1. Purpose of Activities
a. Clearing packet loss all site under MetroE
2. General description of operation: (Include the network topology, before and after activity.):
Pemindahan Vlan ini bertujuan untuk clearing paket loss under Metro, saat ini utilisasi link Metro
Telkom sudah 82 % dan 73 %.
3. Operation schedule and description (Include the time for each step, script.):
1.
2.
3.
4.
4. Down time and impact site list (Include the exactly duration and detail impact NE list).
No BTS DOWN , beacause all site metro support VRRP, when vlans are removing in ranagg-kendari.1, node B will up because in ran-agg-kendari.2 there are same vlans as
redundancy, vice versa.
5. Potential impact ( Please mention that the potential impact for this activity )
-
Page 1