Final Alignment Checklist- PMDI

Tag No
Date
Witnessed by

SN
1
2
3

Checks
Check NCR, SIMN, EPP, RFI records open items.
Motor solo run completed and accepted?
Piping are tested and cleaned, all supports are installed?

Tools Verification
Dial Indicators calibration
Inside/Outside Micrometer - calibration
Torque Wrench - calibration
Alignment Bracket 1. Quick-fit or universal brackets for small machines
2. Fabricated brackets - for larger more critical machines
3. Sag or deflection is measured and accounted
No fabricated or defective tools

Yes

No

Shims
Pump foot no shims installed
Motor foot thickness 3 - 12mm, maximum 4 pieces
Full bearing, clean, flat and pre-cut
Shim material - 300 series stainless steel

Hold down bolts


Bolts are as per drawing
No lock washer is installed
Not bolt bound with at least 1mm annular clearance
Torqued as per torque table
Jack bolts are disengaged and alignment screws are complete.

Soft Foot
Tolerance 0.05mm maximum per foot

Hub face and Rim run-out


Tolerance 0.05mm maximum

DBSE or DBHF
Tolerance 0.25mm

Actual Reading

10

11

12

13

Shaft Alignment - Pipes off


Pump and Motor are free to turn and no abnormal sound.
Tolerance 0.05mm

Piping connection - Suction & discharge flanges


1. Parallelism 0.025mm

2. Gap gasket thickness 1.6mm


3. Offset 1.5 mm
Pipe supports are in place
Correct gasket and bolts size and grade
Torqued per torque table and tightening sequence 30,60,100,100%
Piping strain - maximum movement is 0.05 mm
Shaft Alignment - Pipes on
Tolerance 0.05mm

Additional Observations