ElecComp Inc.
ElecComp Inc. isa large contract manufacturer of
circuit boards and other high-tech parts, The
company sells about 27,000 high-value products,
whose life eyele is relatively short, Competition in,
this industry forces ElecComp to commit to short
lead times to its customers; this committed service
time to the customers is typically much shorter than.
manufacturing lead time. Unfortunately, the manu-
facturing process is quite complex including @
somplex sequence of assemblies at different stages,
Because of the long manufacturing lead time and
the pressure to provide customers with a short
response time, ElecComp kept inventory of finished
products for many of its SKUs, Thus, the company
managed its supply chain based on long-term
forecast, the so-called push-based supply chain
strategy. This make-to-stock environment required
the company to build safety stock and resulted in
huge financial and shortage risk.
Executives at ElecComp had long recognized that
‘his push-hased supply chain stratezy was not the
appropriate strategy for their supply chain
Unfortunately, because ofthe long lead time, a pull-
fnsed supply chain strategy, in which manufacturing
and assembly-are done based on realized demand,
‘ess not appropriate either,
Thus, ElecComp focused on developiny
supply chain strategy whose objectives are
1, Reducing inventory and financial risks.
2 Providing customers with competitive response
times.
This could be achieved by
* Determining the optimal focation of inventory
across the various stages of the manufacturing and
assembly process.
+ Caleulating the optimal quantity of safety stock for
teach component at each stage.
‘The focus of redesigning ElecComp’s supply chain
wes on a hybrid strategy in which a portion of the
supply chain is managed based on push, that is, a
Imuke-o-stock environment, while the remaining
portion of the supply chain is managed based on
pull, thatis, a make-to-order strategy. Observe that
the supply chain stages that produce to stock will be
the locations where the company keeps safety stock,
‘while the make-to-order stages will keep no stock at
all Hence, the challenge was to identify the location
in the supply chain in which the stratezy switched
from a push-based, that is, a make-to-stock, strategy
toa pull-based, that is, a make-to-order, supply chain
location is referred to as the push-pull
EleciComp developed and implemented the new
push-pull supply chain strategy, and the impact was
‘dramatic, For the same customer lead times, safety
stock was reduced by 40 to 60 percent, depending
‘on product line. More importantly, with the new
supply chain structure, EleeComp concluded that
they could cut lead times to their customers by 50
percent and still enjoy a 30 percent reduction in
safety stock
‘To understand the analysis and the benefltexpe-
rienced by ElecComp, consider Figure 3-11 in which
a finished product (part 1) is assembled in a Dallas
facility from two components, one produced in the
‘Montgomery facility and one ina different facility in
Dallas. Each box provides information about the
value of the product produced by that facility
‘numbers under each box ate the processing time at
that stage; bins represent safety stock. Transit times
between facilities are provided as well. Finally, each
facility provides committed response time (0 the
downstream facilities. For instance, the assembly
facility quotes a 30-day response time to its
‘customers. This implies that any order can be
satisfied in no more than 30 days, The Montgomery
facility quotes an 88-day response time to the
assombly facility. As a esult, the assembly facility
needs to keep inventory of finished produets in order
to satisfy customer orders within. its 30-day
‘committed service time.
Observe that if somehow ElecComp can reduce
the committed service time from the Montgomery
facility to the assembly foclity from 88 days to, sy.
50 or perhaps 40 days, the assembly facility will be
‘ble 10 reduce its finished goods inventory while the
Montgomery facility will need to start building
inventory. Of course, ElecComp’s objective is t0Agrayboxiss
prosesing age
Number under the bon
Tstheprocsing ine
FIGURE 9-14 How to read the diagrams.
minimize systemwide inventory and manufacturing
costs; this is precisely what Inventory Analyst™
from’ LogicTools (www.logic-tools.com) allows
users todo. By looking atthe entire supply chain, the
tool determines the appropriate inventory level at
each stage
For instance, if the Montgomery facility reduces
ts commited lead time 13 days, then the assembly
facility’ does not need any inventory of finished
goods, Any customer order will trigger an order for
parts 2 and 3, Part 2 will be available immediately.
Since the facility producing part 2 holds inventory,
‘while pat 3 will be available at the assembly facility
Sestak ot = 7410]
FIGURE 3-12 Current safety stock locaton.
. = = he
Number above the box
‘enumber of units
rie ake
“downsteam ut
tow the comment
fineto Bonet tage
a
Costin the bois the
‘ae of he product
Pins indeat safety
sock eeleshade
stock, emp means ne
‘atety tock
in 13 days: 13 days’ committed response time by the
‘manufacturing facility plus 2 days” transportation
lead time. It takes another 15 days to process the
‘order atthe assembly facility and, therefore, the oer
will be delivered to the customers within the
committed service time. Thus, in this case, the
assembly facility produces to order, that is, a pl
‘based strategy, while the Montgomery facility needs
to keep inventory and hence is managed based o
us, that is, a make-to-stock strategy.
