Traffic Diversion Proposal v3
Traffic Diversion Proposal v3
Traffic Diversion Proposal v3
FLYOVER
TRAFFIC DIVERSION
PROPOSAL
CLIENT : Jabatan Kerja Raya
CONTRACTOR : Wan Manan SDN. BHD.
CONSULTANT : Mesh Engineers SDH. BHD.
TABLE OF CONTENTS
Purpose ..................................................................................................................................... 3
2|P a ge
1 Purpose
The purpose of this report is to document the locations and scope of works for the temporary road
diversions for the Flyover Bridge project.
3|P a ge
4|P a ge
5|P a ge
6|P a ge
7|P a ge
8|P a ge
4 Scope of Works
No.
Item
1
1.1
Temporary Drainages
Provide earth drains/ channels along the temporary road including maintenance during construction
period as approved and directed by the S.O.
2.
2.1
Pavement
Preparation of formation as specified and as directed by the S.O. for receiving temporary road pavement.
2.2
Crushed rock aggregate 350mm thick as roadbase material complying with grading limits as per Standard
Specifications.
2.3
2.4
Asphaltic concrete wearing course (AC14) 50mm thick including maintenance during construction period.
3.
3.1
4.
5.
6.
Diversion 1
Diversion 2
Diversion 3
Diversion 4
Resurface/Wearing
Course
500m
900m
175m
-
2m Road Widening
(1m each side)
500m
600m
-
Full Roadworks
150m
9|P a ge
10 | P a g e
11 | P a g e
Temporary Diversion 1
Photo 1 (P1) Start of Temporary Diversion 1, resurface and edge and central linemarking, signage
at intersection noting detours and directions.
Photo 2 (P2) 1m width road widening both lanes, resurface and edge and central linemarking
12 | P a g e
Photo 3 (P3) 1m road widening both lanes, resurface and edge and central linemarking, Temporary
Earth Drain (100m) left hand side
Photo 4 (P4) End of Temporary Diversion 1, resurface and edge, central and intersection
linemarking.
13 | P a g e
Photo 5 (P5) Start of Temporary Diversion 2, widen road to 5m width, resurface and edge and
central linemarking.
Photo 6 (P6) Widen road to 5m width, resurface and edge and central linemarking.
14 | P a g e
Photo 7 (P7) - Widen road to 5m width, resurface and edge and central linemarking.
15 | P a g e
Photo 10 (P10) End of Temporary Diversion 2, resurface, edge and intersection linemarking only.
16 | P a g e
Photo 11 (P11) Start Temporary Road Diversion 3 Resurface road, edge and central linemarking.
Warning sign regarding upcoming tunnel height.
Photo 12 (P12) Resurface road, slow sign approaching tunnel, edge and intersection linemarking.
Detour direction sign at approaching intersection.
17 | P a g e
Photo 14 (P14) 1m road widening both lanes, edge linemarking. New Roadworks diversion back to
main road. Intersection, Edge linemarking. Direction signage required.
18 | P a g e
Photo 15 (P15) - New Roadworks diversion from main road to kampung area. Full roadworks
required. Intersection, Edge linemarking and direction signage required.
19 | P a g e