Estimation of BasketBall court

S. No. Item

Nos.

D/H

Qty

Unit

Rate

Amount

425 Providing and placing in position RCC for roof,


beams, columns column footing lintels chhajjas,
balcony, stairs etc, excluding cost of reinforcement
but including centring, shuttering, proping,
finishing &curing etc.complete. 1:2:4

904b Providing and placing in position tested steel for


R.C.C. work including cutting, bending, binding etc.
as per drawings and placing in position complete
up to floor two level including cost of binding wire
and all wastage etc. complete.
reinforcement

29

15

130.5

78.5

29

15

0.15

130.5 cum.

0.5 5122.125 Kg

4488.6

585762.3

52.9

270960.4

250.5

217935.0

1220 Cement concrete flooring 1:2:4 (1cement, 2sand,


4graded stone aggregate, 20mm nominal size) laid
in one layer and finished with floating coat of neat
cement. 40 mm thick finishing in floor
1

870
Total =

20 % above tender rate =


1 % for labour welfare =
3.5 % for contingencies =
Gross Total =

1074657.7

214931.5
10746.6
37613.0
1337948.9
13.38 lacs