explains the different deliverables of our project and what falls
underneath each deliverable.

Custom
Home

Foundati
on

Blueprint

Attain
Permits

Complet
ed &
Approve
d

Footings
poured &
set

Home &
Garage
exterior
closed

Acceptan
ce
Review

Completi
on
Foundati
on
poured &
set

Drivewa
y&
Landsca
pe

Interior
&
exterior
wiring

Construc
tion

Drywall
&
insulatio
n added

Pass
Inspectio
ns

Walk
through

Flooring
installed

Interior
&
exterior
plumbin
g

Interior
&
exterior
painting
& finsh

Approval
Signatur
es
obtained

House
Complet
ed

High Level Milestone Plan (HLMP)

These are the milestones to be completed for this project

Key Milestones

Blueprint

Completed & Approved

Foundation

Footings poured & set

Foundations poured & set

Construction

Home & Garage exterior closed

Driveway & Landscape

Interior & Exterior Wiring

Drywall & Insulation

Flooring

Interior & Exterior Plumbing

Interior & Exterior Painting/Finish

Completion

Walk through

Pass inspections
Acceptance Review

Approval Signatures

Target Date

January 1-7

January 7,
2015
January 7-31

January 17,
2015

January 31,
2015
February 1-March 15

February 11,
2015

February 18,
2015

February 23,
2015

March 1, 2015

March 7, 2015

March 12, 2015

March 15, 2015


March 15-23

March 20, 2015

March 23, 2015


March 23-30

March 30, 2015

Assumptions
In the project scope we are assuming that:
Materials will be readily available
Everything not included in the scope will not be a part of the project
Workers will work all their scheduled shifts
Employees will not go on vacation during the length of the project