Following are the paths of soft files and brief description of the work:
No. Folders Path
Description of Job
1.
C:\Abraham\9.
Baram EOR Conceptual Study (DFES)
Front End Job\1. TP : Zahari B A Razak
Baram
- Issued structural integrity study report revision A for review on 8
EOR\Final
December 2009 (reviewed by Azam and Zahari).
Conceptual
- Structural integrity study report revision B for approval (in-progress of
Study
incorporating comments from TPs, postponed until further notice due to
uncertain prospect of Baram EOR project).
2.
C:\Abraham\2.
Laila Tie-in to Betty (BEDP-A) Conceptual Study (SSB)
Petronas Job\10. TP : Jose C Ungson JR
Laila Tiein\From Yap 26 - SSB issued latest SACS models (sent on 31 March 2010) and summary
Apr
file (sent on 6 April 2010).
- SSB issued MoM of structural meeting dated on 18 February 2010,
however this MoM was invalid due to deck layout changes (HSE issue).
3.
C:\Abraham\2.
Kumang KAKG-A Recovery of Boatlanding and Riserguard
Petronas Job\21. TP : Jose C Ungson JR
Kumang KAKGA Offshore Visit - Underwater inspection was done as per scope, except following items :
No MPI was performed on both ends horizontal brace (dented brace)
in Row B1-B2 at elevation (-) 52200 as recommended by CTE.
No CVI and MPI on hinge clamps at Leg A3, A4 and Vertical
member (VEM N52-N58) at Row B.
- Boatlanding retrieval was done and no anomalies found except one stair
landing platform.
- No official re-assessment report for KAKG-A jacket after the incident.
It is recommended to re-run all in-service analyses considering asinstalled condition of jacket.
4.
Via email.
Bumi A 20 Casing Structural Study (CarigaliHess)
TP : Timbul Suryatin
- Chan (CarigaliHess) sent structural drawings on 10 June 2010 for our
info.
- Existing slot indicated 20 conductor, CarigaliHess has been requested
to provide conductor calculation check might be done by Perunding
Worley (Carigali Hess structural engineer: Biman).
- We requested info (as per Slim Conductor spreadsheet Paul) to Chan
and he hasnt replied yet.
-

Page 1 of 2

Hand Over Notes


5.

6.

7.

8.

9.

C:\Abraham\2.
Petronas Job\14.
Drilling Casing
(VIV)

Via email.

C:\Abraham\2.
Petronas Job\27.
Diamond

C:\Abraham\2.
Petronas Job\24.
Tangga Barat

C:\Abraham\2.
Petronas Job\22.
Yetagun C

Drilling Conductor Design Work Sheet (PAFA) In-House


Design Sheet Training
TP : Timbul Suryatin
- File of Drilling Conductor Design Work Sheet - Rev Oct 09.xmcd has
been tested, however only one output file was created and the remaining
output files could not be created. Need further verification on this issue
and recheck with introductory guide from PAFA.
QUE$TOR Structural Tonnage Validation DFES study
DFES contact person : M Radzi B M Anua/Zarinah Bt Mohamed
- Some input can not be modified in QUE$TOR.
- So far no conclusion yet. It is noted that there are some discrepancies
between project database and QUE$STOR.
Diamond Conceptual Study DFES study
TP : Jose C Ungson JR
- DFCS to assist development of DBM, CTR and scope of work for ITB
package preparation. Deadline is 10 July 2010.
- DFES focal person : M Radzi B M Anua/ S M Basheer B Sulaiman
Tangga Barat TBCP-A (Module 5,6, LQ and MSF south) lifting issues
TP : Timbul Suryatin
- Module 7 lifting issue can be resolved by separate lifting of helideck
and LQ due to weight and geometry issues.
- MSF south will be lifted by providing foldable deck configuration as
agreed in meeting 11 June 2010. No weight issue.
- Module 5 and 6 can not be lifted due to geometry and weight issues.
OIC requested 300 tonnes weight reduction for module 5.
- PMT focal person : Asraf Ahmad
Yetagun Phase 4 Development SACS model review
TP : Azam B A Rahman
- Review MSF padeyes and SACS model (inplace and seismic). No
major findings.

Thank You and Salam,


Abraham Imam Muttaqin
(I will be transferred immediately to Abu Cluster & Puteri Development Project