APPENDIX I

PAGE 1 OF 1

PROJECT: Bitumen storage and


Distribution Terminal Poject
WELD REPAIR REQUEST
CONTRACT NO. :
TO
:
REPRESENTATIVE OF CLIENT
FROM :
CONTRACTOR QAQC OR CONSTRUCTION

REQUEST NO.:
DATE
:

THIS WELD REPAIR REQUEST IS ISSUED FOR YOUR KIND APPROVAL


DESCRIPTION
a. Piece No.

: ..

b. Drawing No. : ..

d. Metal Type :
e.

Thickness.

SKETCH

FINDING

Approved by: Construction Manager: __________________________ Date:

Approved by: QA/QC Manager _______________________________ Date:

PROPOSE PROCEDURE :
1.
2.
3.
4.
5.
6.

CLEAN DEFECTIVE AREA TO BRIGHT METAL FINISH BY GRINDING.


PREHEAT TO ..
WELDING BY STRINGER BEAD USING ELECTRODE.SIZEMM
GRIND SMOOTH TO SURFACE GEOMETRY
CONDUCT N.D.T (MPI/PT/UT)
CONDUCT HARDNESS TEST

PREVENTIVE MEASURES/REMARKS:
..

ISSUED BY :

REVIEWED/APPROVED BY:

APPROVED BY :

QAQC/CONSTRUCTION

QA/QC MANAGER

CLIENT REPRESENTATIVE

DATE

DATE

DATE