Now that the trade-offs are clear, consider the
product structure depicted in Figure 3-12. Brows
boxes (parts 4,5, and 7) represent outside supplienSo I
[ons |
[GURE 3-13 Optimized sooty stock.
‘while black boxes represent internal stages within
lecComp’s supply chain. Observe that the assembly
facility commits a 30-day response time to the
asiomers and keeps inventory of finished goods,
More precisely, the assembly facility and dhe Facility
manufacturing part 2 both produce to stock. All other
slags produce to order.
Figure 3-13 depicts the optimized supply chain that
provides customers with the same 30-day response
time, Observe that by adjusting committed service
time of various intemal facilis, the assembly sytem
stuns prodiucing to order and Keeps no finished goods
Imentory. On the other hand, the Raleigh and
Montgomery facilities nee to reduce their commited
service ime and hence keep inventory.
So where isthe push and where is the pull inthe
optimized strategy? The assembly Facility and the
[EEz.
Dallas facility that produces part 2 both operate now
ina make-to-order fashion, that is, a pull strategy,
hile the Montgomery facility operates in a make:
torstock fashion, a push-based strategy. The impact
‘on the supply chain is a 39 percent reduction in
safety stock!
ALthis point, it was appropriate to analyze the
Impact of a more aggressive quoted lead time to
the customers. That is, FleeComp executives con-
Sidered reducing quoted lead times t0 the
‘customers from 30 days to 15 days. Figure 3-14
{epiets the optimized supply chain strategy in this
case. The impact was clea, Relative to the haseline
(Figure 3-12), inventory was down by 28 percent
‘while response time tothe customers was halved,
See Table 3-7 for a summary of the results of this
study.
FOURE 3-14 Optimized safety stock with reduced ead time.‘Saety stock ‘Lead tme to Inventory
hholang cost customer Oycietime tums
(Sivean) (Gays) (tursivear)
743100 ‘ 105 12
45400 2 105 va
53700 18 18 13
Finally, Figures 3-15 and 3-16 present a more
complex. product structure. Figure 3-15 provides
information about the supply chain strategy before
optimization and Figure 3-16 depicts the supply
chain. strategy after optimizing the push-pull
boundary as well as inventory levels at different
Pan
Page)
FIGURE 9-15 Current supply chain.
stages in the supply chain. Again, the benefit is
clear. By correctly selecting which stage is going to
produce to order and which is producing to stock
inventory cost was reduced by more than 0 percent
While maintaining the same quoted lead time tothe
customerspid enor
Say srk ast SVE
a
Pals)
FIGURE 3-16 Optimizes supa chan
‘To summarize, using « multistage inventory opt
mization technology (Inventory Analyst™ from
LogicTools), BlecComp was able to significantly
reduce inventory cost while maintaining and
Sometimes significantly decreasing quoted service
limes tothe customers. This was achieved by
1. Identifying the push-pull boundary; that is, iden-
tifying supply chain stages that should operate in
a make-to-stock fashion and hence keep safety
stock, The remaining supply chain stages operate
in a make-fo-order fashion and thus keep n0
Jwentory. This is done by pushing inventory to
Jess costly locations inthe supply chain
2 Taking advantage of the risk pooling concept.
This concept suggests. that demand for a
component used by a numberof finished products
has smaller variability and uncertainty than that
ofthe finished goods; see Chapter 2
3. Replacing traditional supply chain strategies
that are typically referred to as sequential. or
local, optimizarion by a globally optimized
supply chain strategy, In a sequential, oF local,
optimization strategy, each stage tries to
‘optimize its profit with very litle regard to the
impact of its decisions on other stages in the
same supply chain. On the other hand, in a
slobal supply chain strategy, the entire supply
chain strategy is integrated, so that strategies
are selected for each stage that will maximize
supply chain performance.
‘To better understand the impact of the new supply
chain paradigm employed by ElecComnp, consider
Figure 3-17, where we plot total inventory cost
against quoted lead time to the customers. The black
trade-off curve represents the traditional relationship
between cost and quoted lead time to the customers.Safety tock cost versus quoted Lead time
son
e000
som
oom
sso
ssoom4
swoon 4
swan |
same
sane |
«+
0 » ”
o 0 109
Led tme quote to aster ays)
curve isa result of locally optimizing decisions
at each stage in the supply chain, The brown trade-
‘off curve isthe one obiained when the firm globally
‘optimizes the supply chain by locating correctly the
push-pull boundary
‘Observe that this shift of the trade-off curve, due
to optimally locating the push-pull boundary, implies
1, For the same quoted lead time, the company ean.
Significantly reduce cost
2. For the same cost, the firm ean signticanlly
reduce lead time,
Aitional relationship between cost and customer
‘quoted lead time is smooth while the new trade-off
ceurve representing the impact of optimally locating
the push-pull boundary is no, with jumps in various
places. These jumps represent situations in which the
Jocation ofthe push-pull boundary changes and sig-
nificant cost savings are achieved,
}
Final, noice thatthe curve epeseting he tas
b, presenting he ts
}