Professional Documents
Culture Documents
Apunte SAP Materials Management Questionarie MM PDF
Apunte SAP Materials Management Questionarie MM PDF
1
1.1
Global Settings
Currencies
Does your company use foreign currencies in
business documents? (e.g. buying products or
entering an invoice in foreign currency.)
Yes
No
Yes
No
It may be more convenient to enter exchange rates in a currency other than your local currency.
Example: Your local currency is Canadian dollars, but you want to enter USD exchange rates such as
DEM/USD, JPY/USD, and USD/CAD.
In which currency do you want to enter
exchange rates?
1.2
Local
currency
Other currency:
Units of Measure1
Do you use various different units of measure to
manage materials in your organization? (e.g.
each, pieces, kilos, pounds, gallons, boxes,)
List the units of measure you use:
Yes
No
1.2.1
No
1.3
Calendar
Do some parts of your organization branches,
departments, warehouses, production facilities,
etc. observe different public holidays than the
rest of your organization (e.g., in one
production facility, the day after Thanksgiving is
a working day, although everywhere else it is a
holiday)?
Yes, we need
different holiday
calendars because:
Yes, we need
different factory
calendars because:
Enterprise Structure
2.1
Starting with 3.1G. Available now in the Simplification Groups Pre-Configured Client.
2.2
Plants
The plant is the fundamental organizational entity in R/3 at which materials are managed. In practice, R/3
plants are often used to represent a production facility, a warehouse, or an operating site. Some reasons why
plants are important in R/3:
The quantity of inventory is tracked per plant a. (e.g. you may have 10 widgets in plant A and 7
widgets in plant B).
The value of inventory may be tracked per plant, and the accounts posted to record
transactions involving inventory may be different in each plant (e.g. each widget has a book
value of $1 in plant A, and $1.07 in plant B).
Each plant has its own data for a material concerning areas such as purchasing, sales, and
production.
Each plant has its own material requirements planning.
List the different R/3 plants you will need, and
describe briefly why each should be a different
plant
2.3
Storage Locations
Each R/3 plant may have several storage locations in which the quantities of stocks are tracked (e.g. there
are 10 widgets in plant A, 7 in storage location 1, 3 in storage location 2, and non in storage location 3).
List the storage locations each of your plants
will need:
2.4
Purchasing Organizations
List the purchasing departments in your
organization:
Are these departments responsible for all
procurement?
These departments
handle all purchases.
2.4.1
Within a plant, distinct quantities of the same material may tracked in several different storage location.
Master Data
3.1
Material Types
3.2
Material Groups
In R/3 each material must belong to exactly one material group. Groups are a rough way to classify
materials. Among other things, material groups:
Limit the scope of standard reports and analyses
Can be used as search criteria
Can restrict user access to exclude specific groups
Please list the different material groups you will
want to use:
3.3
Classification3
Do you want to use a classification system for
the materials in your organization? A
classification system can be used to find
materials with similar characteristics.
If yes, describe briefly how you intend to
classify materials:
3.4
No
Material Numbersa
When creating new materials, do you want R/3
to automatically assign numbers sequentially to
new materials, or will the end user enter the
material number?
Yes. Explain:
No
Yes
No
Yes
No
Yes, because:
Batch Management4
Is there any need to batch-manage your
materials (sub-divide the quantity of your
material into batches and track the batches
individually).
No
3.6
3.5
Yes
Also see question Material Master Data Transfer from Legacy System
3.6.1
No
Yes
No
Yes, prevent marked batches from being issued
from stock.
Yes, allow marked batches to be issued from stock,
but only after warning the user.
3.7
No
Yes
No
Yes
No
Yes
3.8
Material Statuses
Do you want to restrict how a material may be
used within the system on a per material basis?6
Example: Prevent material XYZ from being
used in purchase orders, and issue a
3.9
No
Yes
No
Yes
Order from
Remit payment to
Goods
supplier
3.10
Vendors / Suppliers
3.10.1
Vendor Roles8
For the same purchasing transaction, must you
deal with different parties for different roles?
Example: You order goods from vendor A who
then supplies the goods and presents
you with an invoice. However,
payment must be made to a different
party, vendor As headquarters.
If yes, indicate the possible different roles.
Invoice
presented by
3.10.2
Vendor Numbers9
When creating new vendors in the system, do
you want R/3 to automatically assign numbers
sequentially to new vendors, or will the end user
enter the vendor number?
3.10.3
No
Yes
If yes, explain
3.10.4
3.10.5
3.10.6
No
Yes
No
Yes
Vendor Evaluation
Skip this section if you do not perform vendor evaluations.
