BILL OF QUANTITIES
Item no.
104
803
404
405
700 3
1013
1032
Spl 3
Scope of
works
Embankment
Structure
excavation
Reinforcing
steel
Structural
concrete
Masonry works
(chb)
Corrugated
metal roofing
Painting,
varnishing and
other related
Electrical
works
TILE WORKS
Unit
Quantity
M^3
54.86
Unit
price(Php)
415.54
M^3
50
261.11
13,055.50
Kg.
902.58
91.00
82,134.78
M^3
33.94
5,780.59
196,193.22
M^2
117.78
756.99
89,158.28
l.m.
60
109.89
6,593.45
M^2
807
47.64
38,445.48
Job.
1.00
97,786.00
97,786.00
M^2
49.05
1103.76
54,139.43
TOTAL
Total amount
22,796.52
600,302.66
90,045.40
TOTAL ESTIMATED PROJECT COST
P 690,348.06
LABOR OUTPUT
ITEM
OUTPUT
EXCAVATION
EMBANKMENT
54.86M^3/3.87M^3/m day/3
REINF. BARS
FABRICATION
902.58kg/10kg/md/3
CONCRETING
33.94M^3/.91M^3/md/3
CHB
117.78M^2/2.4M^2/md/3
G.I. ROOFING
60sheets/15sheets/md/2
FINISHING
235.56m^2/7.8m^2/md/3
TRUSS
FABRCATION
TILE FLOOR
FINISHING
TOTAL
412.2kg/10kg/md/3
49.05M^2/1.5M^2/MD/3
# OF DAYS TO
FINISH
12.30
4.72
30.08
12.43
16.36
2
10.07
13.73
10.9
112.59 DAYS
PERT-CPM
START
ACTIVITY CODE :
A. EXCAVATION
FINISH= 48 DAYS
B. EMBANKMENT
C. REINF. BARS FABRICATION
D. CONCRETING
E. CHB
F. ROOF
G. WALL FINISHING
H. FLOOR FINISHING
13
C
17
13
10
11
FINISH