INSPECTION CHECKLIST

Project Code: IQ347-BAZYAN Combined Cycle Power Plant Project


Completion Area:

Checklist Document Name:


Lighting Circuit

Completion System:

Checklist Document Number:


IQ347-300-EL-CHL-00010
Equipment Tag Description:

Equipment Taq #:
Taq Equipment Type:

No
1
2

Description of Item
Check installation of cables and lighting fixtures are complete as per approved
drawings.
Check circuit fuse size/MCB rating correct.

Check equipment IP rating correct for the area it is located in.

Check all fixtures and JB's are securely fitted.

Check earthing complete as per design requirements.

Check all equipment tags are installed and are correct.

Check all cables installed and checklist completed.

Check to see records for Megger testing on the complete circuit from field panel
- with fixtures connections to JB's open.

OK

N/A

P/L

Remarks:

Name

Date

Signature

Owner / Owners Representative


ENKA QC

ENKA Construction