Which of the following criteria do you use to
compute scores for vendor evaluation?
Purchasing
4.1
Buyers12
Price
Quantity reliability
Compliance with
shipping instructions
On time deliveries
other
4.2
No
Yes
You can limit a users access to purchasing documents belonging to his purchasing group.
4.3
No
Yes
Deadline Monitoring14
Do you want to send reminders to inform your
vendor of an impending delivery?
No
Yes, reminders are sent
the agreed delivery date.
days before
No
Yes, reminders are sent when an order is
overdue
days.
4.4
4.4.1
Over Deliveries
Do you normally accept over deliveries from
your vendors? An over delivery is when the
quantity delivered is more than the (open) order
quantity in purchasing document.
If yes, you would normally (by default) tolerate
over deliveries of up to what percentageb?
Should this default tolerance be different for
different materials?
a
b
No
Yes
No, same
default
tolerance for
all materials.
Yes (explain):
4.4.2
Under Deliveries16
When the quantity a vendor delivers is less than the (open) order quantity in a purchasing document, this can
be interpreted either as a partial delivery, with more deliveries expected later or as an under delivery,
with no further deliveries expected. When the shortfall is considered an under delivery, after receiving the
goods, the system would behave as though the order items open quantity were zero.
4.5
No
A shortfall of up to
percent should
normally (by default) be considered an under
delivery; any shortfall greater than this
should be considered a partial delivery.
No, same
default
threshold for
all materials
Yes, explain:
4.6
Yes
No
Yes
Source Determination18
Do you want to manage a list of approved
suppliers for your materials? This means that if a
material is subject to a source list
requirement, you can only buy the material from
suppliers on the list.
No.
in a given plant?
across the entire
company?
everywhere except in
certain plants?
10
4.7
Quota Arrangement
Do you apportion the purchase volume of
certain materials among several vendors?
No
Yes
4.8
Types of Purchasing
Documents
Indicate which purchasing documents you plan to use in the sections which follow.
4.8.1
4.8.2
No
Yes
Purchase Requisitions
Purchase Requisition
Outline Agreement Request (a requisition for a contract or scheduling agreement)
4.8.3
Purchase Orders
Purchase Order
11
4.8.4
4.8.5
Scheduling Agreements
Scheduling Agreement
A purchasing document containing a list of hard and soft deliveries.
4.8.6
No
Yes
4.9
4.10
Purchase Requisitions
Contracts
Scheduling Agreements
12
Asset account
Project
Cost center
Sales order
Production order
Other please
specify
4.10.1
Authorization Check for G/L
20
Accounts
Do you want to prevent users from charging
purchasing document items to accounts which
they are not authorized to post?
If yes, in which purchasing documents:
4.11
Item Categories
4.11.1
Vendor Consignment21
No
Purchase Requisitions
Contracts
Purchase Orders
Scheduling Agreements
4.11.2
No
Yes
No
Yes
No
Yes
Subcontracting
Do you need purchasing transactions to support
subcontracting (i.e., you issue material
components to a vendor who processes them
into different materials for you)?
If yes, in which purchasing documents:
4.11.3
Yes
13
4.11.4
Services
Do you issue purchase orders for services?
No
Yes
4.12
Tolerance Limits for
22
Archiving
Wait at least
days after a purchasing
document has been completed before
marking the document for archiving and
deletion.
Wait at least
days after a purchasing
document has been marked before archiving
and then deleting it.
4.13
No
Yes
4.14
14
4.15
4.15.1
General
What pricing components do you use in your
purchasing documents?
No
Yes.
Describe:
4.15.2
No
Yes:
4.15.3 Taxes27
Can the materials you purchase be subject to
different tax rates depending on:
15
purchased:
the materials country and/or state of origin:
other factors:
4.16
4.16.1
4.16.2
No
What protocol:
4.17
4.17.1
Purchasing Documents
Would you like to transfer open purchasing
documents from your existing system into the
R/3 system?
If yes, indicate which types of documents and
No
Purchase requisitions:
Yes
Yes
Scheduling agreements:
16
Purchase orders:
other , describe:
Contracts:
4.17.2
Price Information
Would you like to transfer vendor / material
specific price data from your existing system?
If yes, give a rough estimate of the number of
different vendor / material prices to be
transferred:
No
Yes
Inventory Management
In this section, indicate which types of inventory transactions you will use.
5.1
5.1.1
Receipts
Goods receipt from vendor with reference to purchase order.
