Professional Documents
Culture Documents
Kurva S MPKK
Kurva S MPKK
Task Name
Duration
Start
Finish
Persiapan Pekerjaan
4 days
Tue 10/6/15
Fri 10/9/15
Survei
2 days
Tue 10/6/15
Wed 10/7/15
Pengumpulan Data
2 days
Thu 10/8/15
Fri 10/9/15
4 days
Mon 10/12/15
Thu 10/15/15
Load Flow
2 days
Mon 10/12/15
Tue 10/13/15
Short-Circuit
2 days
Mon 10/12/15
Tue 10/13/15
Koordinasi Proteksi
2 days
Tue 10/13/15
Wed 10/14/15
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 1
ID
Task Name
Duration
Start
Finish
Arch Flash
2 days
Tue 10/13/15
Wed 10/14/15
Transient Stability
2 days
Wed 10/14/15
Thu 10/15/15
10
Harmonic Analysis
2 days
Wed 10/14/15
Thu 10/15/15
1 wk
Mon 10/19/15
Fri 10/23/15
11
12
3 days
Mon 10/19/15
Wed 10/21/15
13
2 days
Thu 10/22/15
Fri 10/23/15
2 wks
Mon 10/26/15
Fri 11/6/15
14
Studi Integrasi
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 2
ID
Task Name
Duration
Start
Finish
15
1 wk
Mon 10/26/15
Fri 10/30/15
16
Pembuatan Solusi
1 wk
Mon 11/2/15
Fri 11/6/15
3 wks
Mon 11/9/15
Fri 11/27/15
17
Prosedur Operasi
18
2 wks
Mon 11/9/15
Fri 11/20/15
19
Finalisasi solusi
1 wk
Mon 11/23/15
Fri 11/27/15
1 wk
Mon 11/30/15
Fri 12/4/15
3 days
Mon 11/30/15
Wed 12/2/15
20
21
Presentasi Tahap I
Presentasi di Pertamina RU IV
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 3
ID
Task Name
22
23
Rencana implementasi
Evaluasi dan Penyempurnaan
Duration
Start
Finish
2 days
Thu 12/3/15
Fri 12/4/15
3 wks
Mon 12/7/15
Fri 12/25/15
24
2 wks
Mon 12/7/15
Fri 12/18/15
25
Penyempurnaan Implementasi
1 wk
Mon 12/21/15
Fri 12/25/15
1 wk
Mon 12/28/15
Fri 1/1/16
26
Presentasi Tahap II
27
2 days
Mon 12/28/15
Tue 12/29/15
28
3 days
Wed 12/30/15
Fri 1/1/16
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 4
ID
29
Task Name
Duration
Start
Finish
2 wks
Mon 1/4/16
Fri 1/15/16
30
Implementasi solusi
1 wk
Mon 1/4/16
Fri 1/8/16
31
Pengujian
1 wk
Mon 1/11/16
Fri 1/15/16
2 wks
Mon 1/18/16
Fri 1/29/16
32
Evaluasi Pengujian
33
Evaluasi sistem
5 days
Mon 1/18/16
Fri 1/22/16
34
5 days
Mon 1/25/16
Fri 1/29/16
1 wk
Mon 2/1/16
Fri 2/5/16
35
Finalisasi Proyek
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 5
ID
Task Name
36
Duration
Start
Finish
1 wk
Mon 2/1/16
Fri 2/5/16
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 6
Resource Names
Oct 4, '15
M T
Persiapan
Mengunjungi PT Pertamina RU IV
Mengunjungi PT Pertamina RU IV
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 7
Resource Names
Oct 4, '15
M T
Analisa Transient
Analisa Transient
Analisa Harmonisa
Analisa Harmonisa
Analisa Sistem
Analisa Sistem
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 8
Resource Names
Oct 4, '15
M T
Pemecahan Masalah
Pembuatan Solusi
Prosedur Operasi
Penyesuaian Solusi
Finalisasi
Presentasi I
Presentasi di Pertamina RU IV
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 9
Pemeca
Resource Names
Oct 4, '15
M T
Rencana Implementasi
Evaluasi
Penyempurnaan
Presentasi II
Presentasi di Pertamina RU IV
Implementasi lanjutan
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 10
Resource Names
Oct 4, '15
M T
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 11
Resource Names
Oct 4, '15
M T
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 12
Nov 1, '15
S M T
Nov 8, '15
S M T
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 13
Dec 6, '15
S M
Nov 1, '15
S M T
Nov 8, '15
S M T
ta yang Kurang
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 14
Dec 6, '15
S M
Nov 1, '15
S M T
Pemecahan Masalah
Nov 8, '15
S M T
Dec 6, '15
S M
Pembuatan Solusi
Penyesuaian Solusi
Finalisasi
Presentasi di Pe
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 15
Nov 1, '15
S M T
Nov 8, '15
S M T
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 16
Dec 6, '15
S M
Rencana I
Nov 1, '15
S M T
Nov 8, '15
S M T
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 17
Dec 6, '15
S M
Nov 1, '15
S M T
Nov 8, '15
S M T
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 18
Dec 6, '15
S M
Dec 6, '15
S M T
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 19
Jan 3, '16
S M T
Dec 6, '15
S M T
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 20
Jan 3, '16
S M T
Dec 6, '15
S M T
Presentasi di Pertamina RU IV
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 21
Jan 3, '16
S M T
Dec 6, '15
S M T
Rencana Implementasi
Jan 3, '16
S M T
Evaluasi
Penyempurnaan
Presentasi di Pertamina RU IV
Implementasi lanjutan
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 22
Dec 6, '15
S M T
Jan 3, '16
S M T
Implemen
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 23
Dec 6, '15
S M T
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 24
Jan 3, '16
S M T
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 25
Feb 7, '16
S M T
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 26
Feb 7, '16
S M T
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 27
Feb 7, '16
S M T
RU IV
anjutan
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 28
Feb 7, '16
S M T
Feb 7, '16
S M T
Implementasi solusi
Pengujian
Evaluasi sistem
Penyelesaian masalah pengujian
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 29
Task
Manual Summary
Split
Start-only
Milestone
Finish-only
Summary
External Tasks
Project Summary
External Milestone
Inactive Task
Deadline
Inactive Milestone
Baseline
Inactive Summary
Baseline Milestone
Manual Task
Baseline Summary
Duration-only
Progress
Manual Progress
Page 30
Feb 7, '16
S M T