Forecast based planning

Material: EE04760
Material type: ROH
Plant: 2010

Maintained MRP type VV and Lot size EX

Forecast model D

Execute forecast through MP30

Forecast has been entered for 12 months

MD04 before MRP Run

MRP Run (for single Item- single level) T code MD03

MD04- After MRP Run

Purchase req. has been created for respected forecast date.

Forecast Based planning with SFG & FG


Material: M032805
Plant: 2010
Maintained forecasting view in material master

MRP type maintained VV and Lot size EX

Maintained forecast values in MP30

MD04- Before MRP Run

12 months forecast has been created

MRP Run through MD03

MRP has been carried out for material M032805

MD04- After MRP Run

After MRP run planned orders has been created for respect forecast date and
quantity.