Goods receipt from production
Goods receipt from customer returns
Goods receipt into inspection, considered part of inventory
Goods receipt into inspection (not considered part of inventory yet, i.e., no accounting
postings)
Goods receipt from subcontracting vendor with reference to subcontracting order (consumes
components issued to vendor)
Other, describe:
5.1.2
Issues
Goods issue to customer (Sales)
Goods issue for production
Goods issue for consumption (e.g. issue to cost center)
Returns to vendor
Goods issue to subcontracting vendor with reference to subcontracting order
Goods issue to scrap
17
5.1.3
Transfers
Transfer to different company
Transfer to different plant
Transfer to different location
Other, describe:
5.2
5.3
5.3.1
Customer Consignment
Do you need to track company owned stock
held by customers (i.e., do your customers
purchase materials from you on a consignment
basis)?
5.3.2
Yes. Number of
copies:
No
Yes
No
Yes
No
Yes
No
Yes
Vendor Consignment
Do you need to track vendor owned stock held
by your company (i.e., do you purchase
materials from your vendors on a consignment
basis)?
5.3.3
No
Returnable packaging
18
5.3.4
Subcontracting
Do you need to track company owned stock
issued to subcontracting vendors?
5.4
Yes
No
5.5
No
Availability Check30
During goods issues or transfers, the system can run an availability check to ensure that the quantity being
issued is not needed for another purpose (e.g. reserved for a production order).
Do you want the system to check availability?
No
Yes, warn user if
unavailable.
5.6
Yes, because
No
Yes
No
Yes
5.7
thus bypassing the automatic account determination, and possibly overriding the account assignment made in a purchasing
document.
b
Standard priced materials only; not possible for moving average priced materials.
c
This is distinct from issuing to a reservation or to a production order, both of which may also be issues for all components of a
BOM.
19
5.8
5.9
Reservations34
Reservationsc are typically created automatically to reserve material for production orders, but end users
also create reservations manually. When the system checks material availability (e.g., for MRP, during
availability checks for goods issues, for sales orders, ), reserved materials are usually considered
unavailable.
Will you need reservations?
days
One side effect of automatic creation: a material may be stored in any storage location at a given plant, without restriction TBC.
We suggest that storage location creation be automatic for the movement type used to enter initial balance of stock from legacy
system.
c
Not to be confused with material reserved for sales orders, which uses a different mechanism.
b
20
5.10
Quality Inspection
Do you want to use the QM module to support
quality inspection of goods received into
inventory?
5.11
Yes
Document life35
How long would you like to retain in the SAP
system documents evidencing material
movements?
6
Take)
6.1
6.1.1
Cycle counting
Wait at least
days after a material
movement document has been created before
archiving and then deleting it.
No (skip rest
of section)
6.1.2
No
Yes
B
C
D
Sampling
Do you want to use sampling: counting only a
randomly selected portion of the items subject
to inventory and extrapolating the results to all
units?
No
Yes
21
6.2
Posting Tolerances
Do you want to segregate the users who post
physical inventory differences into groups
distinguished by the maximum dollar amount of
difference each may post?
If yes, indicate for each group the maximum
dollar amount per item counted that may be
posted:
Inventory Valuation
7.1
Price control36
No
Yes
Standard price
Moving average price
Different valuation methods for different
material types? Please explain:
7.2
Split valuation37
At a given plant, can the same material have
more than one valuation price?
No
Yes
7.3
Account determination38
Roughly how many different G/L accounts do
you need for inventory? (e.g., One account for
raw materials, one for finished products, )
22
7.4
Lowest-value
FIFO Valuation
LIFO
Valuation
Invoice Verification
Describe briefly how you verify vendor invoices
for goods or services purchased:
8.1
8.2
Taxes
List the types of taxes that may be appear on a
vendors invoice:
None
Tolerate quantity variance up to
dollars.
None
Tolerate price variance of up to
dollars or
percent, whichever is less.
No
Yes, block invoices if days_late *
value_of_item is greater than:
No
Yes
23
No
Yes, block
percent of all invoice
whose value is larger than
dollars
(probability of blocking an invoice with
lesser value decreases proportionally to the
value).
8.3
Document Life47
How long would you like to retain for reference
in the SAP system vendor invoices?
24
Abbreviations
AKA
Also Known As
ATP
Available To Promise
BOM
Bill of Material
EAN
International Article Number, same as Universal Product Code (UPC) in United States
EDI
G/L Account
MM
Material Management
MM SRV
MRP
PO
Purchase Order
PREQ
Purchase Requisition
QM
Quality Management
RFQ
TBC
To Be Confirmed
TBD
To Be Determined or To Be Defined
UPC
25
End Notes
1
26