Pressure Test Step

MAS

1. Test Pressure (P test) 20 BarG


Pressure
Holding Time
30 Minute

Test Pressure

Leak Test & Inspection


Design
Pressure
25% Design

10 Min.

Pressure

2. Test Pressure (P test) > 20 BarG - 50 BarG


Pressure

Holding Time
30 Minute

Test Pressure
Design

Leak Test & Inspection

10 Min.

Pressure
50% Test
Pressure

25% Design

10 Min.

Pressure

3. Test Pressure (P test) 50 BarG


Pressure
Holding Time
Test

Design

30 Minute

Pressure

10 Min.

Pressure
75% Test

10 Min.

Pressure
50% Test
Pressure

10 BarG

10 Min.

Leak Test & Inspection

MAS

1.
2.
3.
4.

Pressure Test Step

Increase pressure with pressure rate 3-5 Barg /Minute


Hydrostatic test at XX Barg. (XX time of Design Pressure) Holding Time
Decrease pressure to design pressure for leak test. Holding at pressure unt
After inspection, Decrease pressure with pressure rate 3-5 Barg/Minute

Remark

Ref. No.
Date
25/2/2011

Time (Min)

Time (Min)

Time (Min)

Page
1/1

(Min)

Ref. No.
Date
25/2/2011

Holding Time 30 Minute


at pressure until inspection to be finish