KMV PROJECTS LTD- RVR PROJECTS PVT LTD (CONSO

AREA CALCULATION OF C-7 CONTRACT AS ON DATE 18/09/2

AS PER TENDER DRG (SQM)


MAIN STATION BUILDING
TOTAL

A
1
2
3

CONCOURSE LEVEL
MEZANINE LEVEL
PLATFORM LEVEL

2181.5
2258.8
3284.0

2962.3

2942.0

4670.8
2158.5
5867.3

2982.4

5143.8
2258.8
6266.4

6815.0

5881.6

12696.6

7724.3

5944.7

13668.9

STAIRCASE SOUTH
CONNECTING SLAB

179.1
951.4

304.1

483.2
951.4

225.7
270.6

380.0

605.7
270.6

STAIRCASE NORTH
CONNECTING SLAB

179.0
666.3

283.8

462.8
666.3

258.5
634.1

338.7

597.3
634.1

1975.7

587.9

2563.6

1388.9

718.7

2107.6

TOTAL AREA
B

1731.1
2158.5
2925.4

2939.7

AS PER THE EXECUTION DRG


(SQM)
MRS
SCS
TOTAL

ENTRY/ EXIT STRUCTURE


1ST LEVEL (GR FLR)

TOTAL AREA
C

2ND LEVEL (MEZ LVL)

STAIR CASE SOUTH


CONNECTING SLAB
STAIRCASE NORTH
CONNECTING SLAB
TOTAL AREA
D

133.8
992.4
134.0
716.0
1976.2

EXTRA CONNECTING SLAB


PLATFORM LEVEL
STAIRCASE SOUTH
STAIRCASE NORTH
TOTAL AREA

0.0

WATER TANK

TOTAL AREA

133.8
992.4
134.0
716.0

163.1
424.3
182.2
425.4

0.0

1976.2

1194.9

0.0

1194.9

276.3
246.0

276.3
246.0

474.7
632.1

302.7
258.1

777.5
890.2

522.2

522.2

1106.9

560.8

1667.7

114.2
3951.9

1224.3

114.2

5176.2

120.4
3690.7

163.1
424.3
182.2
425.4

126.9
1279.5

247.3

5217.5

LTD (CONSORTIUM)
DATE 18/09/2012

DIFFERENCE IN AREA

972.3

TENDER COST

236120766.0

33731538.0

41.3

REVISED COST

41.3