RAB-Office Alt 3
RAB-Office Alt 3
Office
Kepada Yth,
Ditempat
Perihal : Cost Estimation
NO
A
1
2
2
3
4
5
6
URAIAN PEKERJAAN
PEKERJAAN PERSIAPAN & PEMBERSIHAN
Site Visit
Site Marking (Lantai satu 15x5 meter dan lantai dua 15x5 meter)
Operasional
Project Cleaning - mobilisasi pembuangan sampah proyek
General Cleaning - Clean Ditail
Mobilisasi peralatan
Fee Design (Free)
Volume
Satuan
1,00
150,00
1,00
1,00
1,00
1,00
ls
m2
ls
ls
ls
ls
HARGA SATUAN
1.500.000
1.200.000
Sub Total
B
PEKERJAAN BONGKARAN
C
1
2
3
Meja Direktur
Bahan Playwood 18mm Fin. HPL , Ukuran 1800x800x720
Sofa 3 seater (Area Lobby Receptionist)
1.500.000
1.200.000
2.700.000
6,00
12,00
30,00
m2
m2
m2
300.000
9.000.000
9.000.000
Sub Total
D
Total
1,00
unit
5.000.000
5.000.000
1,00
unit
6.300.000
6.300.000
3
4
5
6
7
8
9
10
11
12
1,00
1,00
1,00
10,00
1,00
6,00
6,00
1,00
1,00
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
1.500.000
4.600.000
6.600.000
2.000.000
4.500.000
2.000.000
2.500.000
12.000.000
6.000.000
Sub Total
E
1.500.000
4.600.000
6.600.000
20.000.000
4.500.000
12.000.000
15.000.000
12.000.000
6.000.000
93.500.000
FLOORING
-
Sub Total
F
ME & Plumbing
1,00
ls
GRAND TOTAL
Pembayaran DP 50%
Pembayaran 30 %
Pembayaran 15%
Retensi 5%
105.200.000
52.600.000
31.560.000
15.780.000
5.260.000
M Sampurno
Direktur