AST Reference Cell Installation Option 2

Above Ground Storage Tank (AST)

Bore Exit Point Varies


per Job Specifications &
Site Requirements

Bore Entry Point Varies


per Job Specifications &
Site Requirements

HDD Rig

Ring Wall
Depth Varies per
Job Specifications
Grade
Pilot Bore Path

Above Ground Storage Tank (AST)


See Above Ground
Access Below

See Above Ground


Access Below

Ring Wall

3" Solid PVC Pipe Extending from Tank Edge


to Above Ground Access on Each End

Product Installed in Bore-Hole via Pull-Back


Process by HDD Rig
3" Slotted PVC Pipe with Drain Sleeve Wrap
Extending Full Length of Tank Diameter

Above Ground Access


(Each End)
Fabricated Steel Frame
3" PVC Slip Cap with
Steel Eyelet

3" Solid PVC Pipe


1/4" Pull Rope

Grade
24" X 24" X 4" Thick Concrete Pad